100 likes | 218 Views
Construction Progress Review for the NSTX Upgrade Project. Anthony Indelicato DOE-Princeton Site Office February 2014. How’s spending?. Today. $71.2M spent. $17.5M available. 1/2. CD-0. Feb 09. Sep 15. Dec 11. Dec 10. Apr 10. 1/4. 3/4. CD-1. TPC=$94.3M. $5.6M. CD-2. E. F.
E N D
Construction Progress Review for the NSTX Upgrade Project Anthony Indelicato DOE-Princeton Site Office February 2014
How’s spending? Today $71.2M spent $17.5M available 1/2 CD-0 Feb 09 Sep 15 Dec 11 Dec 10 Apr 10 1/4 3/4 CD-1 TPC=$94.3M $5.6M CD-2 E F CD-3 std adv CD-4 10 months of schedule contingency CD-3 Overdrive FY09 FY10 FY11 FY12 FY13 FY14 FY15 $5.2 $9.0 $9.9 $20.5 $22.8 $23.7 $3.2 Budget odometer
How’s the performance so far? • SPI = 0.94 & CPI = 0.98 • 80% complete • Contingency = 30% of ‘to go’ costs (variances zeroed) • Budget at completion = $86.8M • Estimate at completion = $90.3M • Level 2 milestones: • Ahead = late against PMB, well ahead of Sep 15 CD-4 date How’s the baseline? • All scope remains as planned. • TPC remains ‘on-target’. • CD-4 date remains ‘on-target’ .
FPD Analysis • Center Stack construction efforts still critical path, significant efforts made in OH winding operations since last review • CS Assembly efforts shifted to D-Site to allow for parallel efforts • Schedule thoroughly scrubbed for opportunities to improve completion date • Bottoms up EAC will provide confidence in validating cost and schedule needs to attain CD-4 The Project has realized significant cost/schedule contingency usage in completion of the Center Stack work-scope; recent efforts have arrested this trend. Quality has been excellent.
Transition to Operations Progress? • Operational Readiness Assessment Planned • The ORA will cover all NSTX-U systems: project upgrades, research upgrades and restart of existing systems that have been dormant. • Pete Kelley (BHSO), an experience DOE Fac Rep, to lead the team • Focus on safety of personnel and equipment • PPPL Activity Certification (ACC) Process being used to return NSTX-U to operations – Princeton Site Office direct participation • PSO engaged FES, SC-31, and PPPL in reviewing Accelerator Safety Order for relevant elements based on October OPA review. • Path forward still under discussion.
Construction Progress? • Overall Progress is satisfactory. . . • All construction efforts are well underway • Safety performance has been excellent to date • Critical Path. . . • Remains through the construction of new Center Stack assembly • OH Coil Winding in progress in Center Stack Fabrication facility; layer 1 complete, transition to layer 2 in progress. • Five of six high risk Vacuum Pressure Impregnation (VPI) efforts completed satisfactory (only OH VPI remains) • Management. . . • EVMS system in place and fully functioning • Construction proceeding well in NSTX Test Cell • All previous Review Recommendations addressed • Project is getting the resources it needs
Conclusion • Project has made significant strides in maintaining critical path schedule since last review. Contingency usage rate has decreased as well. • Good communication between PPPL and Site Office. • Estimates are updated regularly. Six month EAC update in progress. • Funding and human resources are in place. • Elements of DOE Order 413.3B are met. • Technical quality remains high… This is very important.
Office of Science Princeton Site Office Charge Questions • Critical Path Construction Efforts: Does the Project team have a realistic, executable schedule for Center Stack (CS) remaining construction efforts? Does the project have adequate resources and the appropriate skills mix to execute the remainder of the project per the plan? • Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the contingency remaining adequate for the risks that remain? • Management: Evaluate the management structure as to its adequacy to deliver the scope within budget and schedule. Are risks being actively managed? Has the project responded satisfactorily to the recommendations from the previous project reviews?