1 / 24

Proposed full upgrade of the L1CTT/DFE for Run2b

Proposed full upgrade of the L1CTT/DFE for Run2b. Meenakshi Narain Boston University. Outline: Proposal Reviewers comments and responses Schedule Cost. Groups. Simulation and Algorithm development: Kansas: Graham Wilson, Carsten Hensel Manchester: (Liang Han), Terry Wyatt

dudley
Download Presentation

Proposed full upgrade of the L1CTT/DFE for Run2b

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proposed full upgrade of the L1CTT/DFE for Run2b Meenakshi Narain Boston University Outline: Proposal Reviewers comments and responses Schedule Cost

  2. Groups • Simulation and Algorithm development: • Kansas: • Graham Wilson, Carsten Hensel • Manchester: • (Liang Han), Terry Wyatt • Notre Dame: • Mike Hildredth • Hardware: • Boston University: • Meenakshi Narain, Eric Hazen, Ulrich Heintz, Shouxiang Wu • FNAL: • Marvin Johnson, Stefan Gruenendahl, Jamieson Olsen

  3. Run IIa Run IIb Physics Motivations • In Run IIa and RunIIb, the L1 Track Trigger Provides: • CFT tracks for L1Muon Seeds • High pTisolated track trigger capability • CFT tracks +CPS clusters  embryonic electrons • Found tracks for STT • As instantaneous luminosities hit 1e31, the rejection for L1CTT drop drastically. • Accomplish high eff with low fake rates using the full granularity of the CTT.

  4. L1CTT architecture • A multistage system • Analog Front End (AFE): • Signals from the tracker • Mixer • Sort signals in trigger sector wedges • Digital Front End (DFEA): • Track Trigger logic • Octant (CTOC) • Combine track information from several DFE boards • CTTT • Construct track trigger terms • Trigger Manager • Construct 32 AND/OR terms used by the L1 Trigger Framework in forming the trigger decision

  5. L1CTT architecture • The approved upgrade: • Replace Digital Front End daughter boards (DFEA): • Need to fit 3-5 times more equations • Rebuild these cards using larger FPGAs • Use XC2V6000 Chip with 6M system gates

  6. Lessons from Run2a commissioning • Current “approved plan” • upgrade of the DFEA daughter boards. • Provide a 5x increase in available logic resources. • With the experiences over the last year while commissioning the present Run2a L1CTT system a few very important issues have surfaced: • Lack of extensive testability of the input and output information from the DFEA • Excessive Firmware download times • Clock and SCL signal distribution (dependent on upstream info) • A shortage of spare backplanes (there are none)

  7. The Proposal • In order to add testability to the system, one needs: • A new motherboard (daughterboard – to a less extent) design. • Improved diagnostics: input and output buffers, and L3 capability. • To alleviate colossal download times we need: • A new DFE crate controller with a faster connection to the D0 online computers. • A new DFE backplane design Utilize this chance to put the cables to the back. • No transition boards. • Also an independent SCL/clock distribution • This decouples us from upstream downtime issues • Detailed specifications of the boards are being developed – follow links through the Run2 trigger web page

  8. Installation & Commissioning • The proposed scheme is driven by the desire to enhance testability and reliability of firmware downloads. • Eases Installation and commissioning • Plan to run on a partial crate of the new system on the platform in parallel with the existing DFEA using LVDS splitters • Key to successful commissioning of the new system • Advantages: • Can assemble the whole crate outside of the collision hall • Extensive testing of the entire chain possible before putting in collision hall • Enhanced testing capability • Use Run2a Data derived test vectors to verify • Take out the old crates (2 of them) and replace them with new ones • Use the existing Run2a tools used for commissioning • Low level changes will be transparent at user level

  9. Rescope Review • Review held on April 5th, 2004 • Reviewers: • Darin Acosta (UF), John Anderson, Bill Freeman (Fermilab) • Charge to the Committee: • Total cost of the new CTT project. • Is the total cost well estimated and does it include all necessary cost for materials and labor? • Contingency: • What is the uncertainty of the cost estimate (i.e. how much contingency should be assigned to the total cost of the project?) • Schedule of the new CTT project: • Is the schedule reasonable and attainable? • Milestones and tracking. • Are there sensible milestones in the schedule that will allow management to track the progress of the project? • Technical Feasability: • Is the project feasible as described and does it optimize installation and commissioning time? This is not a detailed technical review – more of an overall “sanity check”.

