240 likes | 510 Views
So what is Level 2 BIM?. An overview of the ‘shrink wrap’. Way back in 2011. 2.32 Government will require fully collaborative 3D BIM (with all project and asset information, documentation and data being electronic) as a minimum by 2016 .
E N D
So what is Level 2 BIM? An overview of the ‘shrink wrap’
Way back in 2011.......... 2.32 Government will require fully collaborative 3D BIM (with all project and asset information, documentation and data being electronic) as a minimum by 2016. A staged plan was published with mandated milestones showing measurable progress at the end of each year.
March 2013 brings • Working to industry standards • Employers Information Requirements • Pre-Contract BIM Execution Plan (BEP) • Post-Contract BIM Execution Plan (BEP) • Common Data Environment • Standards, Methods & Procedures • Information model
And then the ‘shrink wrap’ https://www.innovateuk.org/documents/1524978/1866952/A%20digital%20tool%20for%20building%20information%20modelling%20-%20Functional%20specification
PAS1192-2:2013 PAS 1192-3:2014 BS1192-4:29014 BIM Protocol Government Soft Landings Classification The Digital Plan of Works (DPoW)
1. PAS1192-2:2013 • http://shop.bsigroup.com/forms/PASs/PAS-1192-2/ • Working to industry standards • Employers Information Requirements • Pre-Contract BIM Execution Plan (BEP) • Post-Contract BIM Execution Plan (BEP) • Common Data Environment • Standards, Methods & Procedures • Information model
Academy – 50 Works Packages Assess 10 key design packages – 46 documents Assess all works packages – 206 documents 1399
2. PAS1192-3:2014 shop.bsigroup.com/forms/PASs/PAS-1192-3 Published 31st March 2014 Organisational Information Requirements (OIR) Asset Information Requirements (AIR) Asset Information Model (AIM)
Fig 10. Ensuring data and information governance and assurance
3. BS1192-4:2014 or COBie – UK - 2012 • A formal schema that helps organise information about facilities
http://www.bimtaskgroup.org/cobie-uk-2012/ Due to be published Easter 2014 (August?)
4. BIM Protocols • http://www.bimtaskgroup.org/bim-protocol/ • 2.0 Priority of Contract documents 2.2. In the event of any conflict or inconsistency between a Model prepared and delivered in accordance with this Protocol and any document or information extracted from such Model, except where the Information Requirements states otherwise, the Model shall prevail.
5. Government Soft Landings, GSL http://www.bimtaskgroup.org/wp-content/uploads/2013/02/GSL-Summary-170213.pdf
6. Classification – Uniclass2 http://www.cpic.org.uk/uniclass/ • Co - Complexes • En - Entities • Ac - Activities • Sp - Spaces • EF - Entities by Form • Ee - Elements • Ss - Systems • Pr - Products • Zz - CAD • PP - Project Phases
With thanks to Ian Chapman, NBS. Presentation from July 2013
7. The Digital Plan of Works http://www.bimtaskgroup.org/wp-content/uploads/2013/02/BIM-The-Digital-Plan-of-Work-v7-1.pdf
In Short..... PAS1192-2:2013 How - Construction PAS 1192-3:2014 How – In Use BS1192-4:29014 Exchange BIM Protocol Legals Government Soft Landings The Big Picture Classification Names The Digital Plan of Works (DPoW) What & When
Thankyou! E: duncan.reed@tekla.com M: 07734 740240 T: @djhreed67