An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lafayette New Terminal Program Update May 8, 2019

  2. Terminal Program Update - Funding

  3. EDA Grant Application • Funding Approved • Coordinating additional information TSA OTA Application • Submitted Grant Application, unfunded in 2019 Airlines • Working with airlines to discuss leasable space and an agreement to buildout space QTA/Ready Return Concessions Terminal Program Update - Funding

  4. Enabling Demo • Construction Complete. Final Acceptance upcoming Rental Car Quick Turn Around Facility (QTA) Construction: • Notice to Proceed (NTP) 4/15/19; Scheduled Completion Q1 2020 • Upcoming Construction Activities • Earthwork, demo existing utilities, tie in new utilities Terminal Program Update – Projects

  5. Program Package 1: RTR, Enabling Projects and Terminal Foundations Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update – Projects Program Package 2: Structural Steel, Elevators and Escalators Approved 1/15/19, Notice to Proceed 1/15/19 Program Package 3: Terminal Building Shell, MEP and Finishes Terminal Building Shell, MEP and Finishes - Bid and Award March – June 2019

  6. New Terminal Program Progress: Day 1 Progress: Day 176

  7. Project 2 – RTR Facility • Final interior finishes (VCT floor, paint, testing/commissioning equipment) • Seeding laydown areas • May/June completion GMP 1 – Project 2 RTR Facility

  8. Project 3 – Terminal Foundations • Construction piers, grade beam, pilasters and anchor bolts – ongoing • Underground utilities – ongoing GMP 1 : Project 3 Terminal Foundations

  9. Project 3 – Terminal Foundations • Completion July 2019 GMP 1 : Project 3 Terminal Foundations

  10. Project 5 – Enabling Parking • Phase 3B - Substantial completion short term parking lot • Phase 3A • Soil Stabilization – under engineer/PM review • Asphalt and fencing – ongoing GMP 1 – Project 5 Enabling Parking