1 / 25

Efficient installation of offshore wind farms…also in the future

Efficient installation of offshore wind farms…also in the future. Case study: Burbo Banks Offshore Wind Farm. Rasmus Lund, Siemens Wind Power A/S. Agenda. Siemens’ offshore track record Siemens’ offshore wind turbines Efficient installation of offshore wind farms

emi-whitley
Download Presentation

Efficient installation of offshore wind farms…also in the future

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Efficient installation of offshore wind farms…also in the future Case study: Burbo Banks Offshore Wind Farm. Rasmus Lund, Siemens Wind Power A/S

  2. Agenda • Siemens’ offshore track record • Siemens’ offshore wind turbines • Efficient installation of offshore wind farms • Case study: Burbo Banks Offshore Wind Farm

  3. Worldwide market leader in offshore projects Vindeby, DK  11 turbines (1991) Baltic I, DE  21 turbines1) Middelgrunden, DK  20 turbines (2000) Burbo Banks, UK  25 turbines (2007) Samsø, DK  10 turbines (2002) Lynn / Inner Dowsing, UK  54 turbines (2008) Rønland, DK  4 turbines (2002) Gunfleet Sands, UK  48 turbines1) Rødsand/Nysted, DK  72 turbines (2003) Rhyl Flats, UK  25 turbines1) Frederikshavn, DK  1 turbine (2003) Greater Gabbard, UK  140 turbines1) HornsRev II, DK  91 turbines1) Sheringham Shoal, UK  88 turbines1) Rødsand II, DK  90 turbines 1) London Array, UK  175 turbines1) Hywind, NO  1 turbine (2009) Walney, UK  102 turbines1) Lillgrund, SE  48 turbines (2007) 1) In progress

  4. Two new family members for Siemens offshore • 2.3 MW - 82 m rotor introduced 2002, certified for IEC IA • 2.3 MW - 93 m rotor introduced 2005, certified for IEC IIA • 2.3 MW - 101 m rotor introduced 2009, certified for IEC IIB • 3.6 MW - 107 m rotor introduced 2004, certified for IEC IA • 3.6 MW - 120 m rotor planned for installation late 2009, to be certified for IEC IA/B Siemens’ offshore line-up

  5. Efficient installation is becoming more critical • Larger projects • Projects located further offshore • Year-round installation Trends Increased focus on efficient installation of offshore wind farms

  6. There are many pieces to the puzzle when it comes to efficient installation • Improved wind turbine design for easy interface and safe installation • Well planned onshore pre-assembly and tests at base harbor • Efficient wind turbine component arrangement and planning of installation vessels • Ensuring co-operation with owner and all suppliers in design, planning and execution • Focus on efficient quality control at base harbor • Choice of an efficient buffer system at base harbor Key elements of efficient installation

  7. An example: Burbo Banks

  8. Key project facts • 25 x 3,6 MW • Round 1 UK project: 90 MW output • Tip height 137m above mean sea-level. • Water depth: 7-12 m • Tide: +/- 5m • Distance to shore: 7-12 km • Mean wind speed: 9 m/s • The wind farm is generating enough electricity to power the equivalent of over 80,000 homes 137 m 107 m 83,5 m

  9. Scope of work • 25 pcs SWT-3.6-107 offshore wind turbines • Transportation, installation, commissioning and tests • 34kV switchgear • SCADA system • 5 years service and maintenance

  10. Logistics UK Blades Towers Nacelles Hubs Power units

  11. One vessel for 6.25 turbines

  12. Location

  13. Port layout • Port of Mostyn, UK • Purpose- Logistics centre - Buffer • Arrangement - 45,000 m² • Main tasks at harbor- Pre-assembly- Test - Quality control- Vessel loading

  14. Port layout • Port of Mostyn, UK • Purpose- Logistics centre - Buffer • Arrangement - 45,000 m² • Main tasks at harbor- Pre-assembly- Test - Quality control- Vessel loading

  15. Nacelle loading

  16. Blade loading

  17. Installation jack-up

  18. Tower installation

  19. Nacelle installation

  20. Blade installation

  21. End result • All 25 SWT-3.6-107 wind turbines were successfully installed in 43.5 days, well ahead of schedule

  22. Another example: Lillgrund110 MW – 48 x SWT-2.3-93

  23. Example 3: Lynn & Inner Dowsing194 MW – 54 x SWT-3.6-107

  24. Example 4: HywindThe world’s first floating WTG – 2.3 MW – 1 x SWT-2.3-82

  25. Successes and lessons learned • Pre-assembly and tests at base harbor • Arrangement of installation vessels • Installation within time schedule • Very good co-operation with clients and subcontractors • Detailed planning of all phases early in the project • Importance of pre-assembly setup and efficient quality control at base harbor • Importance of an efficient buffer system • Sufficient time lag between difference project phases Successes Lessons learned

More Related