Efficient Grain Facility Design & Operation By: Gregg Davidson, Owner DAVIDSON GRAIN SOLUTIONS (DGS)

PRESENTATION FOR North Dakota Grain Dealers Association 101 st Annual Convention and Industry Show January 20-22, 2013 Fargo Holiday Inn. Efficient Grain Facility Design & Operation By: Gregg Davidson, Owner DAVIDSON GRAIN SOLUTIONS (DGS). Davidson grain solutions ( dgs ).

donkor
Download Presentation

Efficient Grain Facility Design & Operation By: Gregg Davidson, Owner DAVIDSON GRAIN SOLUTIONS (DGS)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PRESENTATION FOR North Dakota Grain Dealers Association 101st Annual Convention and Industry Show January 20-22, 2013 Fargo Holiday Inn Efficient Grain Facility Design & Operation By: Gregg Davidson, Owner DAVIDSON GRAIN SOLUTIONS (DGS)

  2. Davidson grain solutions (dgs) • Troubleshooting • Plant Engineering • Master-Planning • Construction Management • Start-up & Training Maddock, ND ● Moorhead, MN ● Plymouth, MN

  3. For me: • Offer up some new ideas and some proven reminders to: • Change/improve your existing facility successfully • Build a new addition or new facility • Operate your facility better and safer • Maintain your facility better and safer • For you: • Look for new ideas that you can incorporate back home • Reinforce old ideas that are proven • Think of a question or comment • Relax and enjoy the presentation followed by questions The GOAL today…

  4. Step 1 - Conceptual Design • Step 2 - Front End Engineering Design • Step 3 - Detailed Design • Step 4 - Construction • Step 5 - Start-Up & Warranty • Step 6- Safety Devices, Operation, & Maintenance • Bucket Elevator Legs • Drag Conveyors • Belt Conveyors 6 steps to improve your facility

  5. Process flow diagram (front gate thru exit gate) • Changes to existing flow or developing new flow • Crops handled and annual bushels per crop • Total annual bushels handled • Operating hours non-harvest and harvest • In-bound truck/rail weighing and sampling • Out-bound truck/rail weighing and sampling • Receiving system(s) truck/rail flow rate • Storage type and capacities • Grain temperature monitoring • Drying system flow rate/moisture reduction STEP 1 - Conceptual Design

  6. In-house transfer flow rate • Rail load-out flow rate and allowed loading time w/0 penalty • Truck load out flow rate • Equipment by-pass/duplication options • Sanitation goals • Automation goals • Operator control room scheme • Special requirements for inspectors and required certifications • Other key business goals • Other key customer goals • Interference with existing operations • Future growth considerations • Cadillac or nice Chevrolet ($$$) • Potential concerns by neighbors and public Conceptual design – page 2

  7. Site plan (outside front gate thru outside exit gate) • 3D for aerial perspective • 2D for details • Existing structures, roads, and landmarks • Off-site improvements (drainage, public roads, traffic flow) • Site grading and drainage • Utilities (electrical, gas, water, sewer, fire, communications) Conceptual Design – Page 3

  8. Roads and parking (traffic flow, customers, employees, surfaces) • Emergency vehicle access • Structures • Railroad • Landscape areas • Low maintenance areas • Site security (lighting, gates & fence, guard shack, public locks) • Other key business and customer goals • Construction staging area • Interference with existing operations • Future growth considerations • Cadillac or nice Chevrolet ($$$) • Potential concerns by neighbors and public Conceptual design – page 4

  9. Organizational chart • Show owners, designers, contractors, & subs • Show overall responsibilities for each • Show method of project delivery for each • Design – build • Design – bid - build • Consider shared document website for info sharing • Project schedule • Weather impact • Project budget • Weather impact Step 2 – front end engineering design

  10. Permits • City • County • Watershed district • State • Federal • Railroad • Utilities (electrical, gas, water, sewer, fire, comm.) • Determine electrical classification for all areas Front end engineering design – page 2

  11. Land ownership • Clear title • Easements • Site survey report • Existing topography, buildings, roads, and landmarks • Geotechnical report • Locate multiple soil borings directly under key areas • Estimated total soil settlement • Estimated differential soil settlement • Estimated water table during construction & operation • Determine geotech’s ability to perform material testing Front end engineering design – page 3

  12. Operational safety • Explosion prevention and venting • Fall protection guarding • Running equipment guarding • Secondary egress • Others specific to the facility • Determine construction management needs • Evaluate internal skills, experience, and time available • Consider outside help for: • Conceptual and Front End Engineering Design • Bid package development • Over-sight of Construction, Start-Up, & Warranty Front end engineering design – page 4

