160 likes | 318 Views
ENV-2E02 Energy Resources 2004 - 2005. 6. History of Electricity Supply Industry. Keith Tovey Н.К.Тови М.А., д-р технических наук Energy Science Director C Red Project. 6. Early Background 1900 - 1957.
E N D
ENV-2E02 Energy Resources 2004 - 2005 6. History of Electricity Supply Industry Keith Tovey Н.К.Тови М.А., д-р технических наук Energy Science Director CRedProject
6. Early Background 1900 - 1957 • Prior to 1900 - numerous small utilities sprang up in towns and cities. Many operated on DC (Direct Current). • Early 20th Century, Local Authorities in control of supply. • Supply switched to AC, • Some areas still had DC until after Second World War. • In 1924 there were about 435 power stations supplying electricity. • In 1930s, the Central Electricity Board began establishing a National Grid, initially at 33kV, then 66 kV and finally by the early 1950's, 132 kV. • Higher voltages for transmission minimise transmission losses. • The CEB built larger stations connected to grid
6. Early Background 1900 - 1957 • At end of War, the number of stations had dropped to 345. • cf 240 in 1965 • 168 in 1976 • 78 in 1986 • 1947 Electricity Act (effectively Nationalisation) • In most other countries, supply of electricity, gas etc. remained in the control of the Local Authority. • The Act also set up the BRITISH ELECTRICITY AUTHORITY as the successor company to the CEB.
6. Early Background 1900 - 1957 • ELECTRICITY AUTHORITY as the successor company to the CEB. • Finally in mid 1950's, the BRITISH ELECTRICITY AUTHORITY was reorganised as follows:- • CEGB -responsible for generation and supply to the local Electricity Boards. CEGB only operated in England and WALES, and was divided into 5 regions. The CEGB operated nuclear, coal, oil, gas, and hydro stations. • ELECTRICITY BOARDS - purchased electricity from the CEGB and distributed it to customers. There were 12 Area Boards (e.g. MANWEB, SEEBOARD etc). These Boards did not generate electricity. • ELECTRICITY COUNCIL - This was a body covering the whole Electricity Industry, and had a Research Centre at Capenhurst.
6. Early Background 1900 - 1957 • SCOTLAND, the organisation was different. • SOUTH OF SCOTLAND ELECTRICITY BOARD. (essentially area covered by SCOTTISH POWER) • Generated and supplied electricity to customers in the South of Scotland. It also operated nuclear power stations. • NORTH OF SCOTLAND HYDRO BOARD. • Generated electricity mostly by Hydro-electricity and supplied electricity to the North of Scotland and the outlying islands. Fossil Fired power stations were built, and the hydro component became less than 50%. • The NSHB exchanged electricity with SSEB who in turn exchanged electricity with the CEGB. • A low power link was also installed to link the CEGB with Electricite de France (EdF).
6. DEVELOPMENTS ELECTRICITY SUPPLY 1957-90 • CEGB began installing Super-grid at voltages of 275 kV and finally 400 kV. • Decision taken in early 1960's to build new power stations to avoid shortages of late 1950's and early 1960's. • Sited on coal fields or on coast (Nuclear and Oil). • Electricity became National Electricity Vector • Consequences:- • Less coal by rail - closure of lines in 1960's • More Grid Lines needed • ( even today there are parts of the country which are vulnerable eg SW and SE). • Made implementation of CHP difficult. • Power stations became very • Large stations did not have nearby heat sink for CHP.
Typical UK Electricity Demand in Winter 2003 For an up to date indication of actual demand – consult www.bmreports.com
Typical UK Electricity Demand in Summer 2002 1st August 2002
6.2. Forecasting Demand • Electricity CANNOT be stored, and generating capacity at any instant must be closely matched to demand. • FORECAST DEMAND AS ACCURATELY AS POSSIBLE. • FACTORS AFFECTING DEMAND:- • Weekdays have generally similar demand pattern • Weekends have a different but generally consistent demand pattern. • Minor variations occur:- • e.g. larger morning peak on Mondays, more spread out evening peak on Fridays.
6.2. Forecasting Demand • Weather affects demand by shifting curve upwards:- • *Dominant factors:- • EXTERNAL TEMPERATURE (approx. 8% increase in heating demand per 1o C drop in temperature). • INDUSTRIAL DEMAND (these are usually constant for a given day) • Other factors:- • * Wind chill • * Solar gain • - affect consumption by a few percent at most. • Seasonal factors shift evening peak to late evening as daylight hours increase.
6.3. Levels of Forecasting • MADE BY NATIONAL GRID TRANSCO • 1) LONG TERM:- Strategic planning of requirements of period of years. • 2) SHORT TERM:- (about 1 week ahead) • on basis of long range weather forecasts • 3) 24-HOUR FORECAST:- (previous afternoon) • on basis of latest weather information. • indirectly influences which generating plant are used. • 4) SHORT TERM FLUCTUATIONS:- • equipment failures, • television adverts etc. • dealt with by use of pumped storage schemes, use of GAS TURBINES etc. • A reserve of about 0.5 - 1.0% is usually provided by running generators slightly under full load.
6.3. Levels of Forecasting • FORECASTS FOR SPECIAL OCCASIONS ARE VERY DIFFICULT • SPECIAL SPORTING EVENTS can cause minor problems • (e.g. the CUP FINAL going to extra time), • Electricity cannot be stored except in small quantities so power stations are called into use as needed. • If a station is cold it may need up to 1 day to come on line. Even when hot most will need at least 20 minutes to come up to full power. • Cheapest marginalplant were run first • Then base-load Coal - most efficient coal. • Above plant are run continuously for several days on end as demand is always above output (at least in short term) • The cost for running a particular plant will depend on how warm the plant is. 6.4. Meeting Demand - former CEGB Method