310 likes | 574 Views
Case 1. – Verification of the Inception Report. Please a ssess the Inception report in terms of: Activities , Output Resources and Timinig by using the following distributed documents: Extract from the Terms of Reference Extract from the Technical Proposal
E N D
Case 1. – Verification of the Inception Report Please assess the Inception report in terms of: • Activities, • Output • Resources and • Timinig by usingthe following distributed documents: • Extract from the Terms of Reference • Extract from the Technical Proposal • Extract from the Inception Report
Case 1. Findings Activities:TP 2. Strategy/Activities Proposed vs IR 3.3 Expected Results • New activity included for project management • Assessment: • Not in contradiction with ToR • Does not modify objectives or purposes • Might cause problems in input allocation – KE days should be reduced on other activities
Case 1. Findings Activities: • Activity 2.7 deleted • Assessment: • No related output mentionned in ToR • Activity specified in ToR and Technical Proposal • Should be re-included
Case 1. Findings (Cont’d) Output: • Missing outputs: • R.1: ‘Necessary capacity for project monitoring and reporting ensured’; ‘Min. 300 OTS checks and field visits’; • R.2: ‘Management, … support to final beneficiaries’; ‘Project management capacity of beneficiary institutions improved’ • R.3: ‘Operation Generation capacity’; ‘More demand oriented operations designed’
Case 1. Findings (Cont’d) Output: Assessment • Missing from TP too • No clear link to Activity in ToR • Need to identify activities to outputs explicitely
Case 1. Findings (Cont’d) Output: • Activity 1.3: ‘organizational structure revised’ (TP) vs ‘support ensured’ (IR) • Assessment: • No such output in ToR • Revision has been proposed not simply support • Beneficiary can refer to TP
Case 1. Findings (Cont’d) Output: TP 2. Strategy/Activities Proposed vs. IR 3.3 Expected Results • Activity 1.10 4 study visits instead of 5 • Activity 1.11 6 internship instead of 5 • Assessment: • ToR specifies, should be aligned, but there is room for consideration if no overall cost reduction can be demonstrated
Case 1. Findings (Cont’d) ResourcesTP 2. Strategy/Input Table vs. IR 7. Resources • KE days reduced in SCs 1.1 – 1.3 and increased in Project management and Closure phase, total (300) remained unchanged • LTNKE days decreased in SCs 1.1, 1.3, and 1.4., total reduced from 700 to 550 • ONKE days increased in SCs1.2 – 1.4 from 700 to 1000
Case 1. Findings (Cont’d) ResourcesTP 2. Strategy/Input Table vs. IR 7. Resources • Assessment • Contribution of KE reduced in SCs – shift to project management from technical content • Replacement of KE and LTNKE involvement by ONKE – danger of shift from senior to junior expertise • Decrease of KE and LNKE input in SC 1.1 is not compensated, overall input reduced • Overall increase in 1.2 shall be justified
Case 1. Findings (Cont’d) Time schedule (Cont’d) Assessment • Extended duration of activities as a possible consequence of shift in experts’ structure (see assessment of input) • Danger of shift of milestones towards the last phase of the project • Completion of 1.4 RCOP evaluation due to delay coincides with 1.5 RCOP revision
Case 2. – Verification of the Inception Report Please assess the Activities undertaken in inception period (both inception and non-inception) in terms of • Activities, • Output • Resources and • Timinig by using the distributed documents: • Extract from the Technical Proposal • Extract from the Inception Report
Case 2. Findings TP 2. Strategy/Input Table vs. IR 7. Resources vs. IR 4. Inception Activities + IR 5. Non-inception Activities Resources: • KE inception activities: 33 in IR 4-5, instead of 30 in IR 7 (and TP Input Table) • Assessment: Inception activities shall be aligned with Inception Report Chapter 7. Resources • KE overall activities 52 for 2 months (less potential working days in 2 months) • Assessment: Inception activities shall be in line with working day numbers
Case 2. Findings (Cont’d) Resources/timing • No spending of NKE mandays under SC 1.3 • Disproportionately high spending of NKE mandays under SC 1.4 (25%) • Activity 2.2 has not started (planned start month: 1) • Assessment: find justification in Inception Report text under Key Issues, Review of Risks, or Changes in the Workplan • If delays not justified, request for contingency plan • if overspendings not justified, consider to reject
