Status of the LHC Project Luciano MAIANI. CERN Council June 21, 2002. 1. LHC progress since October 2001. Contract for Cryogenic line: adjudicated (Nov. 2001) Signed Super-conducting cable production: Reviewed by external Panel in Feb. 2002 (all firms interviewed)
E N D
Status of the LHC ProjectLuciano MAIANI CERN Council June 21, 2002
1. LHC progress since October 2001 • Contract for Cryogenic line: • adjudicated (Nov. 2001) • Signed • Super-conducting cable production: • Reviewed by external Panel in Feb. 2002 (all firms interviewed) • New production schedule defined and agreed • Contracts for the assembly of the main dipoles: • Adjudicated ( Dec. 2001) • Defined and signed • Civil engineering works • steadily progressing • Hand-over dates of the caverns to experimental Collaborations confirmed (ATLAS: April 2003, CMS: July 2004) • LHC schedule redefined according to signed contracts • Agreement on M&O costs reached with Funding Agencies LHC Status
LHC Schedule • We are very unhappy that the 2006 schedule could not be held; • Definite damage for many physicists and students around the world; • New schedule is based on official dates in the contracts of the main industrial items, with some reasonable (but not so large) time contingency; • Schedule determined by technical rather than financial constraints; • Makes possible an overall affordable scheme, for both machine and detectors. LHC Status
LHC Cost to Completion • We confirm the Cost to Completion given in 2001; • A contingency >100M is included in the Medium Term Plan; • The analysis of Manpower, in the framework of new schedule, savings etc. is in progress • Attribution of (36) Work Packages to specific groups, responsible towards LHC/CERN Management has been going on and is now almost completed • Earned value accounting, FI updated contract follow up are being implemented. LHC Status
Status report on the LHC machine Lyndon Evans LHC Status
Civil engineering at Point 5 LHC Status
Dipoles P. Lienard / LHC-MMS LHC Status
Dipoles P. Lienard / LHC-MMS LHC Status
Cable delivery A. Verweij LHC-MMS LHC Status
Number of dipole UL's delivered to CERN per month (1 dipole is 4 UL-1 + 4 UL-2) LHC Status
Super Conducting cable, last concerns • Breakage of one cabling machine has been announced early this week; 3-4 months to repair; • CERN has ordered one cabling machine as backup, but it will come into operation in spring 2003 only; • We shall ask companies to continue with strand production and use our stored capacity to provide sc cables for dipole cold mass production. LHC Status
Dipoles Dipole assembly at ALSTOM LHC Status
String 2 LHC Status
MQ1 MB1 MB2 MB3 MQ2 MB4 MB5 MB6 LHC Status R. Saban /A C (May 2002)
First Powering of String 2 LHC Status
E-cloud simulations F. Zimmermann/G. Rumolo, ECLOUD Workshop 2002, LHC Status
e- Cloud studies in the SPSPressure evolution with dose 4 orders of magnitude ! in 10 days LHC Status
e- Cloud studies in the SPSPressure evolution with LHC beam time 3 orders of magnitude in 4 days ! LHC Status
Horizontal Emittance Preservation (Almost) 10ms : 3.4mm Vertical 5ms : 3.4mm 15710ms : 3.7mm 2 Batches of 72 bunches with 1.3x10+11 protons/bunch 15700ms : 3.5mm PS Emittance : ~3.2mm LHC Status
Earned Value Accounting • We need to know • Planned (target) cost at a date (PC) • Real cost at a date (RC) • Earned value at a date (EV) • Cost variance: EV-RC • Schedule variance: EV-PC • Real problem: determine EV • Break up of work packages into many, small, work units, RC and EV updated weekly! • Software by AS Division • Implementation for LHC machine&areas: December 2002 (a hard job, but worth the effort) LHC Status
TOF ALICE Detector TRD HMPID TPC PMD PHOS ITS Muon arm LHC Status
Muon Magnet • Dipole Magnet • 0.7 T and 3 Tm • World’s largest warm dipole • Progress: • Coil production in progress in France • Yoke production in progress in Russia Test coil winding Iron yoke LHC Status
TPC status: Field Cage BEING MANUFACTURED! (after re-tendering to reduce cost) Hand lay-up of composite structure Cylinders are fabricated from three 120-degree-‘panels’ glued together (lashing). Production has started in September 2001 Inner FC arrived at CERN end March LHC Status
