1 / 14

Increasing Access to the Grid NIPPC September 8, 2005

Increasing Access to the Grid NIPPC September 8, 2005. Brian Silverstein VP, Operations and Planning Bonneville Power Administration. Increasing Access to the Grid. Expand the Pie Increase Utilization Coordinated Planning. 2001: Network Constraints. Infrastructure Program.

eldora
Download Presentation

Increasing Access to the Grid NIPPC September 8, 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Increasing Access to the GridNIPPCSeptember 8, 2005 Brian Silverstein VP, Operations and Planning Bonneville Power Administration

  2. Increasing Access to the Grid • Expand the Pie • Increase Utilization • Coordinated Planning

  3. 2001: Network Constraints

  4. Infrastructure Program • To address the region’s transmission needs, BPA developed a transmission infrastructure program in 2001 to focus on: • Maintaining reliable transmission service to population centers. • Restoring or enhancing transfer capability across key paths. • Providing margin so the system can be maintained. • Evaluating and investing in non-wires alternatives.

  5. Infrastructure Accomplishments • First major line construction in the Northwest since 1987. • Invested more than $1 billion over four years. • Two 500-kV lines completed, one under way. • Modernized the nation's largest direct current terminal (Celilo Converter - 3100 MW). • Several projects to upgrade local load service.

  6. Status of BPA Infrastructure Additions W a s h i n g t o n Grand Coulee-Bell 500 KV Transmission Line Project April 2003-Dec 2004 Completed Underway Substation Project Completed BPA Transmission Lines Indian Reservation On Hold Proposed Substation Project Completed Olympic Peninsula Reinforcement 1-5 Corridor Generation Addition Northern Idaho Reinforcement Kangley-Echo Lake 500 KV Transmission Line Project July 2003-Dec 2003 Schultz Series Capacitors March 2003-Nov 2004 Puget Sound Area 500/230 KV Transformer Schultz-Hanford Area SW Washington NW Oregon Reinforcement Raymond-Cos West of Mcnary West of Slatt M o n t a n a Portland Area Reinforcement 3 Celilo Modernization Winter 2001-June 2004 Pearl Transformer Project Dec 2002-Dec 2003 Albany Eugene Rebuild I d a h o O r e g o n Swan Valley Goshen Rebuild Anderson Ranch Mountain Home Rebuild Southwest Oregon Coast Reinforcement Lower Valley Reinforcement

  7. 2005: Network Constraints

  8. Non Wires Solutions • Potential Measures • Demand response • Energy efficiency • Distributed generation • Appropriately sited large generation • Objectives • Find least-cost solutions to transmission limitations • Provide equivalent reliability to a transmission fix • Benefits of transmission deferral • Time value of money • Option value of delaying costly investments

  9. Path Utilization Example

  10. Increase Utilization • Flow-based ATC methodology • Constraint Schedule Management • New products and services • Conditional firm • Redispatch • Better remarketing of unused rights • Strategic use of nonfirm and short-term firm

  11. Transmission Buying Strategy for Wind Peak Output Buy When Needed Sell When Not Needed Average Output

  12. Integrated Planning Concept • Objective: Achieve an adequate and least-cost plan in a functionally separated industry. • Premise: Most commitments to long-term transmission, particularly those that require expansion, are tied to utility power purchase agreements. • Concept: Establish a coordinated planning cycle that links individual utility resource planning with a region-wide transmission open season. • Benefits: • Improves our ability to develop transmission when needed. • Provides for a regional adequacy assessment.

  13. Resource Planning Transmission Planning IRP Txm Open Season Start/ Finish Txm Commitments Locational Expansion Costs Utility Resource Plan Integrated Txm Plan RFP Regional Adequacy Assessment Integrated Planning Concept

More Related