An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Connecticut Education NetworkSpring 2002 Deployment Group Meeting Department of Information Technology January 4th, 2002

  2. Meeting Agenda Commission for Educational Technology Connecticut Education Network Deployment plans for Spring/Summer 2002 • Phase 2 Technical Design and Logistics • Management / Support • Content Questions & Answers

  3. Commission for Educational Technology • Oversee Educational Technology efforts in Connecticut. • Establish the Connecticut Education Network. • Establish rigorous standards in technology competency for students, teachers, and administrators. • Assist in the development of the Connecticut Parent Technology Academy. • Establish the Connecticut Digital Library.

  4. Commission Composition • 20 Commissioners • 5 Agency Commissioners • DOIT, SDE, State Library, DPUC, SDHE • UConn, CSU, CommTech Colleges, Charter Oak • Leaders from K-12, Business, libraries • CET replaces JCET • DOIT assigned as primary lead on network http://www.ctedtech.org

  5. Connecticut Education Network “A five-year plan … to provide state-of-the-art, high-speed, reliable Internet access and video, voice and data transmissions that electronically link all educational institutions in the state, including public and independent institutions of higher education, the state's libraries and all elementary, middle and secondary schools …

  6. Current Activities related to CEN • K-12 and Library School Surveys & Report • Architecture / Engineering / Contracts • Data Center / Network Operations Support • Phase 1 Site Activations • Circuit Installations, Extensions, Equipment installation • Cutover planning / Execution • Phase 2 Sites

  7. CEN Basics • Backbone Engineered for “Peak” throughput • All edge links => 155 Mbps • All core links => 622 Mbps • An “optical” grade connection for every district & campus • Hand-off is 100BaseT or 1000BaseT Port • Router and/or switch provided at each edge site • Internet Service “included” for K12 & Libraries • N2H2 based Filtering & Firewall through DOIT • A local responsibility to link remote sites to CEN hub in each district • DOIT will assign 10.128 to 10.143 for each K12 district • Higher Education Sites use their own addressing & ISP • Served hosts may receive a CTEDTECH.ORG DNS entry

  8. N O R T H C A N A A N H A R T L A N D C O L E B R O O K U N I O N S O M E R S S U F F I E L D L I S B U R Y E N F I E L D T H O M P S O N N O R F O L K G R A N B Y W O O D S T O C K C A N A A N E A S T G R A N B Y E L L I N G T O N W I N D S O R B A R K H A M S T E D L O C K S W I N C H E S T E R P U T N A M E A S T W I N D S O R W I N D S O R T O L L A N D W I L L I N G - A S H F O R D E A S T F O R D T O N S I M S B U R Y P O M F R E T C A N T O N G O S H E N C O R N W A L L N E W B L O O M - S O U T H V E R N O N H A R T F O R D F I E L D W I N D S O R T O R R I N G T O N K I L L I N G L Y C O V E N T R Y M A N S F I E L D B R O O K L Y N A V O N C H A P L I N M A N - W E S T H A M P T O N C H E S T E R H A R T F O R D E A S T B U R L - H A R T - H A R T F O R D H A R - I N G T O N F O R D B O L T O N W I N T O N L I T C H F I E L D A N D - W A R R E N O V E R F A R M I N G T O N W I N D H A M W E T H E R S - C O L U M B I A P L A I N F I E L D F I E L D G L A S T O N B U R Y N E W I N G - T O N M O R R I S S C O T L A N D C A N T E R B U R Y T H O M A S - B R I S T O L N E W P L A I N - P L Y M - T O N B R I T A I N V I L L E O U T H W A S H - L L I H K Y C O R I N G T O N H E B R O N B E T H - M A R L - S P R A - L E H E M B O R O U G H G U E W A T E R - C R O M W E L L F R A N K L I N V O L U N N W O L C O T T B E R L I N T O W N S O U T H - O N E W M I L F O R D B I N G T O N S P O R T L A N D G R I S W O L D I L W O O D B U R Y E A S T S H E R - C O L C H E S T E R H A M P T O N M A N R O X B U R Y N O R W I C H B O Z R A H W A T E R B U R Y M E R I D E N M I D D L E T O W N B R I D G E - M I D D L E - W A T E R C H E S H I R E B U R Y M I D D L E - F I E L D P R E S T O N P R O S - N A U G A - P E C T N E W T U C K S A L E M N O R T H F A I R F I E L D S O U T H B U R Y E A S T H A D D A M S T O N I N G T O N B R O O K - H A D D A M M O N T V I L L E W A L L I N G F O R D D U R H A M F I E L D B E A C O N L E D Y A R D F A L L S O X F O R D B E T H A N Y N D A N B U R Y C H E S T E R E N E W T O W N D W A T E R - M N O R T H F O R D S T O N I N G T O N A G R O T O N N R H H A V E N N O R T H V E S E Y M O U R R I P B E T H E L K I L L I N G - N E W O E E D B R A N - S E A S T W O O D - W O R T H L O N D O N I F O R D D A N - L Y M E B R I D G E A E S S E X S O N I A M D E M O N R O E R O L D B Y N N E W O L D L Y M E O W E S T - T N H A V E N S A Y - R I D G E - R E D D I N G G U I L F O R D S H E L T O N E N B R O O K B R O O K I V F I E L D L A C B R A N F O R D H O R A N G E T W E S T S A H A V E N E T R U M B U L L E A S T O N M I L F O R D W E S T O N D R O F B R I D G E - T W I L T O N A P O R T R T F A I R F I E L D S N E W C A N A A N W E S T P O R T N O R W A L K S T A M F O R D D A R I E N G R E E N W I C H M a s s a c h u s e t t s S A S T A F F O R D S H A R O N N k R K E N T G r N h I o L o R E Y T d S e w I e s l N a n L E B A N O N d T O W N L Y M E Phase 1 Higher Ed Sites Phase 1 K12 Activities (Winter 2001-2002) Phase 2 Activities (Spring 2002) Phase 3 Activities (Summer 2002 – Spring 2003) 5 0 5 1 0 1 5 2 0 2 5 3 0 M i l e s M a y 1 2 , 2 0 0 0

