An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vendor Forum Thursday, November 13, 2003 Auditorium 3000 George Washington Way Richland, WA 5:00pm – 6:30pm

  2. Topics • Bid Process • Scheduling • Minimizing and Controlling Change • Quality Expectations • Packaging and Shipping for Construction • Invoicing

  3. Bechtel Field Procurement Representatives • Frank McAlpin • Material Specialist • Luz Almonte • Field Purchasing • Darby Gaynor • Field Expediting • Andrea Rocha • Accounts Payable • Noelle Michaelson • Training/E-Procurement • Tony Paredes • Field Purchasing Manager • John Gorski • Marshaling Yard Manager • John Burke • Purchasing/Special Services Supervisor • Dan Richards • Field Purchasing Supervisor • Carrie Brittain • Small Business Program

  4. Bid Process Flow Chart

  5. Bid Process • Read the entire document! • Provides a better understanding of the scope of work • Easier to identify and resolve discrepancies. • Saves time and money for both Bechtel and the vendor.

  6. Purchase Order Requirements • Commercial Requirements • Technical Requirements • Schedule Requirements • "Or Equal" means buyer approved equal. Approval must be obtained prior to any award being made. In no event should alternate materials be delivered, prior to approval of substitution/deviation. Unapproved materials may be returned to Seller, and any associated charges shall be to the Seller's account.”

  7. Scheduling • Importance to RPP/WTP: • Efficient Performance • Ability to meet construction dates • On-time start up • Creates a solid base line to measure progress

  8. Scheduling • RPP/WTP Milestone Dates Measure: • Progress against the plan • Early warnings of problems • Corrective action, if needed • Timely payments • Deviations from the schedule costs the project thousands of dollars a day!

  9. Scheduling Metrics • Data Collection Process: • Based on Original Promise Date • If material is received prior to or on the date = On-Time • If material is received after the date = Late

  10. Proactive vs. Reactive to Change • Completely understand the scope of work • Plan for potential changes: • Develop a strategy if they occur • Optional items that may be needed later • Notification of changes need to be made as soon as possible.

  11. Quality • As a supplier, your biggest responsibility is to ensure that your products conform to the PO requirements. • Bechtel Quality Program Goals • Ensure that awards are given to capable suppliers. • Communicate unique project requirements to suppliers. • Ensure fulfillment of all requirements. • Communicate early identification of discrepancies

  12. UOS&D • Unsatisfactory, Overage, Short and/or Damaged • Occur during receipt inspection • Hold Payment until discrepancy is resolved

  13. Resolving UOS&D’s • When replacements are required • A new packing slip for shipment • Note on the packing slip which items are being replaced • Note UOS&D number

  14. Packaging and Shipping for Construction • The packaging and shipping requirements are frequently overlooked and underestimated. • The key customer is project construction! • Items that are marked and tagged so they can be efficiently installed. • Intact and clearly identified against Bechtel PO numbers.

  15. Packaging and Shipping for Construction • Keys to successful Shipments • Clear Packing Slip: • Purchase Order Number • Line Item Numbers and Quantity Shipped • Delivery Destination (2579 Stevens Drive or Jobsite) • Clearly Mark all packages with PO Line Item Number • Supporting Documentation • Material Safety Data Sheets (MSDS) • Certificate of Compliance (C of C)

  16. Invoicing • 3 Categories of Invoices • The invoice is correct, the equipment has been shipped and is accepted at the job site. • The invoice has errors that will not permit it to be paid. • The invoice is substantially correct, but some minor elements require clarification/correction.

  17. Invoicing • Final Payment • All back-charges are resolved • Equipment and documentation are received. • All receipt problems are resolved. • Supplier to sub-supplier payment acknowledged.

  18. Summary • READ the Purchase Order and any revision requirements. • Implement an Effective Quality Management System • Demonstrate a Management Commitment to Quality • Adhere to lines of communication • Ask questions

  19. Overall The success of the RPP/WTP Project depends on the success of our suppliers!

  20. Inside Track

  21. fkmcalpi@bechtel.com 371-0399 Thank You For Your Time! Contact: Frank McAlpin