1 / 30

Operating Committee Report

Operating Committee Report. WECC Board Meeting December 7, 2006. Topics. OC Goals Public Service of Colorado Disturbance Reliability Coordination – LeRoy Patterson WECC Mandatory Standards – Don Watkins. 2003 Blackout Recommendations. Status: Complete. Westwide System Model.

ella
Download Presentation

Operating Committee Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Operating Committee Report WECC Board Meeting December 7, 2006

  2. Topics • OC Goals • Public Service of Colorado Disturbance • Reliability Coordination– LeRoy Patterson • WECC Mandatory Standards – Don Watkins

  3. 2003 Blackout Recommendations • Status: Complete

  4. Westwide System Model • Status: Project Will Meet Completion Date • WECC-AREVA Contract Executed November 13, 2006 • Significant Effort on the Parts of LeRoy Patterson and Sarah Dennison-Leonard • Project Kickoff Meeting December 1, 2006 • First Step – Merge 3 Reliability Coordination System Models

  5. WSM – Milestones • Nov 2006 - Contract signed • July 2007 - Start Stages 2 & 3 • Sept 2007 - Stage 1 Complete • Model Delivered • May 2008 - Stages 2 & 3 Complete • State Estimator and Network Applications Delivered

  6. WSM Challenges • Finding a Host Site for WSM • Member Participation and Cooperation

  7. WECC Interchange Tool • Status: Project Will Meet Completion Date • WECC-OATI Contract Executed July 2006 • Stage 1 Pre-Factory Acceptance Testing • November 1-2, 2006 • Stage 2 Factory Acceptance Testing • December 6-7, 2006 • WECC Staff – Eric Langhorst Coordinating Project Development

  8. WIT – Milestones • July 2006 - Contract signed • Jan 2007 - Module 1 In Production • Jan-Dec 2007 – WECC Member Testing & Process Integration • July 2007 - Module 3 Complete • July 2008 - Module 2 Completion

  9. WIT Challenges • Member Participation and Cooperation • Companion Business Practices Approved

  10. Operating Reserve Standard • Status: Multiple Standards In Different Phases of Consideration • BAL-STD-002-1 • Operating Reserve Standards Task Force (ORSTF) Proposal • MIC Will Request Board Approval Consideration

  11. Frequency Response Standard • BAL-00X-1 • Second 60 Day Posting Began Nov 2006 • Extensive Changes to First Version • Static Distribution of FRR Replaced with Dynamic Distribution (System Droop) • Controversial FRR Marketing Restrictions Simplified • Still Controversial

  12. FRS Timeline Recommendation • Jan 2007 - Comment Period Ends • If Comments are Extensive, Another 60 (or 30) Day Posting Will Be Required • Mar 2007 - Joint Meeting/OC Meeting Discussion • Apr 2007 - Board Meeting/Technical Session? • Jun 2007 – OC/MIC Approval • Jul 2007 – Board Approval FPA Section 215 Standard

  13. CRITF Proposal • Contingency Reserve Identification Task Force (CRITF) • Utilize Current E-Tagging Platform and Methodology to Track Movement of Contingency Reserve Transactions Between BAs • Two Business Practices Currently Being Developed

  14. CRITF Proposal Timeline • Business Practices are Currently Drafted • Nov 2006 - Response to Comments • Mar 2007 - OC Consideration • Apr 2007 - BOD Consideration • Dec 2007 - Implementation

  15. Reliability Coordination Strategy • Status: Project Will Meet Completion Date (July 2007) • OC Reliability Coordination Strategy Task Force Formed • 2 OC Representative from Each of the 4 WECC Sub-regions • No Representatives from Current RC Hosts

  16. RC Strategy Current Steps • Hire Consultant • Objective 3rd Party for Specifications, Request for Proposals, and Recommendation • Resolve Controversial Member Issues

  17. RC Strategy Primary Objectives • Infrastructure Host and RC Center Host Specifications, Request for Proposals, and Recommendation • Consultant • Resolve Controversial Member Issues and Consultant Oversight • RC Strategy Task Force • Tool Integration, Training, Staffing • OC Subcommittees, WECC Staff

  18. Tom Botello – SCE Terry Baker – PRPA Steve Cobb – SRP Tom Glock – APS Doug Hincks – AESO Mike McAvoy – CSU LeRoy Patterson –WECC Jerry Rust – NWPP Jan Sharpless - BOD Ken Silver – LDWP John Stout - BOD RCSTF Members

  19. RC Strategy Timeline • Dec 2006 - Select Consultant • Feb 2007 - Define RC Configuration • May 2007 - Consultant Recommends Host Sites • Jun 2007 - OC Approval of Recommendations • Jul 2007 - Board Approval of Recommendations

  20. OC – Other Issues • LDWP Completed its Control Area Certification • Signed Reliability Coordination Empowerment Agreement with CMRC • Renewable Resource Task Force • Creation of Whitepaper Is Behind Schedule • WECC Members Slow to Return Surveys • Future Workshop is Still Planned • WECC Staff Coordinating PCC-OC Activities

  21. PSCO CONTROLLED LOAD SHEDDING 2/18/2006

  22. SUMMARY • Saturday, Feb 18, 2006 • Public Service Company of Colorado (PSCO) Conducted Controlled Outages • 0848 to 1018 MST • 300,000 Total Customers Impacted • 3 Groups Shed for 30 Minute Intervals with 100,000 Customers in Each Group • 428MW Firm Load

  23. Report Team • Fred LeBlanc, WASN, Chair • 17 Members • NERC Included • Colorado Public Utilities Commission Heavily Involved

  24. SUMMARY contd. • February 17 – 18 Presidents Day Weekend • Actual Temperature in Denver was -13F • Temperature Forecast Error Was -14 F • Resulting in Gas LDC Over Burning Due to Forecast Error • Low Gas System Pressure • Interruption of Gas Supply to Electric Generators to Ensure Residential Supply Remained Viable

  25. SUMMARY contd. • 3,132 MW of Generation Capacity Was Forced Off Line • 2,277 MW Due to Freezing/Mechanical Trouble • 855 MW Due to Lack of Natural Gas Fuel • Existing Gas Trading Cycle is not Dynamic Enough to Meet Changing System Conditions • Gas Traders Left Early for Holiday Weekend

  26. SUMMARY contd. • Communication Between Internal PSCO Units Was Not Adequate to Identify Scope of the Problem Early On • Communication with Reliability Coordination Occurred but Follow-up Was Lacking • PSCO Interruptible Procedures Were Out of Date

  27. SUMMARY contd. • PSCO Shed Load for the Loss of the Front Range Power Plant at 454 MW. • The Rocky Mountain Reserve Group Was Reporting 1,000 + MW When Load Shedding Was Initiated • System Operators Acted Appropriately To Initiate Controlled Load Shedding

  28. Recommendation Summary • The Report Includes 22 Conclusions Resulting in 28 Recommendations. Significant Recommendations: • WECC to Request NERC & NAESB to make Gas Trading Cycle More Responsive • WECC Members to Review their Emergency Operating Plans Relative to a Gas Supply Emergency

  29. Recommendation Summary contd. • RDRC Will Review Their Procedures for Actively Soliciting System Information During Unusual Operating Events. • PSCO Shall Improve Their Internal Communication Between Gas Supply, Gas Control, Real-time Dispatch, and Transmission Operations During Fuel and Electric Energy Emergencies

  30. Recommendation Summary contd. • RMRG to Review their Reserve Procedures • PSCO to Review their Weather Forecasting Tools and Processes • Generator Owners Shall Correct Identified Freezing Problems

More Related