90 likes | 372 Views
2. . Senate Bill 100 requiresDesignate
E N D
1. 1 CCPGSenate Bill 100Lamar Front Range Update August 19, 2010
2. 2 Senate Bill 07-100 Upon recommendations by the 2006 Transmission Task Force on Reliable Electricity Infrastructure, the Sixty Sixth General Assembly passed Senate Bill 07-100. Under SB 07-100, PSCo must meet the following requirements:
Designate Energy Resource Zones (ERZ)
Develop plans for the construction or expansion of transmission facilities necessary to deliver electric power consistent with the timing of the development of beneficial energy resources located in or near such zones
Consider how transmission can be provided to encourage local ownership of renewable energy facilities
Submit proposed plans, designations, and applications for certificates of public convenience and necessity to the commission for simultaneous review
rts Upon recommendations by the 2006 Transmission Task Force on Reliable Electricity Infrastructure, the Sixty Sixth General Assembly passed Senate Bill 07-100. Under SB 07-100, PSCo must meet the following requirements:
Designate Energy Resource Zones (ERZ)
Develop plans for the construction or expansion of transmission facilities necessary to deliver electric power consistent with the timing of the development of beneficial energy resources located in or near such zones
Consider how transmission can be provided to encourage local ownership of renewable energy facilities
Submit proposed plans, designations, and applications for certificates of public convenience and necessity to the commission for simultaneous review
rts
3. 3 2009 SB-100 Transmission Plan
4. 4 2009 SB-100 Transmission Plan
5. 5 SB-100 2010 Activities Pawnee Smoky Hill 345kV Project
CPCN Approved in 2009
Local Permitting
SLV Calumet Comanche
Hearings: Feb 1-11, 2010
Additional Hearings: July 26, 30, 2010
Missile Site 345 kV Substation
No CPCN Required by PUC Order
Lamar Front Range
Studies in Process
6. 6 Lamar Front Range Scope Purpose: evaluate transmission alternatives to reliably alleviate existing constraints that inhibit potential resource development in southeast and east central Colorado from reaching electrical customer loads along the Front Range.
Accommodate resource development in ERZ #3 (GDA 6) and ERZ #2 (GDA 5, 7)
Interconnect Lamar/Vilas to Comanche & Missile Site
Two Primary Alternatives
Eastern Corridor
Central Corridor
7. 7 Lamar Front Range Alternative 1
8. 8 Lamar Front Range Alternative 2
9. 9 Questions