Barrel Toroid Engineering Design Components Manufacturing Integration at CERN Installation in the PIT TB layout as simulated for final mechanical structural analysis Engineering & Monitoring @ CEA, LASA LHC Status
0% 50% 100% In production Finished ATLAS:Barrel Toroid components production TB conductor (32 units x 1730 m) : • almost finished Double Pancakes (16 units) : • 9 DPCs made, #12 is being wound Integration 1 Coil Casings (8 units) : • 2 delivered and accepted Vacuum vessels (8 units) : • 1st vessel accepted, 2nd produced Tie Rods (64 units) : • All forged, 2 machined Thermal shield (8 units) : • First delivery in June ‘02 Integration 2 Super insulation (500 m2) : • In production, first delivery June ‘02 Stops(256 units) : • Batch 1 in production, delivery ‘May ‘02 Warm structure : • Final design phase (cost optimization) industrial contacts Installation Cryo ring : • Engineering finished tendering phase
conductor pancake Al coil casing P(resin + m-spheres) bladders prepag cryostat Barrel Toroid Integration Work @ CERN Integration 1 • Integration 1 contracted to an outside Firm in 2000 for ~ 3.5 MCHF • End 2001 the Firm stops preparation work with substantial financial claims • Feb 2002 ATLAS negotiated a new solution with the second bidder + CEA Saclay + JINR + ATLAS team to do the work at CERN • Work will start in bldg 180 mid May 2002. Original cost and schedule respected. Integration 2 • Work contracted to the JINR group + CEA Saclay + ATLAS team in bldg 180. • Tooling prepared, readiness on schedule • Includes final functional test LHC Status Coil Casing
The first ATLAS Barrel Toroid vacuum vessel leaving FCM, Spain, for CERN (Felguera Construcciones Mecanicas S.A.) LHC Status
The first ATLAS Barrel Toroid vacuum vessel arriving at CERN LHC Status
The CMS Detector SUPERCONDUCTING COIL Total weight : 12,500 t Overall diameter : 15 m Overall length : 21.6 m Magnetic field : 4 Tesla Silicon Microstrips Pixels CALORIMETERS ECAL HCAL Scintillating PbWO4 crystals Plastic scintillator/brass sandwich IRON YOKE TRACKER MUON ENDCAPS MUON BARREL Chambers(DT ) Cathode Strip Chambers (CSC) Chambers(RPC ) Drift Tube Resistive Plate Resistive Plate Chambers (RPC) LHC Status
Magnet Barrel Yoke finished LHC Status
Status of Conductor: CMS Each length is 2650m long
CB-2 mandrel ready Coil is made of 5 submodules CB-2, CB-1, CB0, CB+1, CB+2 Mandrel for CB-2 is finished ~6 months late – problem with supply of special elements in high strength alloy for mandrels, plates and flanges. CB-2 completed end 02 CB+2 completed end 03 LHC Status
Swiveling Platform (Korea) Assembly finished at Pt. 5 Swiveling Platform LHC Status
Milestone Plots ATLAS CMS ALICE LHC Status
Costs to Completion and C&I • ATLAS • C to C 47 C&I 21 Total 68 MCHF • CMS • C to C 48 C&I 15 Total 63 MCHF • ALICE • C to C 4 C&I 3 Total 7 MCHF C to C Reviewed by CORE accepted by RRB C&I Reviewed by Scrutiny Group accepted by RRB LHC Status
ATLAS LHC Status
CMS LHC Status
Concerns in the Experiments • ATLAS • Barrel and Endcap Toroid Schedule • CMS • ECAL electronics • Si tracker and RPC mass prodution • LHCb • HPD production LHC Status
M&O TotalsNote : No recording media LHC Status
M&O MoU • Contains Definition of Process • Agreed by all RRB’s in April 2002 • Ready for circulation and signature LHC Status
Conclusions • M&O for 2002 agreed for all experiments • Initial Estimates for 2003 ready for Scrutiny Process • Approval of final figures in Oct 2002 LHC Status
Summary on Detectors • Next Steps • Funding Agencies confirm funding profile … June • Collaborations produce contingency plan • Review Installation Plans …. Sept 2002 • Oct RRB • Agree plan for ALICE,ATLAS,CMS completion • Very Positive Atmosphere to complete the detectors LHC Status
Conclusions • Enormous progress over the last year • Contracts • In depth reviews on all aspects • ERC • We have a consolidated picture of all costs to completion • Work still to be done to consolidate the picture on manpower to completion • Financing means are being found • Not out of the woods, yet, but… • A new solid, long term plan for LHC commissioning in 2007 will be ready for December 2002 and submitted to Council LHC Status