Resource requests and allocations for the CERN T0/T1 center in 2003 + 2004 (preliminary, v1.0)

Resource requests and allocations for the CERN T0/T1 center in 2003 + 2004 (preliminary, v1.0). Changes since last evaluation ALICE DC shifted by 3 month into 2004 ATLAS DC shifted by one year to April 2004 Fine tuning of the CMS request

Download Presentation

Resource requests and allocations for the CERN T0/T1 center in 2003 + 2004 (preliminary, v1.0)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Resource requests and allocations for the CERN T0/T1 center in 2003 + 2004 (preliminary, v1.0) Bernd Panzer-Steindel, CERN/IT

  2. Changes since last evaluation • ALICE DC shifted by 3 month into 2004 • ATLAS DC shifted by one year to April 2004 • Fine tuning of the CMS request • Resource request increase by LHCb ( GEANT 4) Bernd Panzer-Steindel, CERN/IT

  3. Bernd Panzer-Steindel, CERN/IT Jan 2004 Dec 2004 July 2003

  4. Bernd Panzer-Steindel, CERN/IT July 2003 Jan 2004 Dec 2004

  5. Plan Bto cope with resource over-allocation in Q2 • (a combination of one or two options is probably sufficient) • spread the load per experiment over a longer time period • shift one or two data challenges in time, forward or backward by 2-3 month • reduction of non-LHC resources by 50 % == 150 KSI2000 • add resources from the testbed, computing data challenge and LCG-x installations == 300 KSI2000 • add the base-line resource per experiment == 50 KSI2000 Bernd Panzer-Steindel, CERN/IT

  6. Purchasing strategy • New tender for disk and cpu server is out • fill the stores with enough equipment in October • install 2004 equipment end December or beginning of January Budget 2004 • 500 KSFr for new LHC CPU resources , 100 KSFr for replacement •  ~ 400 KSI2000 • 500 KSFr for new LHC disk resources , 100 KSFr for replacement •  ~ 40 TB • 500 KSFr for non-LHC investments • Possible problem • Decision is due on who pays for LHC tape storage in 2004 • estimated 600 KSFr If IT has to pay : extra budget ? or to be deduced from the 1.2 million Bernd Panzer-Steindel, CERN/IT

  7. Disk resources • this years delivery very late • installation has started this week • total resources per experiment • CMS 12.1 TB, ATLAS 12.6 TB, ALICE 6.1 TB, LHCb 7.0 TB • some extra resources available through LCG prototype • upgrade of WACDR in July, move to at least one server • per experiment, improved CASTOR – GRIDftp integration • re-discussion of the disk storage requirements for the experiments in the current COCOTIME round ~ 40 TB extra for 2004 Bernd Panzer-Steindel, CERN/IT

  8. Questions • Is the move from GEANT3 to GEANT4 causing the same • resource changes for all 4 Experiments ? • There are two in-efficiencies not yet considered :  Lxbatch cluster (LSF, IO wait, etc.) 0.8 ??  Experiment specific (crashing jobs, submission inefficiencies, etc.) 0.8 ?? • Memory size of the simulation jobs ( > 200 MB ??) Bernd Panzer-Steindel, CERN/IT

  9. Summary • No need to buy anything still in 2003 • Can cope with the physics DC’s in 2004 with a bit of • ‘re-arrangements/adjustments’ • More detailed discussions about disk space necessary Bernd Panzer-Steindel, CERN/IT