1 / 10

Columbus, Mississippi Air Toxics Study

Columbus, Mississippi Air Toxics Study. Jerry Beasley, Ph.D., P.E. Mississippi Dept. of Environmental Quality 2013 Metro 4-SESARM Spring Grants/Planning Meeting May 21, 2013. Project Purpose.

erek
Download Presentation

Columbus, Mississippi Air Toxics Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Columbus, MississippiAir Toxics Study Jerry Beasley, Ph.D., P.E. Mississippi Dept. of Environmental Quality 2013 Metro 4-SESARM Spring Grants/Planning Meeting May 21, 2013

  2. Project Purpose • Address concerns in the community about toxic air emissions and also reports of creosote odors and emissions continuing to occur from the old Kerr-McGee plant site. • Until 2003, the Kerr McGee Chemical Corporation used creosote and creosote tar solutions or pentachlorophenol to make pressure treated wood products. Contamination was later discovered in sediment samples from off-site drainage ditches and in soil samples from private residences.

  3. Site Location – Lowndes County

  4. Columbus Air Toxics Monitoring Sites Proposed SVOC Monitoring Site (3 Months) Columbus Brick Distances (Closest point on site to the monitor locations) Columbus Brick – KMMS =0.34 miles KMMS – Sanderson = 0.16 miles Sanderson – SBMS = 0.41 miles KMMS – SBMS = 0.7 miles Kerr-McGee Monitoring Site (KMMS) VOC & SVOC (3-months) Sanderson Plumbing Stokes-Beard Elementary Monitoring Site (SBMS) VOC

  5. VOC/SVOC Monitoring Trailer

  6. VOC Sampling • 60 VOCs started being monitored in January 2013 • 1 in 6 days – 24 hour samples • The VOC sites are the Kerr-McGee site and the Stokes-Beard Elementary School Site. • Sanderson Plumbing is a toilet site and custom molding manufacturer where its HAPS are emitted from surface coating operations. • Columbus Brick uses natural gas-fired dryers and kilns. The HAPs are emitted from the actual drying of the bricks.

  7. SVOC Sampling • A separate sampler is used to collect SVOC samples at the Kerr-McGee property. • 22 SVOCs started being monitored in April 2013 and will operate for a period of three months. The monitor will then be moved to another location on the property and operated for three months. • 1 in 6 days – 24 hour samples

  8. Stokes-Beard ElementaryPreliminary VOC Data

  9. Kerr-McGeePreliminary VOC Data

  10. For more information, please contact: B.J. Hailey (601) 961-5783 bhailey@deq.state.ms.us