240 likes | 265 Views
Learn how Alaska DOT&PF uses Super-Cor Bridges for high cover, heavy loads, and medium spans. Discover design specifications, FEA analysis, and case studies showcasing the benefits of Super-Cor technology. Contact Doug Myers for more information.
E N D
Alaska DOT&PF Super-Cor Buried Bridge Spans April 10, 2012 Doug Myers Greeley, CO
Where Would AKDOT Use Super Cor Bridges High Cover, Heavy Loads, Medium Bridges: 1 High Cover,the efficient profile of the Super Cor Bridge allows for higher fill heights for bridge/culvert crossings 2 Heavy Loads,the strength of the Super Cor Bridge System can effectively handle E80 Railroad Loadings, Heavy off road trucks crossings, etc… 3 Medium Bridges, Super Cor Bridge Spans allow for clear spans over 50 ft., which provide an alternative to medium span conventional bridges.
Why Would AKDOT Use Super Cor Bridges High Cover, Heavy Loads, Medium Bridges: 1 Lower Cost Mobilization,Super-Cor Bridge spans are assembled on site and can be transported on standard highway load trucks 2 Lower cost Construction,Super-Cor Bridge spans do not require large cranes or girder launching equipment to set. 3 Lower Cost overall, High cover designs result in shorter spans, smaller structures, accelerated construction.
DESIGN AND SPECIFICATIONS SNAP SHOT OF FEA ANALYSIS All buried bridge span structures should be analyzed through finite element as required by AASHTO and FHWA AASHTO LRFD Bridge Specifications
WSDOT US-2 Lowering- Spokane Super-Cor arch Design Build Staged Construction – 2 yr project 30ft span, 17ft rise, 40+ft of fill Big R Designed arch, footings, temp wire wall and permanent headwalls
WSDOT US-2 Lowering- Spokane Super-Cor Arch Design Build Staged Construction – 2 yr project 30ft span, 17ft rise, 40+ft of fill Designed footings, temp wire wall and headwalls
WSDOT SR153 – Beaver Creek Fish Passage • BEAVER CREEK PROJECT • REMOVE EXISTING RCB • REPLACE WITH CLEAR SPAN 33’ ARCH • STATE HIGHWAY 153
WSDOT SR153 – Beaver Creek Fish Passage New 33’ Span Super Cor Arch Existing 8’ X 8’ RCB
Super-Cor Technical Resource Manual available electronically Please email me and I will send you a link
Big R Bridge Thank You Big R Bridge Doug Myers dmyers@bigrbridge.com Ph: (253) 797-8293 Fax: (425) 660-6159
Fairbanks Gold Mine – Super-Cor Arch Grade Separated Crossing for new haul road. Cat 793F ~860,000 gross machine operating weight Design was for 2 loaded trucks
Fairbanks Gold Mine – Super-Cor Arch Varied width CIP concrete footing 46ft span x 20ft rise 29ft of fill at deepest point 265ft long
Fairbanks Gold Mine – Super-Cor Arch Fully assembled and ready for backfill in ~2 weeks
Fairbanks Gold Mine – Super-Cor Arch Engineered backfill Process Super-Cor never Requires thrust beams Shape was monitored – Total station control No bracing required
Fairbanks Gold Mine – Super-Cor Arch Live Load test – no movement! – Super-Cor Arch Completed structure
Port Saint Nicholas Road – POW Island – Super-Cor Arch
El Segundo – Super-Cor Arch