1 / 34

13-1

Objectives. Lesson objective - to discuss the fundamentals of Life cycle cost to include… What does it include? Why is it important? Expectations - You will understand why life cycle cost is so important and what kinds of issues it addresses

elina
Download Presentation

13-1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Objectives • Lesson objective - to discuss the fundamentals of • Life cycle cost • to include… • What does it include? • Why is it important? • Expectations - • You will understand why life cycle cost is so important and what kinds of issues it addresses • At the end of this lesson, you should understand (1) the fundamental issues and (2) how to make life cycle cost estimates Life Cycle Cost 13-1

  2. Discussion subjects • Review • Parametric cost estimates • Development • Procurement • UAV application • Operations and support • Manned aircraft • UAV applications Life Cycle Cost 13-2

  3. Review - Life cycle cost • Development cost • The cost of developing a system • Considered a “non-recurring” cost • Occurs only once (hopefully) • Procurement cost • The cost to buy a system once it is developed • Includes a lot of “recurring” cost • Costs incurred every time a system is produced • Operations and support cost (Q&S) • The cost to maintain and operate a system after purchase • Includes the cost of maintaining crew proficiency • Excludes the cost of combat operations Development + procurement + O&S  Life cycle cost Life Cycle Cost 13-3

  4. Review - cost issues • Development cost • Customers want this to be as small as possible • New systems are expensive • Most of the cost is associated with risk reduction, engineering and test • Programs need “margin” to cover uncertainty • Procurement cost • This cost is sensitive to procurement quantity • Repetitive tasks become more efficient • Also sensitive to the size and complexity • Aircraft empty weight is considered a cost driver • Operations and support cost • Most of the life cycle cost of an aircraft is the “O&S” • O&S cost can be reduced by good up-front design Life Cycle Cost 13-4

  5. Pre-concept design • The product of this phase is a set of initial requirements and cost, risk and schedule estimates • Key technical issues addressed during this phase include: • Overall needs and objectives • Concepts of operation • Potential design concepts • Initial cost and schedule • Effectiveness estimates • Analysis of alternatives The technical work done during the pre-concept design phase establishes the initial cost and schedule estimate that the project will have to live with for the rest of its life Review - LCC importance Life Cycle Cost 13-5

  6. 100 95 85 70 50 10 Cumulative Percent Of Life Cycle Cost Milestones I II III IOC Out of Service The cost driver - early decisions Detailed Design Preliminary Design Concept Design Pre-concept Design Source – Defense Systems Management College, 3 Dec. 1991 Life Cycle Cost 13-6

  7. Next subject • Review • Parametric cost estimates • Development • Procurement • UAV application • Operations and support • Manned aircraft • UAV applications Life Cycle Cost 13-7

  8. Parametric cost estimates • Parametric models or cost estimating relationships (CERs) are used widely for aircraft cost estimating • - By industry for initial cost estimates • - By customers for proposal evaluation • Used when little is known about the design • - But also used to check internal consistency of detailed estimates • Methodology updates occur periodically • - Need to capture technology benefits and costs • Most recent updates focused on advanced structural materials • - Composite airframe materials drive airframe cost • Although no CERs yet exist for UAVs, they will exist someday and we need to understand the approach * (1) Advanced Airframe Structural Materials, a Primer and Cost Estimating Methodology, RAND R-4016-AF, Resetar, Rogers and Hess, c1990 Life Cycle Cost 13-8

  9. Material Aluminum Titanium Steel Composites Other USAF/AFRL data RAND data F-18 (1978) 48% 14% 15% 11% 12% F-15 (1972) 52% 40% 5% 2% 1% AV-8B 47% ?% ? 26% 27% F-111 (1967) 59% 5% 33% 1% 2% F-16 (1976) 79% 2% 4% 5% 10% B-2 27% 23% ? 37% 13% C-17 70% 9% ? 8% 13% F-22 16% 39% ? 25% 20% F-18 (E/F) 27% 23% ? 22% 13% Material utilization trends RAND Data - Advanced Airframe Structural Materials, a Primer and Cost Estimating Methodology, RAND R-4016-AF, Resetar, Rogers and Hess, c1990 AFRL Data – Evolution of U.S. Military Aircraft Structures Technology, AIAA Journal of Aircraft, Paul,Kelly,Venkaya,Hess, Jan-Feb 2003 Life Cycle Cost 13-9

