This summary provides updates on the follow-up of space requests and the new building in Prevessin. It includes information on the replacement of various buildings, the increasing number of users, and ongoing works.
E N D
SUMMARY B974 / AMS B506 / n-TOF request B777 / New building in Prevessin Space requests follow-up - Claire Work follow-up - Sébastien SPOB November 18
B974/ AMS • Works to be started before the end of the year. SPOB November 18
B506 / n-TOF request • SME could agree to move • ATLAS is not interested in going in B603 • DIRAC doesn’t want to move • TOTEM cannot move easily some labs in B506 – the period is in addition not appropriate SPOB November 18
B777 / New building in Prevessin SPOB November 18
B777 / New building in Prevessin • It should be taken into account • B974 AMS building replacement • B510 replacement as it should be demolished in 8 years from now • B188 replacement in case HSE would still consider it as the best fit for their training centre project • Annual increase of the number of users of 3% i.e ~ 350 persons [to be normalised taking into account their presence on CERN site] SPOB November 18
Move cascade V1 SPOB November 18
Move cascade V2 SPOB November 18
Space requests follow-up SPOB November 18
Space requests follow-up SPOB November 18
Space requests follow-up / Loans SPOB November 18
Work status follow-up SPOB November 18
Bat 188Installationde 2 fenêtres SPOB November 18
Bat 188Installationde 2 fenêtres SPOB November 18
Bat 2 Ancienlabo TelecomInstallation d’unebaievitrée SPOB November 18
Bat 52 Secrétariat NeutrinoInstallation d’unebaievitrée SPOB November 18
2019 - Works already identified Total estimated cost 600kCHF Priorties to be defined – Many works still unknown. SPOB November 18