Under Test End Dates. 1 st February 2011. Context. Business Process for a Generator Unit Under Test Involves email communication between TSOs and SEMO Mod 33_10 provided for clear set of steps for and the timings involved in a Generator Unit being granted Under Test status
E N D
Under Test End Dates 1st February 2011
Context • Business Process for a Generator Unit Under Test • Involves email communication between TSOs and SEMO • Mod 33_10 provided for clear set of steps for and the timings involved in a Generator Unit being granted Under Test status • Issue is with cancellation of test dates • Flexibility of unit to declare available following an outage • Mod 65_08 delivers the flexibility
Options TSO and SEMO have reviewed this request for increased flexibility: • Reduce 2 WD notice for change to 1 WD • Incorporate in Validation of TOD process • Move to calendar day process for approval • Deliver Mod 65_08(V2) as this allows testing to be cancelled via EDIL