An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WEC Library & Teaching Rooms Refurbishement Project

  2. Project Communication Presentation Purpose of today; For WEC building users to undertand the scope, programme and impact of the summer works. • The team • Scope/areas of work • Key dates • Logistics • Noisy works • Contacts and meetings

  3. The team • Estates Project Manager – Raghbir Nagra • External Project manager – (Mace) Mark Jaloszynski • Design & Build Contractor – (ISG) Andy Thorogood • Client Design Team • Wilson Mason • Elementa • Ross & Partners

  4. Scope of works - Library Presentation title footer

  5. Scope of works - Library Presentation title footer

  6. Scope of works - Library Presentation title footer

  7. Scope of works - Library Presentation title footer

  8. Scope of works – Teaching Rooms Presentation title footer

  9. Scope of works – Teaching Rooms Presentation title footer

  10. Key dates • Teaching room construction 25th June to 17th September • Library closes to staff and students 25th June • Construction works commence 9th July • Library open 15th October ISG operate a double shift 08:00 – 18:00 and 18:00 to 01:00. Noisy works, deliveries and corridor refurb will be undertaken during the 2nd shift to minimise building disruption.

  11. Sp Sp Compound Plan Logistics Temporary toilets Level 2 Gantry Level 1 Gantry Access / egress staircase Storage container 1000kg beam hoist Hoarding Security checkpoint Opening cut into brick wall – gates formed in hoarding

  12. Noisy works • Low impact/noise activities during the day (still will be activities continuing) • Heavy demolition, drilling, cutting to be completed during 2nd shift, post 18:00 and/or weekends • Deliveries and bulk material movements post 18:00 can be via main entrance.…during the day, via scaffold gantry • Lift only used post 18:00 • Corridor refurbishment out of hours • Corridor accessible during the day; always safe and clear

  13. Reporting/communications Questions & complaints

  14. Reporting/communications • External liaison sessions every Tuesday 15:30-16:00 from 3rd July in the WEC Refectory. • Mark Jaloszynski • Ext 5785 or 07734 711522 • (or Jonathan Kirby 07584 317609) • 2nd floor office opposite boardroom • Mark.jaloszynski@macegroup.com • Raghbir Nagra • Ext 6926 or 07787 536 551 • Raghbir.nagra@kcl.ac.uk

  15. WEC Library & Teaching Rooms Refurbishement Project Questions…..