  9. Phase II CEN ActivitiesFinal Planning now / Implementation Spring & Summer • Gigabit Ethernet in South Central CT • 20 Year Lease of Fiber Cables by Contract • DOIT (State) Master Agreement • Monitoring, Maintenance, Repair by vendor • Contract available to towns, state agencies and higher education institutions • Additional ATM Locations for “2nd six” • Redundancy in ISP services

  10. Phase II Installation Activities • Verification of Building Entry Conduits • Design / Evaluation for necessary construction • Verification of Demarcation Points • Finalization of backbone hub sites • Looking for UPS/Generator, 24h Access, 2 racks • IP routing, DNS, addressing information • Development of individual cutover plans • Installation of backbone fiber and equipment • Installation of edge site fiber and equipment

  11. CEN Fiber Backbone October 2001 4 Strands for delivery in Spring 2002 Future CEN backbone expansion

  12. N O R T H C A N A A N H A R T L A N D C O L E B R O O K U N I O N S O M E R S S U F F I E L D L I S B U R Y E N F I E L D T H O M P S O N N O R F O L K G R A N B Y W O O D S T O C K C A N A A N E A S T G R A N B Y E L L I N G T O N W I N D S O R B A R K H A M S T E D L O C K S W I N C H E S T E R P U T N A M E A S T W I N D S O R W I N D S O R T O L L A N D W I L L I N G - A S H F O R D E A S T F O R D T O N S I M S B U R Y P O M F R E T C A N T O N G O S H E N C O R N W A L L N E W B L O O M - S O U T H V E R N O N H A R T F O R D F I E L D W I N D S O R T O R R I N G T O N K I L L I N G L Y C O V E N T R Y M A N S F I E L D B R O O K L Y N A V O N C H A P L I N M A N - W E S T H A M P T O N C H E S T E R H A R T F O R D E A S T B U R L - H A R T - H A R T F O R D H A R - I N G T O N F O R D B O L T O N W I N T O N L I T C H F I E L D A N D - W A R R E N O V E R F A R M I N G T O N W I N D H A M W E T H E R S - C O L U M B I A P L A I N F I E L D F I E L D G L A S T O N B U R Y N E W I N G - T O N M O R R I S S C O T L A N D C A N T E R B U R Y T H O M A S - B R I S T O L N E W P L A I N - P L Y M - T O N B R I T A I N V I L L E O U T H W A S H - I L L H K Y C O R I N G T O N H E B R O N B E T H - M A R L - S P R A - L E H E M B O R O U G H G U E W A T E R - C R O M W E L L F R A N K L I N V O L U N N W O L C O T T B E R L I N T O W N S O U T H - O N E W M I L F O R D B I N G T O N S P O R T L A N D G R I S W O L D I L W O O D B U R Y E A S T S H E R - C O L C H E S T E R H A M P T O N M A N R O X B U R Y N O R W I C H B O Z R A H W A T E R B U R Y M E R I D E N M I D D L E T O W N B R I D G E - M I D D L E - W A T E R C H E S H I R E B U R Y M I D D L E - F I E L D P R E S T O N P R O S - N A U G A - P E C T N E W T U C K S A L E M N O R T H F A I R F I E L D S O U T H B U R Y E A S T H A D D A M S T O N I N G T O N B R O O K - H A D D A M M O N T V I L L E W A L