  10. Cost drivers • CERs capture overall air vehicle cost drivers • 1. Size including airframe and empty weight, area, etc. • 2. Performance including speed, specific power, etc. • 3. “Construction” including load factor, engine location, area ratios, wing type, avionics weight ratio, etc. • 4. Program including number of test aircraft, new vs. existing engines, contractor experience, etc. • Of these, a few emerge statistically as real drivers* • - Airframe unit weight (AUW) • - Empty weight (EW) • - Maximum speed (Vmax) • - Number of test aircraft (NTA) • - Airframe material type and composition • Software should also be a driver (no data in 1990?) • * (2) RAND N-2283/2-AF, Aircraft Airframe Cost Estimating Relationships : Fighters, December 1987 Life Cycle Cost 13-10

  11. Cost categories and elements • RAND defines CERs in two major overall cost categories: non-recurring and recurring costs* • - Non-recurring (development) cost elements are: • - Non-recurring engineering hours (NRE) • - Non-recurring tooling hours (NRT) • - Development support cost (DS) • - Flight test cost(FT) • - Recurring (production) cost is normalized for 100 air vehicles and made up of the following elements: • - Recurring engineering hours (RE100) • - Recurring tooling hours (RT100) • - Recurring manufacturing labor hours (RML100) • - Recurring manufacturing material cost (RMM100) • - Recurring quality assurance hours (RQA100) • * Their methodology does not include engines, avionics, armament, training, support equipment and spares. These elements must be added. Life Cycle Cost 13-11

  12. Baseline CERs • RAND starts with an aluminum baseline cost estimate • - Non-recurring cost elements • NRE(hrs) = 0.0168(EW^.747)(Vmax^.800) (13.1) • NRT(hrs) = 0.01868(EW^.810)(Vmax^.579) (13.2) • DS = 0.0563(EW^.630)(Vmax^1.30) (13.3) • FT = 1.54(EW^.325)(Vmax^.823)(NTA^1.21) (13.4) • - Recurring cost elements • RE100(hrs) = 0.000306(EW^.880)(Vmax^1.12) (13.5) • RT100(hrs) = 0.00787(EW^.707)(Vmax^.813) (13.6) • RML100 (hrs)= 0.141(EW^.820)(Vmax^.484) (13.7) • RMM100 = 0.54(EW^.921)(Vmax^.621) (13.8) • RQA100 (hrs-cargo acft) = 0.076*RML100 (13.9) • RQA100 (hrs-non-cargo) = 0.133*RML100 (13.10) Life Cycle Cost 13-12

  13. Typical application • RAND example, hypothetical all-aluminum fighter • EW (lb) 27000 • Vmax (kt) 1300 • NTA 20 • Structure (lb) 13000 • Production quantity 100 • Typical labor rates (1999 $/hr)* • Engineering $86 • Tooling $88 • Manufacturing $73 • Quality Assurance $81 • * From Raymer, page 588 - Inflation factors can be used to adjust these to current year prices (also required for material costs) Life Cycle Cost 13-13

  14. From equations 13.1 through 13.10 • NRE(Khrs) = 10634 • NRE($) = $914.5M • NRT(Khrs) = 4611 • NRT($) = $405.7M • DS($) = $389.4M • FT($) = $577.6M • Nonrecurring = $2,287M • Total program (from NR + R) = $5.44B • RE100(Khrs) = 7463 • RE100($) = $642M • RT100(Khrs) = 3636 • RT100($) = $320.0 • RML100(Khrs) = 19502 • RML100($) = $1423.7 • RMM100 ($) = $559M • RQA100(Khrs) = 2594 • RQA100($) = $210.0 • Recurring($) = $3,155M Baseline cost Life Cycle Cost 13-14

