1 / 46

Concrete Roundabouts

Concrete Roundabouts. & Intersections. Why Concrete Roundabouts …. No rutting with turning motion of heavy vehicles… Long-term solution… Low maintenance… Good skid resistance… Constructed quickly. Roundabout Issues. Thickness design Joint layout Transitions Staging

ednap
Download Presentation

Concrete Roundabouts

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Concrete Roundabouts & Intersections

  2. Why Concrete Roundabouts … • No rutting with turning motion of heavy vehicles… • Long-term solution… • Low maintenance… • Good skid resistance… • Constructed quickly

  3. Roundabout Issues • Thickness design • Joint layout • Transitions • Staging • Opening to traffic

  4. Roundabout Thickness Design • Use existing design procedures • AASHTO 1993 extremely conservative • AASHTO ME • ACPA StreetPave • Design for ALL traffic • Worst case would likely be combined directional traffic from N-1 legs

  5. Follow the Steps • IS006P • Intersection Joint Layout • 10-step method • Available from ACPA • Do not exceed maximum joint spacing at slab exterior for wedge shaped slabs • Use isolation joint at truck apron

  6. Isolate Circle

  7. Pave Through (Not Common)

  8. Narrow Radial Slabs/Truck Aprons

  9. Isolation Joint Narrow Radial Slabs/Truck Aprons

  10. Narrow Slivers

  11. Narrow SliversWidened Gutter

  12. Curb Placement – Widened Gutter

  13. STAGING • Piece meal • Partial Closures • Full Closure

  14. Quadrant Construction

  15. Half at a Time

  16. Production Rate Comparison Fixed Form 12’ Wide 70 – 120 CY/Hr Slip Form Paver 24’ Wide 10”+ depth 200CY-400CY/Hr Reconstruction Mainline New Construction 2500-4000CY/Day

  17. Partial Closure2008 Success Stories • City of Longview Washington • City of Redmond Washington

  18. SR 432 / SR 433PCCP RebuildCity of Longview

  19. Finished Intersection

  20. Intersection Rebuilt in 3 Phases

  21. Ma Bell Vault Work Around

  22. Preformed Traffic Signal Loop

  23. Work was around the Clock

  24. Bull Floating

  25. SR 520 Avondale Rd/Union Hill Rd Redmond WA 100,000 ADT

  26. 100,000 ADT • 2600 CY • Construct in 2 Weekends • Gary Merlino Construction • Consultant Design • INCA Engineers Bellevue

  27. Combination Closures: • SR-395 & Yelm, Clearwater, Kennewick Avenue: • Lane Closures Stages 1,2, 4 • Complete Closure Stage 3, Thursday at 7:00 PM to Monday 6:00 AM. • Late opening penalty of up to $2,400.00 per hour.

  28. Time for Completion: • Kennewick Avenue and Clearwater were built concurrently. This saved a considerable amount of time. Crews always had a place to work. • In 15 days approximately 3384 cubic yards were placed in the two intersections. • Construction staging was as follows:

  29. Kennewick Avenue Stage 1:

  30. Kennewick Avenue Stage 2:

  31. Kennewick Avenue Stage 3:

  32. Kennewick Avenue Stage 4:

  33. Photo Stage 4:

  34. Crater Lake & McAndrewsMedford, OR

  35. Crater Lake & McAndrews • 60,000 ADT • Widening work done prior to any traffic modifications • Closed half of the intersection for 1 week • Total 2 weeks to complete

  36. Construction Time • 70 – 120 cy/hr typical for hand placement • 2 lane roundabout , 80’ dia., could be paved in 7-10 days under complete closure

  37. Opening Strength • Acceptable opening strength dependent on slab thickness • 7” 370 psi = 2,040 psi compressive • 8” 335 psi = 1,760 psi compressive • 9” 275 psi = 1,310 psi compressive • 10” 200 psi = 820 psi compressive • Based on FE analysis assuming 1000 trucks per day, k-value of 200 pci, no edge support. • Beam strength typically lower than in-place strength by 50-150 psi

  38. Reasons for Success: • WSDOT had several preliminary meetings with City of Kennewick to discuss impacts and City concerns. • WSDOT invited businesses to pre construction meeting. • WSDOT met with contractors to discuss feasibility. • WSDOT kept public informed via newspaper, radio, and television news broadcasts. • WSDOT web page with up to date information. • WSDOT gave flyers to businesses weekly.

  39. Reasons for Success Continued: • WSDOT/Acme partnered on the modifications to the traffic control plan allowing continuous work operation with increased safety for employees. • Clearwater & Kennewick were constructed concurrently maximizing crew efficiency. • Detailed schedule with known milestones. • Meeting or beating schedule. • Something going on all the time. • Decision makers available to resolve issues.

  40. Keys to SuccessAll Projects • Adequate time for planning • Industry Input • Qualified Contractor • Just in Time Training • Timely Decision Making • REALISTIC SPECIFICATIONS

  41. Thank you! Questions?

More Related