L I N G F O R D D U R H A M F I E L D B E A C O N L E D Y A R D F A L L S O X F O R D B E T H A N Y N D A N B U R Y C H E S T E R E N E W T O W N D W A T E R - M N O R T H F O R D S T O N I N G T O N A G R O T O N R N H H A V E N N O R T H V E S E Y M O U R R I P B E T H E L K I L L I N G - N E W O E E D B R A N - S E A S T W O O D - W O R T H L O N D O N I F O R D D A N - L Y M E B R I D G E A E S S E X S O N I A M D E M O N R O E O L D R B N Y N E W O L D L Y M E O W E S T - N T H A V E N S A Y - E R I D G E - R E D D I N G G U I L F O R D S H E L T O N N B R O O K V B R O O K I F I E L D A L H C B R A N F O R D T O R A N G E W E S T S A H A V E N E T R U M B U L L E A S T O N M I L F O R D W E S T O N D R O F B R I D G E - T W I L T O N A P O R T R T F A I R F I E L D S N E W C A N A A N W E S T P O R T N O R W A L K S T A M F O R D D A R I E N G R E E N W I C H M a s s a c h u s e t t s S A S T A F F O R D S H A R O N N k R K E N T G r N h I o L o R E Y T d S e w I e s l N a n L E B A N O N d T O W N L Y M E Phase 1 Activities (present) Phase 2 Activities (Spring 2002) Phase 3 Activities (Summer 2002 – Spring 2003) 5 0 5 1 0 1 5 2 0 2 5 3 0 M i l e s M a y 1 2 , 2 0 0 0

  13. Core sites are fully redundant and run a separate backbone between sites • Gig-E links between schools are cascaded along the route to optimize fiber • CWDM or DWDM can be employed when GigE insufficient

  14. What do you need to do? • Maintain / Upgrade in-district networks • Watch contract renewal dates • Verify & Keep current Information we have • Network Diagram • IP Addressing & config to your current ISP • Demarcation Street Address • WAN plans you have in the district • Help plan/install fiber cable installation • Help keep schedules tight, communicate issues (site visits) • Monthly -> Biweekly Conference Calls

  15. Other Issues • Connections to Libraries • Municipal Connections & ISP Services • Service Level Agreements • Options for WAN services through DOIT contracts

  16. Phase III Thoughts • Hoping to receive funding to reach the (entire) rest of state next fiscal year • Increasing volume means we need to streamline cutover processes • Expect to issue another RFP for additional leased fiber services • Crossover with Municipal & Government Network planning increasingly important

  17. CEN Website http://www.doit.state.ct.us/cen FAQ’s Architecture Engineering Status Monitoring / Traffic Monitoring

  18. Questions & DiscussionContact Information: Rob Vietzke, CEN Network Architect 860-622-2238 Rob.Vietzke@uconn.edu John Vittner, CEN Implementation Manager 860-622-2241 John.Vittner@po.state.ct.us Bob Dixon, Director of Enterprise Network Services 860-622-2435 Robert.Dixon@po.state.ct.us Michael Helfgott, Executive Director, CET 860-622-2522 Michael.Helfgott@po.state.ct.us www.doit.state.ct.us/cen