  15. Engine cost • - Raymer’s cost discussion (Chapter 18) includes an equation for engine procurement cost in 1999$ • R(propul) = 2251*(0.043*Tmax + 243.25Mmax • + 0.969*TiT -2228) (13.11) • where • Tmax = Maximum thrust (lb) • Mmax = Maximum Mach • TiT = Turbine inlet temperature (degR) • ≈ 2000 - 2500 degR • - For other propulsion cycles we will use $/lbm(engine) • Avionics cost • - Raymer recommends a weight based approximation of $3000-$6000 per pound ($1999) • - We will use $5000/lb for both avionics and payloads Other costs Life Cycle Cost 13-15

  16. RAND recurring cost methodology is based on production quantities of 100 aircraft • - Other quantities are adjusted for the “learning curve” • - A term used to describe the efficiencies that result from learning repetitive processes and tasks • - Learning curve effects are generally expressed by exponential forms such as the following from RAND • Cost (Qn) = Cost(Q100)*(Qn/100)^exp (13.12) • exp(engineering hours) = 0.163 • exp(tooling hours) = 0.263 • exp(manufacturing hours) = 0.660 • exp(manufacturing material) = 0.231 • exp(tooling hours) = 0.714 • exp(total program) = 0.356 where Quantity effects Life Cycle Cost 13-16

  17. Advanced material effects • Advanced materials effects are applied to the aluminum baseline as separate cost factors • Effects of advanced materials vary by element • - Tooling (both nonrecurring and recurring) has twice the sensitivity to material type as engineering • - Tooling focuses primarily on airframe structure • - Engineering hours are driven by a wider range of design and manufacturing issues such as, design, integration, test, evaluation, etc. • Overall effects are captured by historical Structural Cost Fractions (SCF) for airframe structure • NonrecurringRecurring RE - 42% RT - 82% RML - 67% RML - 67% RMM - 58% RQA - 69% NRE - 45% NRT - 87% Life Cycle Cost 13-17

  18. Complexity factors • Used to capture labor hour and cost effects of different design and manufacturing processes • - RAND uses complexity factors (CFs) to determine material effects by structural cost element • NRE NRT RE RT RML RMM RQA • Al 1.0 1.0 1.0 1.0 1.0 1.0 1.0 • Al-li 1.1 1.2 1.1 1.1 1.1 2.7 1.1 • Ti 1.1 1.4 1.4 1.9 1.6 2.8 1.6 • Steel 1.1 1.1 1.1 1.4 1.2 0.7 1.4 • GrExp 1.4 1.6 1.9 2.2 1.8 4.9 2.4 • GrBi 1.5 1.7 2.1 2.3 2.1 5.5 2.5 • GrTP 1.7 2.0 2.9 2.4 1.8 6.5 2.6 Life Cycle Cost 13-18

  19. Methodology • Advanced material effects are applied to each cost element • MWC (j) = SCF(j)*[CF(i,j)*SW(i)/ SF(I)]+[1- SCF(j)] • (13.13) • where • MWC(j) = Material weighted cost element j • SCF(j) = Structural cost fraction for cost element j (chart 24-18) • CF(i,j) = Complexity factor (chart 24-19) • SW(i) = Structural weight by material type • See RAND Report R-4016-AF, Advanced Airframe Structural Materials, a Primer and Cost Estimating Methodology, for more application information Life Cycle Cost 13-19

  20. UAV cost issues • Unfortunately, there are no known UAV CERs and no consistent UAV cost data bases. An example: • - Total procurement cost projected by the Defense Airborne Reconnaissance Organization (DARO) for Predator in 1996 was $118M for 13 systems. • - In 1998 12 Predator systems were listed as $512M or $42.7M per system • - The same document budgeted $23.9M for one system for delivery in 1998 • These contradictions exist across a number of UAV types and it is clear that a comprehensive cost study is needed to resolve the issues • - Such a study is beyond the scope of this course • We will take a simpler approach Life Cycle Cost 13-20

