An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Approaches to Historic Bridge RehabilitationCase Study #2 Lake Park North Lion Bridge Rehabilitation Milwaukee, Wisconsin Darrell Berry, PE, SE

  2. Case Study #2 Lake Park North Lion Bridge • Steel arch with concrete deck • Originally built in 1896, narrowed in the 1960s • Length: 90 feet; Width: 10 feet clear • Single span steel arch • Design Live Load: 85 psf or 15,000 lb. vehicle North Lion Bridge Lake Michigan Milwaukee, Wisconsin

  3. Case Study #2 Lake Park North Lion Bridge Rehabilitation • Owner: Milwaukee County Department of Parks, Recreation and Culture • Design Engineer: Mead & Hunt, Inc. • General Contractor: Vista Design & Construction, LLC • Project Cost: $1.6 Million • Project dates: started Feb 2009, completed Oct 2009.

  4. Case Study #2 Significant Issues Associated With Project • Arch Structure • Railing • Stone Facing on Abutments • Lion Statues

  5. 1. Steel arch structure, including bearings & concrete deck

  6. Case Study #2 How Arch Issue Was Resolved • Deteriorated structural steel was removed and replaced, with details matching original. • Bearings were removed and replaced. • Concrete deck was removed and replaced • Precast concrete panels • Cast-in-place concrete surface

  7. Case Study #2 2. Metal Railings

  8. Case Study #2 How Railing Issue Was Resolved • Railings were removed from bridge and delivered to a fabrication shop. • New finials were added and made larger to fill the openings. • Edges were welded to uprights. • Railings were painted and reinstalled.

  9. Case Study #2 3. Stone facing on abutments

  10. Case Study #2 How Stone Facing Issue Was Resolved • Missing stones were replaced with matching stones. • Entire abutments were tuckpointed, with color to match existing. • All surfaces were gently cleaned to remove moss and dirt.

  11. Case Study #2 4. Lion Statues

  12. Case Study #2 How Lion Statue Issue Was Resolved • 110 year old statues were in good condition with minimal graffiti. • Cleaning used a gentle process with water and light power wash. • Digital 3D image will be prepared in near future.

  13. Case Study #2 Lessons Learned/Conclusions • Rehabilitated bridge is part of beloved, historic park. • Bridge and lion statues are enduring symbols of a celebrated Milwaukee landmark. • Cooperation and collaboration between all parties lead to an extremely successful, award-winning project.