VET Credit Conversion System The Project Roadmap: Our main project landmarks By Quarter Mr Matthew Agius – MQC/NCHE
Q1: Months 1 – 3Mar, Apr, May 2011 • Start of 4 WPs in March 2011 • 1: Management (MQC P1) • 2: Development – Review (MCAST P5) • 5: Quality Assurance (MQC P1) • 6: Dissemination (MQC P1) • Completion of Deliverables • DEVPT – First Project MeetingApril 2011
Q2: Months 4 – 6Jun, Jul, Aug 2011 • Completion of WP2 (Development – Review) • Continuation of WPs 1,5 & 6 • Completion of Deliverables • DEVPT – Report Presentation of Qualifications for Conversion • DEVPT – Report Review of Qualifications for Conversion • DISS – Project Website & Logo
Q4: Months 10 – 12Dec 2011, Jan, Feb 2012 • Completion of WP3 (Development – Tools & Methodology) in February 2012 • Continuation of WPs 1,5 & 6 • Completion of Deliverables • MGT – Project Interim ReportFebruary 2012 • DEVPT – Templates & Report for new Qualification Descriptions in terms of ECVET February 2012 • QA – Interim Internal Evaluation Report February 2012
Q5: Months 13 – 16Mar, Apr, May 2012 • Start of WP4 (Development – Conversion) in March 2012 • Continuation of WPs 1,5 & 6 • Completion of Deliverables • DISS – MCAST Staff SeminarApril 2012 • DISS – ITS Staff SeminarApril 2012 • DISS – ETC Staff SeminarApril 2012 • DISS – CDL Staff & Private VET Providers Seminar April 2012
Q6: Months 16 – 18Jun, Jul, Aug 2012 • Continuation of WPs 1, 4, 5 & 6 • Completion of Deliverables • DEVPT – Report on Conversion Exercise August 2012
Q7: Months 19 – 21 Sep, Oct, Nov 2012 • Completion of WP4 (Development – Conversion) in November 2012 • Start of WP7 (Exploitation) in October 2012 • Continuation of WPs 1,5 & 6 • Completion of Deliverables • DEVPT – Third Project MeetingOctober 2012 • DEVPT – ECVET Conversion ManualOctober 2012 • QA – Report by External Evaluator 2 October 2012
Q8: Months 22 – 24 Dec 2012, Jan, Feb 2013 • Completion of WPs 1,5,6 & 7 in February 2013 • Completion of Deliverables • DISS – Second Project ConferenceJanuary 2013 • MGT – Project Final Report February 2013 • QA – Final Internal Evaluation ReportFebruary 2013 • EXP – Journal PublicationFebruary 2013