System to Monitor & Evaluate Reconstruction Progress: RANdatabase Case Study. Eddie R Darajat Chief Information Officer Pusat Data & Informasi (Pusdatin) Badan Rehabilitasi & Rekonstruksi NAD-NIAS. The 10th World Bank Seminar Series (Roundtable Seminar) Banda Aceh, 27 March 2008.
E N D
System to Monitor & Evaluate Reconstruction Progress: RANdatabase Case Study Eddie R Darajat Chief Information Officer Pusat Data & Informasi (Pusdatin) Badan Rehabilitasi & Rekonstruksi NAD-NIAS The 10th World Bank Seminar Series (Roundtable Seminar) Banda Aceh, 27 March 2008
Background Earthquake & Tsunami on 26 December 2004 & 28 March 2005
The Fact Nanggroe Aceh Darussalam & Nias
Challenge: How to facilitate and coordinate all stakeholders Donors & Implementers Geographical Areas Projects
Tools requirements provides up to date, transparent and accountable information on the recovery process enable Partners to plan and coordinate their projects with other actors working in the same sectors and locations. allows BRR to coordinate more effectively, pinpoint overlaps and publish reports shows who’s doing what to the world
RAND (Recovery Aceh Nias Database) http://rand.brr.go.id
Concept Note Approval Process Concept Note Submission by Donors & Partners Approval Workshop by Deputy / Expert from BRR, UN, Organization Related Updating Project by Donors, Partner Result Projects Approved (with Unconditional approval ; Conditional approval) ; or Projects Not Approved: (Holding Bay or Turn down) critical information : key performance indicators funding source sector location budget allocation Updated data For monitoring, evaluation report and analysis
Concept Note Approval Process 42 Batch Workshop has been conducted +1700 PCN Submitted 1489 project approved
Integrated team (tim terpadu) • Unit under BRR representing various government institutions that acts as a “one stop shop” • Tax exemption • Import document processing • Visa/work permit, etc. One Stop Services to support partners in build back better process
Output Report Generating Generate customized reports “on-the-fly” based on parameters specified by users
Output Who’s, Doing What, Where
Output Thematic Map
Output Report Example Donor Figure by Funding Agency Type Number of Partner by Sector (%)
RAND FactSheet Commitment : USD 3,4 billion Disbursement : USD 2,2 billion 1489 projects 578 funding agencies 487 implementing partners 23 districts 266 sub districts 2688 villages Status as of February 25, 2008
Output Displayed on www.e-aceh-nias.org QuickStat
Output Key Performance Indicators on RAND
Output Key Performance Indicators Reference for Asset Data Project progress Key Element for Reports + 200 KPI • number of fishlanding rehabilitated • number of elementery school, junior high school, senior high school build • number of houses built • number of livestock provided • number bridges rebuilt • number of loans provided • area of mangrove restored • etc..
Output Supported Publication
Benefit Data Mining generate reports by cross tabulation or relationship of project variables Data Analysis provide perspectives for gap analysis such as sector and location gap of Finance and KPIs Decisions Making Tool assist planning, evaluation and coordination; provide sources for benchmarking, lessons learned and data sharing
Implementation • Role of BRR Outreach Team • Encourage organizations to update • Drop In Centre • Train how to use RAN • Provide report as requested • Trouble shooting
Compliance Rate Start from August 2007, Pusdatin in assistance with UNORC’s Aid Coordination Adviser implemented Compliance Rate Updating Program aimed in enhancing data quality & realizing benefits of RAN through an improvised updating monitoring mechanism & concerted outreach campaign Completed project Last Update within 1 month Last Update within 2-3 months Last Update older than 3 months
What Next? Future Use of RANDatabase As a reference for Tsunami rehab/recon projects Provide info for NGO Assets transferred to PemdaAs library/reference by students, public, etc Extra Potential • Could be used as powerful tool for Pemda NAD (In Vietnam is used by Ministry of Finance) • To record/monitor Pemda projects • To improve transparency of Pemda projects • Can be accessed by public in all Kabupaten/Kota • As a role model for other provinces
Preparation For Handover • Define Custodian • Capacity Building on RAN database • Explore Future Use