380 likes | 411 Views
Power Quality Impacts of Distributed Generation. Roger C. Dugan Sr. Consultant Electrotek Concepts, Inc. Tennessee Tech. February 9, 2004. Introduction. Renewed interest in Grid-connected DG Utility Perspective T & D Capacity Relief Hedge against high market prices End User Perspective
E N D
Power Quality Impacts of Distributed Generation Roger C. DuganSr. Consultant Electrotek Concepts, Inc. Tennessee Tech. February 9, 2004
Introduction • Renewed interest in Grid-connected DG • Utility Perspective • T & D Capacity Relief • Hedge against high market prices • End User Perspective • CHP and Improved Reliability • Incentives from Utility • Commercial Power Producer • Sell kWh or “ancillary services” Electrotek Concepts, Inc
Emphasis of This Presentation • Units connected to distribution (MV) • Typically < 10 MW • Commonly 1-2 MW • Frequently owned by end user • Impact of these units on Power Quality • Operating conflicts • We will look at a few of the many … Electrotek Concepts, Inc
Typical Overcurrent Protection Electrotek Concepts, Inc
Only One Device Has to Operate OperatingDevice Fault Current Electrotek Concepts, Inc
Transmission Fault Protection Multiple Sources Two Devices Must Operate to Clear Fault Electrotek Concepts, Inc
LV Network Systems Electrotek Concepts, Inc
Utility Fault Clearing • Due to cost, distribution systems are designed expecting only one source of fault current • Only one device has to operate • DG must disconnect to allow utility fault clearing process to continue • This is the source of most operating conflicts Electrotek Concepts, Inc
Reduction of Reach Utility relays and DG relays may not know anything is wrong. Electrotek Concepts, Inc
Reduction of Reach • More of a problem at peak load • When peaking units are likely to be connected !! • More of a problem for high resistance faults • Longer fault detection times Electrotek Concepts, Inc
Reclosing • Most faults are temporary • Reclosing is prevalent in North America • Reclosing Interval: 0.2 – 5 sec • “Instantaneous” < 30 cycles Electrotek Concepts, Inc
Reclosing, cont’d • If DG does not get off, two bad things could happen: • DG is damaged by the reclose • Shafts • Winding damage • Fault is not cleared • Reduced reliability • Damage to utility system Electrotek Concepts, Inc
Reclosing DG Must Disconnect Here Electrotek Concepts, Inc
Instantaneous Reclosing • Utilities use this for PQ concerns • Increases the probability that DG will not disconnect in time • Makes it almost a certainty that some won’t • If 1-2 sec, most operations will be easily detected by DG protection • Some utilities use 5 sec reclose on feeders with DG Electrotek Concepts, Inc
Voltage Drop After Fault OOPS! Electrotek Concepts, Inc
Low Voltage After Interruption • A problem when there is a fault at peak loading • When peaking DG is likely to be on !! • This is often the most limiting condition for how much DG can be accommodated without change • Particularly on rural feeders • 500 – 1000 kW Electrotek Concepts, Inc
Ferroresonance Sometimes Conflicting Interconnect Requirements Collide …
Ferroresonance DG Required to have separate Transformer and disconnect at first sign of trouble G 2) DG breaker detects negative sequence and trips leaving transformer isolated on cable capacitance with no load/generation 1) Fuse blows or switch opens 3) Ferroresonance develops Electrotek Concepts, Inc
Ferroresonance Electrotek Concepts, Inc
Ferroresonance Waveform Electrotek Concepts, Inc
Arrester Duty for SLG Electrotek Concepts, Inc
Varying Generation Example 10 000 ft 10 000 ft 20 000 ft 115 kV 12.47 kV Regulator 500 kW 1000 kW 600 kvar Wind Gen 336 MCM ACSR 8 MW (Untransposed) Unbalanced impedances Rapidly-varying “load” Electrotek Concepts, Inc
Varying Generation 1-Phase Regulators Regulator Operations Electrotek Concepts, Inc
Grd Wye-Delta Connection • Some claim this is the best way to interconnect DG • Same way as nearly all central station generation is connected • However, most utilities don’t allow this connection on their system. Electrotek Concepts, Inc
Wye-Delta Connection Electrotek Concepts, Inc
Problems with Wye-Delta • Increases ground fault current • Interferes with coordination • Faulted Circuit Indicators get fooled • Transformer subject to failure • Special design and/or neutral reactor • Utilities often discourage “Specials” Electrotek Concepts, Inc
On Wye-Wye • Most common U.S. connection • Generally well behaved • Does not block Triplen Harmonics • Leads to “Harmonic Surprise” when many machines paralleled with utility system • Also occurs with Delta-Wye • 2/3 pitch machines lessens the impact Electrotek Concepts, Inc
Conclusions • Interconnected DG likely to increase • DG must adapt to Distribution protection system • Too much infrastructure already in place to overhaul the system to better accommodate DG • Who would pay for it? Non-participating ratepayers? Electrotek Concepts, Inc
Conclusions • DG impact on Power Quality • Often good for individual end users • Largest gainers: Those with high-value product that suffer sustained interruptions • But, should not expect power quality improvement in all areas • Maybe slightly negative for utility • Contributes to operating conflicts • Can we see it in the Average indices? Electrotek Concepts, Inc
Conclusions, cont’d • Revisit Overcurrent Protection • Utilities may have to change some practices • Instantaneous reclosing ? • Use of line fuses • Tradeoffs for Transformer Connections • WYE-Delta good for DG but not for ground fault coordination • Special engineering req’d for some DG application. Electrotek Concepts, Inc
Despite These Conflicts … • DG can almost always be successfully engineered • Larger conflict may be over who pays • Some long-standing utility practices may have to be changed Electrotek Concepts, Inc
How Much DG ? • What is the “No Changes” “Penetration Limit” ? • Typical: 15% of feeder capacity • 5% - 10% if Rural Electrotek Concepts, Inc