Case study3 – Verification of activities reported in the InterimReport 1. Assess Interim Report’s Chapters 3. a) ‘Major activities undertaken’,Chapter 4. a) ‘Milestones delivered’and 6. ‘Resource Management’ in termsof: • Activities • Outputs • Resources • Timing by using the following distributed documents: • Extract from the Terms of Reference • Extract from the Inception Report • Extract from the Interim Report Assumption: all the modifications discovered in Inception Report have been approved, except for Activity 2.7 that has been re-included 2. List the supporting documents that you consider necessary to request from the Consultant
Case 3. Findings Activities: • New activity introduced: ‘3.5 Providing on the job support to final recipient institutions on building operation generation facility’ • Assessment: justified, since output specified in ToR; overall input balance shall be considered
Case 3. Findings Activities: • Activity ‘2.1 Training and support needs analysis local stakeholders’ deleted, however started in Inception phase • Assessment: • probably cancelled; • ToR does not specify as activity nor as output; • Beneficiary can refer to TP
Case 3. Findings Output: • Activity 1.1212 training programmes, instead of 15 specified in TP and confirmed by Inception Report • Assessment: • Not in contradiction with ToR (‘minimum 12’) • Beneficiary can refer to both TP and Inception Report
Case 3. Findings (Cont’d) Resources • No unput reported for SC 1.2 • Assessment: probably a mistake, shall be corrected • Over-spending of KE days in SC 1.3 (22 instead of 20) • Assessment: correction is needed, if no modification has been approved earlier; but: what if timesheets already approved?
Case 3. Findings (Cont’d) Resources • Relatively high spending of mandays under SC1.1 (duration of activities in Incept. R. proportion: 17%; days reported: 25%) (Formula: Months to be spent: 17 / Duration months: 99 vs. WDs used: 107 / Total WDs: 430) • Disproportionately high spending of mandays under SC 1.4 (duration of activities in Interim R. proportion: 8%; days reported: 40%) • Relatively low spending of mandays under SC 1.3, see also Inception finding (duration of activities in Interim R. proportion: 12%; days reported: 5%)
Case 3. Findings (Cont’d) Resources • Assessment: find justification in ‘Current and anticipated problems’ chapter • If low use of resources not justified, request contingency plan • If overspendings not justified, consider to reject
Case 3. Findings (Cont’d) Timing • Activities not started: • 1.1Support in DIS processes(planned start month: 5) • 1.8 Support/coaching to PSCs and SMCs (planned start month: 5) • 2.2 Designing Training Programmes (planned start month: 1), see also Inception report finding
Case 3. Findings (Cont’d) Timing • Activities not started: • 2.5 Preparation of training materials (planned start month: 3) • 2.6 Ensuring support to the final recipients for the technical implementation (planned start month: 5) • 3.1On the job support for technical documents(planned start month: 4)
Case 3. Findings (Cont’d) Timing • Activities not started: • Assessment: • delays shall be justified in chapter on Current and anticipated problems and remedial actions foreseen • Also see high spending of resources in SC 1.4 despite of delay of Activity 3.1
Case 3. Findings (Cont’d) Timing • Activity started earlier: • 2.3 Organization training programmes • Assessment: trainings organised before design of training programmes (Activity 2.2)
Case 3. Findings (Cont’d) • Supporting documents (for completed actions): • Act. 0.1: Paper on situation analysis • Act. 0.2: Training Needs Assessment approved • Act. 0.3: Inception Report approved • Act. 1.3: Report on revision of organizational structure, roles and responsibilities • Act. 2.1: Support and Training Needs Analysis approved
Case study4 – Verification of planned activities in the Interim Report Assess Chapter 5. ‘Planned major activities’ of the Interim Report in termsof • Activities • Outputs • Resources • Timing • by using the distributed documents: • Extract from the Terms of Reference • Extract from the Inception Report • Extract from the Interim Report
Case 4. Findings (Cont’d) Time schedule: • Reduced duration compensates delay on activities 1.8, 2.6 and 3.1, - original deadlines kept • Delay, but completion planned in RP2 for activities: 1.1, 2.2 and 2.5 • Assessment: delays are planned to overcome in Reporting Period 2
Case 4. Findings (Cont’d) Resources • Input aligned with time proportion for SCs 1.1 – 1.3 • Overspending rate increased (19% vs 80%) in SC 1.4 • Assessment: re-allocation has to be considered for SC 1.4
Final Conclusions • Stick to Activity structure of ToR • If modifications are needed, do it under sub(-sub)-activity levels • Avoid input micro-management • Find logic between input and output delivered • Assess duration changes of activites • Use tables!