501 likes | 516 Views
The Logical Framework as an Implementation and Monitoring Tool. RBEC Environment & Energy Practice Workshop Almaty, Kazakhstan. 6-9 October 2004 John Hough, UNDP GEF BD PTA. Reminder: The LogFrame is an Approach not a Matrix.
E N D
The Logical Framework as an Implementation and Monitoring Tool RBEC Environment & Energy Practice Workshop Almaty, Kazakhstan. 6-9 October 2004 John Hough, UNDP GEF BD PTA
Reminder: The LogFrame is an Approach not a Matrix • Methodology -including a set of tools- to structure and facilitate: • project planning • project design • project management • project performance assessment
Benefits LFA contributes to: • structured project design process- logical sequence • transparency- clear objectives, side effects • participation- ownership, sustainability • consistent project strategy • assessment of performance- indicators (ex-post & during implementation)
Basic Steps and Elements • Problem Analysis • Stakeholder Analysis • Objectives Analysis • Analysis of Alternatives • Project Planning • Project Planning Matrix (PPM) (the “logframe”)
Problem Analysis • Establishing “cause and effect” relationships – a “problem tree” • “lack of the solution is not the root cause of the problem”! • Identifying “lack of knowledge” as the problem means that the solution is already pre-determined: ie. “provide knowledge” • Getting people to focus on what they need to do vs. what they want to do is often the biggest challenge in project development • Solution Driven Analysis often leads to solving the wrong problem
Lessons learned 1. Doing “good work” or “achieving impact”? 2. “Seeing the wood for the trees”
Problem Analysis • Stakeholder Analysis
Stakeholder Analysis • Problem Analysis cannot be done without Stakeholder Consultation. • Every stakeholder views the problem from a different angle. • Problem analysis and stakeholder identification and analysis are iterative processes, progress in one almost always means returning to the other.
Problem Analysis • Stakeholder Analysis • Objectives Analysis
Objectives Analysis • What is the project “going after”? • What are the indicators?
Problem Analysis • Stakeholder Analysis • Objectives Analysis • Alternative Analysis
Alternative Analysis Systematic search for the best project approach. • What outcomes are required to reach the objective? • How best to reach each outcome? • What outputs are required to reach each outcome? • What activities are required to achieve each output? • Set up criteria for assessment of alternatives, such as: • resources available • political feasibility • social impact
Fundamental Project Design Outcome 1 + Outcome 2 + Outcome 3 = Objective
Lesson Learned • there should be no spare outcomes • nor should there be any outcomes that are not essential for the achievement of the objective
In the logical logframe matrix we simply list the outcomes vertically Objective = Outcome 1 + Outcome 2 + Outcome 3
Assumptions • Conditions that are necessary for the success of the project, but which are not under the direct influence of the project. • Assess conditions according to importance and probability • Need to be monitored / risks • Pay attention to “killer assumptions” (= need to re-design project)
Assumptions vs. Risks • Assumptions tend to be positive eg. “a supportive piece of legislation is passed” • Risks tend to negative eg. “increased pressure on a protected area as a consequence of a resettlement programme” • Assumptions can be formulated negatively as risks, and vice versa – risks as assumptions • Assumptions are generally identified during project design • Risks often appear during project implementation
Converting Assumptions to Outcomes through Cofinancing • If a condition required through an assumption can be brought under the influence of the project, then it becomes a project outcome. • The costs of achieving that outcome would count as co-financing
Listing these vertically in a logical logframe matrix we get: • Objective • = Outcome 1 • + Outcome 2 • + Outcome 3 • + Assumption 1 • + Assumption 2
Similarly these are written vertically: • Outcome 1 • = Output 1 • + Output 2 • + Output 3 • + there may be assumptions at this level too!
3.Basic Steps and ElementsPlanning PhaseProject Planning Matrix (PPM)
ie. the logframe matrix combines the vertical and horizontal logic • Objective • = Outcomes 1+2+3 + Assumptions • = Outputs 1+ 2+ 3+4 + Assumptions • = Activities 1+2+3+4 + Assumptions
3.Basic Steps and ElementsPlanning PhaseProject Planning Matrix (PPM)
Project Planning or “LogFrame” Matrixis a “Summary” of the Project • WHY the project is carried out (development objective, immediate objectives) • WHATthe project is supposed to produce (outputs) • HOWthe project is going to achieve the outputs (activities) • HOWthe success of the project can be measured (indicators) • WHERE the data can be found (means of verification) • WHICH external factors influence the project (assumptions) • WHICH inputs are required for the project (inputs/budget)
In a logframe we are not very interested in activities • Activities are the means to an end • We are interested in “ends” or “impacts” • Summarize the activities in the logframe • Overloading the logframe with activities is confusing, and also a waste of effort since they are likely to change in the light of project circumstances • Activities are detailed in a project management annual activity workplan
Lesson learned GEF Projects tend to be “overdesigned” • They place far too much emphasis on “activities” • There is too much emphasis on measuring or counting outputs and activities
GEF Strategic Business PlanDirections and Targets (GEF/C.21/ Inf.11) The SP’s are what we are “going after” • GEF Strategic Priority / Target • Project Objective / Target • Project Outcomes / sub-Targets • Review the impact indicators associated with these
A word on terminology Development Goal = what the project contributes to, but does not on its own achieve Project Objective = what the project is accountable for delivering Project Outcomes = the constituent elements of a project. The sum of the project outcomes = the project objective
Project targets are rolled up to achieve the SP targets SP1.Target 2: x (y%) countries show improvements in management effectiveness (policy, legislation, capacity, budgets) = Improvements in country 1 + Improvements in country 2 + etc
ie. the Traditional Logframe Matrix and the Results Measurement Framework are easily combined
Using the logframe as an implementation and monitoring tool “Seeing the forest for the trees” • Focuses on targets and impacts, not activities or outputs • Enables us to revisit the “alternatives” and adjust the activities or outputs on a regular basis • Adaptive management
Objectives of Alternative Projects: • Reduced Fishing Intensity • Increased Fish Populations • MUMPA’s • Regulations • Demarcation • Staffing • Decision Making • Financial Tools
Good Indicators • Indicator is a quantitative or qualitative variable or parameter that provides a simple and reliable basis for assessing change or performance (the objective or outcome). • Verifier. Variable or parameterthat retains the essential meaning of the objective and that can be measured on the ground. • Qualifier. Contribute to describe the verifier allowing to respond to: what, when, where, who • Targets/ Baseline- values associated to the verifiers that define how much the objective is planned/expected to be achieved compared to the situation prior to project start. Intermediate targets (milestones) allow assessment of progress.
Example of a Good Indicator Objective: “Conservation of keystone species” Indicator: • At the end of the fifth year (qualifier: when) • the population sizes (qualifier: what) • of species A, B and C (verifier) • within the boundaries of the park (qualifier: where) • have remained constant (target) • compared to X number at project-start level (baseline)
Lesson Learned - Procrastination • Project designers defer measuring indicators to the inception phase • The inception phase defers measuring indicators to project implementation • Project implementation defers measuring indicators to the mid-term evaluation • The mid-term evaluation defers measuring indicators to the second half of project implementation • Project implementation defers measuring indicators to the final evaluation • The final evaluators say “we cannot prove this project has achieved anything”