  10. Responses to Review Comments • DFEA chip decision, merging MB/DB • Already received gift from Xilinx for all XC2V6000 • Start with merged scheme (shorter prototype cycle) and split later on if needed • 48V power distribution system: • Q: “The risk is that the system may induce EMI effects to other sensitive D0 electronics A: In the last 2 months done various tests – no affects seen on the calorimeter. Add shielding as a precaution.

  11. Responses to Review Comments • Crate Controller: • Question design choice, suggest to use commercial solutions A: We had explored commercial off the shelf choices. • These solutions will force use of either a VME or PCI interface, adding complexity to the DFE as well. • Radiated EMI from the various busses on a commercial board presents a risk to cal electronics • Considered a hybrid solution for the CC using commercial VME module like L3 single board computer and a PMC for SCL. • Rejected: • as simple hardware transforms into a large software project (including a new driver). • Software to implement SCL interrupts is a good bit of effort. • 16 MHz VME clock would require noise shielding. • Our design is based on the CMS/OSU design – a commercial solution • Send raw Ethernet frames over a gigabit link • Reuire PC/Linux software effort (drivers available) • Use OSU’s VirtexII Pro rocket I/O transceiver (dedicated EE at OSU) • Also add bi-directional parallel port interface to board.

  12. Responses to Review Comments • DSAT: DFEM/DFEA tester • Question investment of resources in this project, suggest this be merged into DFEM itself. And include SCL on the tester. A: • We need a tester somewhere. • In the two weeks after the review we invested in a tester schematic. We are holding sending it for layout. • However, we do prefer a standalone tester – as something is needed to test/ power-up DFEA/DFEM prior to the setup at FNAL is put together. • We feel this is not a huge resource investment, while merging it with DFEM/DFEA will put unnecessary load on the one engineer doing the DFEA work and may delay the DFEA (which we want to avoid at any cost).

  13. Responses to Review Comments • Test Setup: • Q: A lot of value put it in the in-situ tests of the upgraded L1CTT system during this year’s shutdown, need to develop contingency plans to test outside of the collision hall in case this is not met A: • We do have a plan for test-setup outside the collision hall • For the Fall 2004 shutdown all we really need to achieve is installation of a new crate with power supply and backplane, the LVDS cable extensions and the splitters. • Crate controller and DFEA prototypes can be added (and replaced) during shorter accesses later. • However, we still know from experience with the current system that there is no replacement for testing in situ, especially with regard to timing.

  14. COST & SCHEDULE

  15. Schedule • Aggressive but manageable schedule • Needed to start the project at yesterday’s timescale • Timing of anticipated “Fall Shutdown” – and “CTT slice test” a critical ingredient for ensuring success

  16. Milestones Milestone Date Backplane and Crate Controller

  17. Milestones Milestone Date DFEA/DFEM/ FPGAs Production

  18. Fall 2004 Slice Test • Fall 2004 shutdown: • Aug 23rd and lasts 13 weeks. • During this time plan to run a partial crate of the new system on the platform in parallel with the existing DFEA using LVDS splitters. • Plan to assemble the partial test crate prior to the shutdown. • Extensive testing of the entire chain possible before putting in collision hall

  19. Readiness for Slice Test • Crate Controller:

  20. Readiness for Slice Test • Backplane:

  21. Readiness for Slice Test • Optical DCL/LVDS Splitters:

  22. Readiness for Slice Test • DFEA/DFEM:

  23. L1 CTT Cost Change

  24. L1 CTT Cost Change • Total Cost change to DOE MIE: (escalated, burdened, etc) Original Revised Change Cost Cont. Cost Cont. Cost Cont $361k $155k $717k $186k $356 $31k Total difference in cost + new contingency estimate is: $387k This cost will come from the management reserve. • Lowers the contingency on the total project cost from 33% to 30%. • Have not touched money earmarked for AFE II upgrade

More Related