  21. UAV cost approach • We will assume that manned aircraft CERs apply to UAV air vehicles and propulsion • - Cursory checks show this not a bad assumption • Global Hawk development cost ≈ $350M • - The RAND aluminum baseline development cost CER for EW + payload = 11,100lb, Vmax = 360 kts and two flight test aircraft predicts a development cost of $313M in $1999 (less engines and avionics) • - Avionics development costs are not available • Global Hawk procurement cost goal = $10M • - The RAND aluminum baseline procurement cost CER predicts a unit 20 development cost of $15.7M • - The customer acknowledged in 1998 that Global Hawk unit cost would be about $13M • - Latest reports are that the airframe costs $16-20M Life Cycle Cost 13-21

  22. Other UAV system elements • Little information is available on UAV control station and communications development and no CERs • - Available data indicates Tactical Control Station (TCS) development costs exceed $100M • Development costs for the Global Hawk/Dark Star common ground station (GCS) appear ≈ $250M • We will assume, therefore, that control station development (including communications) ≈ 70% of air vehicle development cost • Ground station procurement is harder to determine • - Predator ground and communications station costs appear about equal at around $3M each • - Global Hawk/DarkStar initial GCS procurement ≈ $25M each for 3 units. Latest reports = $45M • - We will assume control station procurement including communications ≈ 1 air vehicle + payload procurement Life Cycle Cost 13-22

  23. Other system elements - cont’d • We have no good information on UAV payload development costs • - However, there are many payloads available off the shelf and we will assume development cost is limited to integration, which is covered under the air vehicle • We also have no good information on UAV payload procurement costs • - We will use Raymer’s assumed $5000 per pound parametric until something better comes along • - This would imply that predator payload (450lb) costs are about $2.25M, far more than airframe cost • - At a payload weight of 1900lb, Global Hawk payload cost would be $9.5M, about equal to original airframe estimate (recent USAF data cites payload at $11M) • Despite the fact that some of these estimates are guesses, we will use them until something better comes along • - It is better to guess than to leave something out Life Cycle Cost 13-23

  24. Next subject • Review • Parametric cost estimates • Development • Procurement • UAV application • Operations and support • Manned aircraft • UAV applications Life Cycle Cost 13-24

  25. Manned aircraft data • O&S costs are driven by 2 factors • 2/3 by manpower (pilots, operations, maintenance, logistics and other personnel) • 1/3 by flight hours - Flight hours (and numbers of missions) drive maintenance and fuel consumption • Average annual O&S ≈ 10% unit procurement cost • - Typical SE fighter ≈ $3M/yr or $9000/flight hour • Typical manned fighter O&S cost breakdown • - Direct personnel (pilots, maintenance, etc.) = 40-45% • - Pilots (10%), ops support (15%), maintenance (75%) • - Approximately 20-30 maintainers per aircraft • - Indirect (security, medical, facilities etc.) = 20-25% • - Fuel and spare parts = 25-35% (≈ $2K/FH for fighter) • - Other = 5-10% • - 1997 O&S data shows USAF average annual squadron personnel costs at about $45K per person Life Cycle Cost 13-25

  26. This is the portion of the O&S cost that is directly related to flight hours (fuel and spare parts) • - Direct operating costs are key figures of merit for commercial operators • - Airlines typically quote direct operating costs in terms of cost per seat mile • - Others including the military use cost per flight hour ($/FH) and it appears to correlate with empty weight and speed Direct aircraft operating costs Life Cycle Cost 13-26

