1 / 43

PV grid penetration in public grid Kosrae Utility Authority

PV grid penetration in public grid Kosrae Utility Authority . APAC – ADB meeting Manilla Fred Skilling - CEO June 2011. Kosrae – Key Energy Statistics. Current situation in Kosrae. Energy Action Plans of Kosrae State. AIM : become less dependent on imported fossil fuels

enya
Download Presentation

PV grid penetration in public grid Kosrae Utility Authority

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PV grid penetration in public gridKosrae Utility Authority APAC – ADB meeting Manilla Fred Skilling - CEO June 2011

  2. Kosrae – Key Energy Statistics

  3. Current situation in Kosrae

  4. Energy Action Plans of Kosrae State AIM : • become less dependent on imported fossil fuels • Provide affordable and stable electricity to all Kosrae households and business BY: • Introducing more RE sources • Improving the grid-efficiency

  5. Energy Action Plans – RE section Total Capacity that KUA want to install is 400 kWh / 2009 action plans mentioned a gradually approach but can be speed-up after evaluating existing installations. under EDF-9 -> 56kWp installed and results very satisfying. • Phase 1: PV grid connected plant at KUA, ground mounted 200 kWp. • Phase 2: 100 kWp at government buildings and upgrade of KUA’s plant with another 100 kWp

  6. Ongoing1.5 MW Wave energy power plantIPP structure under a PPA with KUAEstimated purchase kWh rate: 0.10 - 0.15 USD / kWhGeneration cost: 0.02 USD / kWhOperation of wave power plant: end 2011

  7. Kosrae’s Approach • 2 high priority projects on action plan: • 1st Grid – connected solar • 2nd wave energy • KUA has started preparing both projects • in the meanwhile looking for other solutions for other technologies • KUA has started planning for IPPs (Solar-Wind Hybrid etc) • Work parallel on all these projects

  8. Funding for the additional 400 kWp PV • Rough price estimate: US$ 2,400,000 ($6,000/kWp) • Project implementation in two phases: • 150 kWp with EU EDF-10 funding (= $900,000) • 250 kWp with either use of the Japan PEC fund or a combination of a grant and a loan as matching grant. • KUA is also stimulating private investors to start an IPP (Independent Power Producer) under a PPA (Power Purchase Agreement) arrangement • Interest in this is showed by two PV companies

  9. Kosrae’s picture for 2012

  10. Why KUA’s interest in Renewable Energy ? • Before 2008 => 100% dependent on diesel • In 2008 => installed 52.5 kWp PV grid connected solar on 5 different locations: 1 car park shading and 4 rooftop installations • Results for utility very satisfactory • Wave Energy: generating cost very low => IPP • Becoming less dependent on expensive imported fossil fuels! • Provide electricity to KUA’s customers' for an affordable rate

  11. Why Grid connected PV? • The sun is the best-measured renewable energy resource in the pacific countries • Crystalline PV modules have a proven track record in the pacific • Amorphous panels are being introduced as test in Kosrae in 2008 (1 kWp) • Suited for Pacific context of limited land availability: no additional land required if the PV arrays are on roofs • Scalable technology • Low maintenance, as there are no batteries

  12. PV prices are coming down! In 2008… Kosrae: 8.17 €/Wp World prices Niue: 6.76 €/Wp

  13. Grid connected PV in Kosrae • The previous table showed prices in Euro • Today the price of grid connected PV solar (installed) is between USD 4.50 / Wp and USD 6.75 / Wp installed in the Pacific. • This means that from 8 euro (= USD 11.25) the price went down to USD 5.50 or more than 40% !

  14. Current trend… • Currently, projects in the Pacific can expect: • PV modules: 3.00 – 4.00 US$/Wp • Inverters: 0.50 US$/W • Installed systems: 5.50 US$/Wp And theseprices are going down…

  15. PV Grid connected systems in Kosrae

  16. System Overview • Crystalline modules chosen for their proven track record • One small system with Amorphous modules (1kW) • Extended warranties purchased on all inverters • Total of 6 systems: 5 are roof-mounted and 1 is on car park shading • Data loggers installed on all systems

  17. Price per kWh(current rate in Kosrae: 39 US¢/kWh Yes indeed… installing Grid Connected PV is a financially attractive alternative!

  18. Current Systems • 52.5 kWp installed on roofs of airport, legislature, hospital, governor’s office, and KUA car park • 1 kWp installed on the recycling plant • Installed in September 2008 • Average production 5,800 kWh/mo. • Specific yield: 1,340 kWh/kWp/yr

  19. Energy Assessment Issues Raised 1- Supply and Installation of 5 PV Grid-Connected Systems: • Faulty Inverter at the Airport installation 2- Maintenance of the PV Systems: • Issue of the Solar PV Tariff system. 3- Monitoring of PV Systems: • Monitoring of the 5 PV grid-connected systems. 4- Project Impacts: • Beneficiaries and Public awareness and perception of the PV systems.

  20. Existing PV System’s Present Status as Monitored • Faulty Inverter at airport installation was replaced in November 2010 - No problems since • Solar panels are guaranteed for 20 years, Inverters and other electronic equipments are guaranteed for 5 years • On line monitoring of the PV grid-connected systems not yet in operation but high on the wish list • All systems are performing well and as utility we are keen to increase the PV penetration to 500 kWp • Awareness and information to end-users important Next slide will give you an overview of the performance of the PV systems

  21. Airport

  22. Airport System

  23. Airport - Cont.

  24. KUA’s car-park system

  25. KUA car park system

  26. KUA – Cont.

  27. Governor’s office

  28. Governor’s office

  29. Governor's office – Cont.

  30. Hospital

  31. Hospital System

  32. Hospital – cont.

  33. Legislature office

  34. Legislator office system

  35. Legislature – Cont.

  36. Generation till end 2010

  37. Total (2009 – 2010) for the 5 buildings

  38. 2011 – 1st and 2nd quarter

  39. KUA’s and Kosrae’s future • Between 2012-2014 → 57% renewable • In 2015 ….

  40. Kosrae’s picture for 2015 • PV – 20 % • Wind – 5% • Wave – 50 % • Diesel – 25% • In other words: 75% renewable

  41. Concluding note: • PV grid connected solar systems is a viable option for Kosrae • 1st phase additional 400-500 kWp • 2nd phase 500-750 kWp • 1.5 MW Wave Power plant in progress • Kosrae and KUA are actively looking for energy efficiency measurements – DSM and SSM • KUA interested in SMART-grid • Together we are working on becoming less dependent on the pollutive and expensive fossil fuel

  42. Thank You KuloMaluhlap

More Related