1 / 12

Anthony Indelicato DOE-Princeton Site Office December 2012

U.S. DEPARTMENT OF ENERGY. Office of Science Princeton Site Office. Construction Progress Review for the NSTX Upgrade Project. Anthony Indelicato DOE-Princeton Site Office December 2012. U.S. DEPARTMENT OF ENERGY. Office of Science Princeton Site Office. What’s the proposed workscope?.

eros
Download Presentation

Anthony Indelicato DOE-Princeton Site Office December 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office Construction Progress Review for the NSTX Upgrade Project Anthony Indelicato DOE-Princeton Site Office December 2012

  2. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office What’s the proposed workscope? Increase toroidal field: 0.5T > 1.0T Increase plasma current: 1 MA > 2 MA Increase pulse length: 1.0 s > 5 s Increase NB heating: 5-7MW > 10-14MW New Center Stack Inner TF bundle, TF joint, OH & inner PF coils Reinforce umbrella structure Exst’g outer PF coils – 6 total Upgraded TF coil support structure New PF coil support structure Existing outer TF coils w/ reinstated water cooling Also…modify coil power system, protection system & ancillary support systems

  3. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office Workscope…continued Add 2nd Beamline Decon, recondition and install New NB armor Install 3 HVEs Relocate from TC basement Modify Vacuum Vessel New NB port New Vacuum Pump Duct (below) Also…modify existing power system and ancillary support systems

  4. U.S. DEPARTMENT OF ENERGY How’s spending? Office of Science Princeton Site Office Today $38.9M to go Contingency: $11.3M (or 30% of ‘to go’) $44.1M spent 1/2 Sep 15 Dec 11 Dec 10 Apr 10 Feb 09 CD-0 1/4 3/4 CD-1 TPC=$94.3M CD-2 E F std adv CD-3 CD-4 14 months of schedule contingency (or 52% of ‘to go’) CD-3 Overdrive FY09 FY10 FY11 FY12 FY13 FY14 FY15 $5.2 $9.0 $9.9 $20.5 $22.8 $23.7 $3.2 Budget odometer

  5. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office How’s the performance so far? • SPI = 1.06 & CPI = 1.00 • 54% complete • Contingency = 30% of ‘to go’ costs • Budget at completion = $82.7 • Estimate at completion = $83.9 • Level 2 milestones: • Past = completed on or ahead of schedule • Ahead = early completion anticipated How’s the baseline? • All scope remains as planned. • TPC remains ‘on-target’. • CD-4 date remains ‘on-target’ with promise of early finish. • Concern: FY13+ Presidential Budget

  6. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office Risks and Concerns • NSTX-U future funding profile: • FY 13 President’s budget provides reduced funding to PPPL . . . • Institutional impacts are high • NSTX-U would be adversely impacted : • Reduction in Lab-wide human resource support . . . Added risk. • Slow down of schedule (due to a constrained budget profile) will add cost. • Actions: • PPPL continues to work closely with PSO and FES to understand impacts of the budget cuts. • The Project developed actionable plans based on differing funding scenarios to determine the impacts on the project. • Early delivery date of the project will be significantly reduced, but project can still meet CD-4 baseline date. • Worst case: If FY13 Budget comes in at President’s mark …AND… future year budgets remain at this reduced level for FY14, a re-baselining will be required for this project.

  7. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office Thoughts • The Budget cycle is still unclear for FY13 and beyond. • Too early to react (i.e., re-baseline) . . but precautionary institutional planning must be done. • The NSTX-U Project’s performance is still the #1 priority as stated by PPPL Directorship and agreed upon by FES. • The Project has built a nice buffer in schedule contingency to date . . . this will come in handy if budget is reduced. • Yes . . . there will be added cost risk to the project.

  8. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office Construction Progress? • Overall Progress is good. . . • All construction efforts are well underway • Vendor performance is good overall • Critical Path. . . • Remains through the construction of new Center Stack assembly • Center Stack Fabrication facility is on line • Entering the “riskiest” stage of construction: potting of quadrants & full center bundle, and OH coil winding • Management. . . • EVMS system in place and fully functioning (Annual Internal Surveillance complete) • Construction proceeding well on the accelerated schedule. • All previous Review Recommendations addressed. • Project is getting the resources it needs.

  9. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office Conclusion • Post CD-3 efforts are proceeding well… • Good performance to date. • Good communication between PPPL and Site Office. • Estimates are updated and remain well within plan. • Funding and human resources are in place. • Elements of DOE Order 413.3B are met. PSO, PPPL and FES must work together as the FY13 budget evolves and assess the impact to NSTX-U and PPPL.

  10. Back-up Slides

  11. U.S. DEPARTMENT OF ENERGY Office of Science Princeton Site Office Charge Questions Construction Efforts: Are construction efforts being executed safely? Yes Does the project have adequate resources and the appropriate skills mix to execute the project per the plan? Yes Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Yes Is the contingency remaining adequate for the risks that remain? Yes Management: Evaluate the management structure as to its adequacy to deliver the scope within budget and schedule. Are risks being actively managed? Yes Response to Prior Reviews: Has the Integrated Project Team implemented all required actions in the Corrective Action Plan that was developed following the Project Status review from May 2012? Yes

More Related