Biogas FuelledCogeneration Systems Jan Buijk 416-804-2203 buijkjan@ddace.com
Separator sheet • Use this range of background colors to introduce new sections Construction Phase
Farmer’s Responsibility during Construction Phase • Award contract & issue a down-payment • Coordinate activities of engineering firm, equipment supplier(s) and installation contractor • Ensure the utility interconnection approval is in place (or delegate to engineering firm) • Review drawing submittals (or delegate to engineering firm) • Ensure Technical Instruction documents are followed
Responsibility of the Equipment Supplier During Construction Phase • Confirm acceptance of purchase order • Place equipment order with factory and outside suppliers (if applicable) • Organize internal kick-off meeting
Activities that take place during Construction Phase • Project kick-off meeting with customer • Provide detailed design drawings and technical details as required to complete system design and integration • Site visit(s) during construction period • Meetings with engineering firm/installation contractor/electric utility as required to address equipment performance and other details • Site audit prior to start-up and commissioning • Identify deficiencies (equipment / installation) • Installation start-up • Project hand-over to customer
Potential Problems during/after Construction Phase • Utility interconnection approval • Coordination of site activities • Under-sizing of cooling systems (radiators/ventilation), gas piping, coolant piping, heat exchangers etc. • Control system details – interface with balance of plant equipment and services • Implementation of high speed internet access for remote monitoring system • Gas quality / composition
Sulfur Content • Sulfur • H2S < 500 mg/10 kWh • Standard maintenance schedule • H2S < 2000 mg/10 kWh • „modified“ maintenance schedule • acidification of oil • reduced Oil lubricity • SOx + H2O corrosion • deposits in exhaust gas heat exchanger, when temperature is below dew point Sulfate deposits exhaust gas temperature below dew point
What is the Timeline • Kick-off Meeting: 3-4 weeks ARO (after receipt of order) • Drawing submittal: 60 days ARO • Equipment delivery: 6-7 months ARO • Start-Up: 9-12 months ARO • Hand-Over: 10-12 months ARO