  13. Civil package • Site plan • Railroad plan • Structures and machinery package • Process flow diagram • General arrangements • Concrete structural • Steel structural • Miscellaneous • Equipment list • Electrical package • Controls package Step 3 – detailed design

  14. Construction safety • Excavations • Fall protection • Ladders and scaffolding • Crane lifts • Electrocution • Personal protective equipment • Other hazards specific to the project Step 4 - construction

  15. Construction contract • Format (design-build, build only) • Project schedule • Responsibility for final engineering • Construction safety • Responsibility for material testing and review • Insurance and bonding • Retainage • Liquidated damages • Start-up • What triggers final payment? • Warranty Construction – page 2

  16. Owner mobilization • Pre-mobilization meeting (per organizational chart) • Construction staking • Temporary electrical service • Temporary water service (fire protection?) • Temporary communications • Contractor mobilization • Critical meetings and inspections • Daily, weekly, monthly • Progress photos • Final punch list (substantial completion) Construction – page 3

  17. Operator training materials • Hard copies & electronic version of manuals • Operator training • Start-up plan to SAFELY meet phased goals • Process equipment • Process safety devices and instrumentation • Dust collection balancing • Building-related devices and instrumentation • Engineered silo/bin loading plan Step 5 – start-up & warranty

  18. Final written acceptance by Owner • Contractor de-mobilization • As-built documentation • Hard copies & electronic version of as-built drawings & specs • Post-project de-briefing meeting • Problems and praises • Future maintenance and project needs • Potential reference and marketing testimony • Issue final payment • Warranty period (solve problems together) Start-up & warranty – page 2

  19. Recommended safety devices • Speed monitor on boot shaft for alarm and shutdown • Belt alignment switch on each side of boot • Bearing temperature sensor on each side of boot • Belt alignment switch on each side of head • Bearing temperature sensor on each side of head • Plug switch at leg discharge • Guarding over all exposed shafts • Explosion panels Step 6 – Bucket elevator Legs

  20. Operation • Install outside if possible • Maximum 650 feet per minute (fpm) belt speed = 7mph • Wear liner selection based on crops, bushels, & years • Spout feeding leg inlet plays huge role in filling cups • Height of leg inlet with respect to boot shaft is critical • Class II drive with backstop capable of starting leg under full load • Reduced voltage starter (soft start) capable of starting leg under full load Bucket elevator legs – page 2

  21. Maintenance • Replace head pulley lagging if belt will not track or crown (1/8” per foot from edge to center of pulley) is gone • Belt replacement guideline based on 1.5% stretch • Example: 100 ft tall leg = 200 ft belt x 1.5% = 3 ft = 1.5 ft take up • Replace bearings based on frequent inspection • Watch/listen for changes Bucket elevator legs – page 3

  22. Recommended safety devices • Speed monitor on tail shaft for alarm and shutdown • Slack/tight chain switch on tail • Plug switch at conveyor discharge • Guarding over all exposed shafts Step 6 – drag conveyors

  23. Operation • 150 to 180 feet per minute (fpm) chain speed = 2 mph • Wear liner selection based on crops, bushels, & years • Class II drive capable of starting drag under full load • Reduced voltage starter (soft start) capable of starting drag under full load Drag conveyors – page 2

  24. Maintenance • Replace bearings, sprockets, and chain based on frequent inspection • Watch/listen for changes Drag convey0rs – page 3

  25. Recommended safety devices • Speed monitor on tail shaft for alarm and shutdown • Belt alignment switch on each side of tail • Bearing temperature sensor on each side of tail • Belt alignment switch on each side of head • Bearing temperature sensor on each side of head • Plug switch at conveyor discharge • Guarding over all exposed shafts Step 6 – belt conveyers

  26. Operation • Maximum 700 feet per minute (fpm) belt speed = 7 mph • Wear liner selection based on crops, bushels, and years • Spout feeding the loader plays huge role in feeding belt • Class II drive capable of starting conveyor under full load • Reduced voltage starter (soft start) capable of starting conveyor under full load • Side wall inspection doors recommended Belt conveyers – page 2

  27. Maintenance • Inspect tail section often for grain re-loading • Replace head pulley lagging if belt will not track • Belt replacement guideline based on 1.5% stretch • Replace bearings based on frequent inspection • Watch/listen for changes Belt convey0rs – page 3

  28. Thank you and Go Bison! Questions? Comments? Efficient Grain Facility Design & Operation By: Gregg Davidson, Owner DAVIDSON GRAIN SOLUTIONS (DGS)