Public-Private Partnerships: Lessons learnt from Turkish experience

tepav. The Economic Policy Research Foundation of Turkey. Public-Private Partnerships: Lessons learnt from Turkish experience. Sibel Guven 10 October 2011, Batumi. Framework. What do we mean, when we say PPP? Any role chambers can play? Two examples from Turkey

Download Presentation

Public-Private Partnerships: Lessons learnt from Turkish experience

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. tepav TheEconomicPolicyResearchFoundation of Turkey Public-Private Partnerships:Lessons learnt from Turkish experience Sibel Guven 10 October 2011, Batumi

  2. Turkey′s experience in PPP solutions Framework • What do we mean, when we say PPP? • Any role chambers can play? • Two examples from Turkey • Organized industrial estates creating conducive local business environment. • Turkish case • Border management companies to facilitate trade. • GTI example of TOBB

  3. Turkey′s experience in PPP solutions Public-private partnerships • Problem definition • Not all public-private interaction is a partnership • Two essential prerequisites for PPPs: • Joint decision-making • Risk-sharing • Financial returnshould be lessthaneconomicreturn • Why do they matter? • The gray/intersection area between markets and states • Market failures and state failures • Key for the effective functioning of both • The complexities of the private sector development process

  4. Turkey′s experience in PPP solutions A PPP is collaboration among government and business • A collaboration, in which risks, resources and skills are shared in projects that benefit each partner as well as the community • PPPs can effectively overcome complex public policy problems by bringing together multiple stakeholders • PPPsexpand the set of resources by not only bringing together financial assets but also each partner’s skills

  5. Turkey′s experience in PPP solutions PPPsstrengthenthealignment of publicandprivatevalue • PPPs can accomplish what outsourcing cannot: creating and sustaining public value by leveraging the combined assets • The scale and sustainability of a PPP depends on the strength of the alignment of public and private value created by the project • Publicvalueaims to attain a desirable collective social outcome, • Privatevalue aims to attain or exceed privately established benchmarks, such as returns and earnings. • Dueto these differences, simply outsourcing when the government does not have the resources to perform a service becomes problematic.

  6. Turkey′s experience in PPP solutions Not everyproject is appropriatefor PPP • PPPs are appropriate under certain conditions • havingtrust and credibility between partners • having a competent and committed executive body • neither of the parties areable to complete the task on their own • creativity in handling the problems where money is not the only answer • no warped priorities of partners and unsuitable assets, such as national security • A competentuse of politicalmanagementamongpartners

  7. Turkey′s experience in PPP solutions Chambers as natural PPP catalyzers • Chambers play a very key role because of their structure • both private and public features • strong dialogue mechanisms • integral role in private sector development process • Two cases from Turkey • Organized Industrial Zones • Border Crossing Arrangements

  8. Turkey′s experience in PPP solutions Case 1: Turkey’s Organized Industrial Zone Experience • Governments cannot deliver adequate services everywhere equally and efficiently • Designating certain areas as “more equal” for improving the investment climate • 250+ Organized Industrial Zones, 70 fully operational • Started as a urban development tool in the 1960s, with a loan from the World Bank • Private-public partnerships were facilitated through the local chambers • Evolved over time to obtain regulatory oversight • The Law on OIZs was enacted in 2000

  9. Turkey′s experience in PPP solutions PPP model in Industrial Zones • A mixed structure of the Management Body • Public involvement • through local government bodies • through chambers • Private involvement • Investors of the OIZ • Areas of joint risk sharing and decision-making • Land development • Utilities provision • Regulatory authorities (licenses and permits)

  10. Turkey′s experience in PPP solutions Roles of actors in OIZs • Public support • Land expropriation • Credit for infrastructure construction • Investment incentives (tax breaks for relocation) • Private contribution • Partially or wholly financing construction and land development • Utilities provision • Management • Investment promotion • Maintenance • Regulatory support to investors

  11. Turkey′s experience in PPP solutions Performance of OIZs in Turkey Infrastructure Setup Time (days): enterprises inside and outside the OIZs Time for Getting the Permit and the License (days): inside and outside the OIZs Kaynak: TEPAV – World Bank Investment Climate Survey 2005

  12. Turkey′s experience in PPP solutions OIZs surely play a role in the diversification performance of the Turkish Industry 65 % of MENA regionsIndustrialexportsarefromTurkey.. ) Number of export items with a volume over 1 billion USD (SITCrev2 classification in 2 digits)

  13. Turkey′s experience in PPP solutions Case 2: TOBB has launched the modernization projects of border gates in Turkey • TOBB / GTI has modernized customs gates with a private-public partnership model • Easing bottlenecks at the gates • First project completed in 2003 • Now 8 gates: İpsala, Habur, Cilvegözü, Kapıkule, Sarp, Dereköy, Hamzabeyli, Nusaybin • Build-Operate-Transfer model • No burden on public budget • Effective daily management • Transfer of a modern facility to government after the concession period Goal is toimprovetradefacilitationthrough a PPP scheme

  14. Turkey′s experience in PPP solutions What do we mean by trade facilitation? • Enhancing border management facilities • Effective customs administration • ICT usage • Logistics • Institutional capacity building border crossing times Reducing inland clearance physical inspection • Upgrading and adjusting transport infrastructure • interoperability of transport systems • Multi-modal systems • Private sector capacity enhancing

  15. Turkey′s experience in PPP solutions TOBB-GTI border gate modernizations • İpsala to Greece

  16. Turkey′s experience in PPP solutions TOBB-GTI border gate modernizations • Sarp to Georgia

  17. Turkey′s experience in PPP solutions TOBB-GTI border gate modernizations • Habur to Iraq

  18. Turkey′s experience in PPP solutions TOBB-GTI border gate modernizations • Cilvegözü to Syria

  19. Turkey′s experience in PPP solutions TOBB-GTI: private management is accomplished, next step is to facilitate the public part • What is in the new gate model? • Effective daily management • User-friendly architecture • Facilitation of customs formalities • A high level of ICT use • Next step: facilitate the public part • Multiple public agency involvement • Feedback-based approach (surveys of private logistics companies) • Shorten the time & reduce cost in each step, starting from the longest • Target: full integration of all public agencies involved • Ultimate target: Fully integrated border management Private sector control Public control

  20. Turkey′s experience in PPP solutions Next Step: Fully Integrated Joint Border Gate Management • One-window for controls of both countries • First pilot: Tel Zivan border crossing between Turkey & Syria • Bolstering strategic partnership framework • Increased trade volume between two countries • Improvement in the logistics sector • 60-70 % decrease in the border waiting time - Threefold the capacity • Investment and operational costs will get significantly lower • A concrete example for the revitalization of the Modern Silk Road in the big picture

  21. Turkey′s experience in PPP solutions Takeaways from a PPP framework • PPPs arekeyto private sector development • Chambers have an essential role to play for creating conducive business environments • It is not only national • Easing bottlenecks have cross-border spillovers • It is not only public sector • Critical role of private sector in design and financing • It is not only demand-driven • Projects to create access to new markets • It is not only economic • Transport issues as a vehicle to bring conflicting parties together