1.8.1.3 DCLL PbLi Loops Design and Fabrication Plan and Cost. B. A. Pint ORNL. Progress to date. First iteration based on SNS experience Total: $4.2 million unburdened Material: $1.95 million Design: $1.87 million Information received Nov. 29. Assumptions. No contingency
E N D
1.8.1.3 DCLL PbLi Loops Design and Fabrication Plan and Cost B. A. Pint ORNL
Progress to date • First iteration based on SNS experience • Total: $4.2 million unburdened • Material: $1.95 million • Design: $1.87 million • Information received Nov. 29.
Assumptions • No contingency • One unit (no mockup) • Mockup another ~$2 million (based on guess) • Tubing based on 316SS - similar Fe-9Cr • Construction labor: $35/hr • Includes dye testing, weld radiography…
Biggest ticket items • Large uncertainty • $1,870,000 for design • $500,000 pump + expansion tank • $400,000 heat exchanger
To Be Done • Integrate current information into schedule • Mockups? • Line items listed for: • Administration/Integration • R&D • Engineering (Design & Title III) • Fabrication/Procurement • Assembly/Installation • Need definitions for some of these
PbLi Breeder Coolant Loop Primary He coolant Line Tritium Extraction Pressure Control Unit Cold Trap Unit Dump Tank Expansion Tank PbLi-He heat exchanger Sump Pump Tank Rupture Disk