  27. Other direct operating costs • There is no information available on O&S cost for payloads, communications equipment and ground stations • - We can assume that the equipment is reliable but that it undergoes regular upgrade and refurbishment at least every 10 years • - We will assume, therefore, annual O&S cost to be about 8% of initial procurement cost • Once again, we are simply making an educated guess but it is better to do so than to leave out an important element of cost • - If our guesses are incorrect, we can improve them when we get more data • - If we leave something out, there is no chance for improvement Life Cycle Cost 13-27

  28. UAV data • Three O&S data points • In 1997 DARO budgeted Hunter UAV operations and support costs were at about $17.5 million for about 2000 flight hours or $8750/FH (almost the same as as a typical manned fighter) • In 1999 the VTUAV program established an O&S cost goal of 25% less than Pioneer at $6500 per flight hour • Published lifetime (10yr?) O&S cost for 11 Predator systems (44 air vehicles) = $697M in $FY97 • Other data • - UAV squadron manning data provides insight to adjust manned aircraft O&S data for UAV applications • - A 4 air vehicle Predator squadron, for example, deploys with 55 people, of which 30 are operators and analysts and 24 are maintainers (13.75 total people or 6 maintainers per aircraft) Life Cycle Cost 13-28

  29. UAV air vehicle application • The minimum data required are number of personnel (maintenance and operators), flight hours (FH), direct cost per FH, other direct cost and indirect personnel • Predator for example has 13.75 persons per air vehicle. At $45K per person per year (FY 97 est.), personnel costs would be $620K/year per air vehicle • Also assuming an indirect personnel cost ratio of 25%, annual indirect costs would be $155K • Assuming 1000 FH per year at $75/FH (chart 13-24 @ 100 kts), air vehicle operating costs would be $75K • Payload O&S is estimated at 8% procurement cost/year = .08*(450lb*$5000/lb) = $180K • Ground station plus comms is also estimated at 8% or cost/year = 0.08*(≈$6M) = $480K • Estimated annual O&S cost for Predator, therefore, would be about $1.5M per air vehicle Life Cycle Cost 13-29

  30. Comparison From Defense Airborne Reconnaissance Office (DARO) 1996 Annual Report - Predator 11-12 System LCC (Base-year FY 1996 $M) * RDT&E = $ 213 * Production = $ 512 * O&S, etc. = $ 697 * Total = $1,422 At 3% inflation = $761M in FY99$ Our estimate for 11-12 systems (44-48 vehicles) would be $660 - $720M • - O&S/production = 1.36 or 14% of production cost per year (assuming a 10 year Life Cycle) • - Average manned fighter ratio = 11% Life Cycle Cost 13-30

  31. System cost - summary • Airframe • Development - Equations 13.1 - 13.4 • Procurement - Equations 13.5 - 13.10 • Propulsion (procurement) - Eq 13.11 • Ground Station + communications • Development - 70% air vehicle development • Procurement ≈ 1 air vehicle + sensor payload • Payload (procurement) - $5000/lb • Operations and support • Air vehicle & payload operators - estimate number • Maintenance personnel - chart 12-30 • Other personnel - add 25% • Air vehicle operating costs (inc. engine) - chart 24-27 • Ground station + communications - 8% procurement/yr • Payload - 8% procurement/yr Life Cycle Cost 13-31

  32. Expectations • You should now understand the basic concept design cost issues including • Development • Procurement • Operations and support Life Cycle Cost 13-32

  33. Reading assignment • Raymer, Aircraft Design - A Conceptual Approach • Chapter 3 – Sizing from a conceptual sketch • Chapter 3.1 : Introduction • Chapter 3.2 : Takeoff weight buildup • Chapter 3.3 : Empty weight estimation • Chapter 3.4 : Fuel fraction estimation • Chapter 3.5 : Takeoff weight calculation* • Total : 25 pages • Note – Use Raymer as a reference book. It is not necessary to memorize or derive any of the equations. Read the sections over for general understanding of the concepts. Life Cycle Cost 13-34

  34. Intermission Life Cycle Cost 13-34

More Related