Lafayette New Terminal Program Update May 8, 2019
EDA Grant Application • Funding Approved • Coordinating additional information TSA OTA Application • Submitted Grant Application, unfunded in 2019 Airlines • Working with airlines to discuss leasable space and an agreement to buildout space QTA/Ready Return Concessions Terminal Program Update - Funding
Enabling Demo • Construction Complete. Final Acceptance upcoming Rental Car Quick Turn Around Facility (QTA) Construction: • Notice to Proceed (NTP) 4/15/19; Scheduled Completion Q1 2020 • Upcoming Construction Activities • Earthwork, demo existing utilities, tie in new utilities Terminal Program Update – Projects
Program Package 1: RTR, Enabling Projects and Terminal Foundations Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update – Projects Program Package 2: Structural Steel, Elevators and Escalators Approved 1/15/19, Notice to Proceed 1/15/19 Program Package 3: Terminal Building Shell, MEP and Finishes Terminal Building Shell, MEP and Finishes - Bid and Award March – June 2019
New Terminal Program Progress: Day 1 Progress: Day 176
Project 2 – RTR Facility • Final interior finishes (VCT floor, paint, testing/commissioning equipment) • Seeding laydown areas • May/June completion GMP 1 – Project 2 RTR Facility
Project 3 – Terminal Foundations • Construction piers, grade beam, pilasters and anchor bolts – ongoing • Underground utilities – ongoing GMP 1 : Project 3 Terminal Foundations
Project 3 – Terminal Foundations • Completion July 2019 GMP 1 : Project 3 Terminal Foundations
Project 5 – Enabling Parking • Phase 3B - Substantial completion short term parking lot • Phase 3A • Soil Stabilization – under engineer/PM review • Asphalt and fencing – ongoing GMP 1 – Project 5 Enabling Parking