Shielding of Route Goward Status – 25 June 2013. Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th) Finishing works : Metalworks – in july 2013 2 nd layer of blacktop and parking – after Septum 16 works.
E N D
Shielding of Route Goward Status – 25 June 2013 • Main works of Route Gowardwillbecompleted end of June 2013 (1st layer blacktop on june 28th) • Finishingworks: • Metalworks – in july 2013 • 2nd layer of blacktop and parking – after Septum 16 works
Somepictures of the works: Temporary road Pilingworks Retainingwall
Formwork for the slab Biocofra Slabreinforcement
Backfilling Concreting Road works
Shielding of Septum 16 Status – 25 June 2013 • Adjudication of the works on 19 June 2013 • June-July 2013 - Preparatoryworks • « Sondages » • Felling of trees • Removal of the barrierclosingaccess to the PS • Removal of the streetlighting • Setting out of the works • Worksite installation • Information campaign for users and TSO • July 2013 – Earthworks • September 2013 - Pilingworks
Worksite installations: Parking route Goward sharedwith CV Concretebatching plant (to beconfirmed) Temporaryspoil dump «Passage pieton» closed Access to building 561 (RP)
Expected in July 2013! Provisional Schedule