ESCL Annual Conference Stockholm 25 August 2006. Large Projects - Insurable to what Extent? What drives the premium?. By Anders Lindberg, MSc CE, Vice President, If P&C Insurance Ltd, Stockholm, Sweden. If P&C:s definition of Large Projects. Contract value to exceed EUR 10 - 50 millions.
E N D
ESCL Annual Conference Stockholm 25 August 2006 Large Projects - Insurable to what Extent? What drives the premium? By Anders Lindberg, MSc CE, Vice President, If P&C Insurance Ltd, Stockholm, Sweden
If P&C:s definition of Large Projects Contract value to exceed EUR 10 - 50 millions Anders Lindberg, If P&C Insurance
Type of projects Infrastructure Process Industry Power Generation Examples Bridges, Tunnels, Harbours Petrochemical plants, Steel Mills Gas Turbines, Waste Incineration Large and Complicated Projects Anders Lindberg, If P&C Insurance
Insurable to what extent? Anders Lindberg, If P&C Insurance
A general principle of Insurance To insure against loss or damagewhere the identified risks and exposuresthrough professional Risk Assessmentand Risk Management can not beeliminated or satisfactory mitigated. Anders Lindberg, If P&C Insurance
The Contract / Tender Documents Risks and Responsibilities • clearly and understandably defined? • clear and fair distribution between parties? Insurance Requirements • relevant and realistic? Time Schedule • realistic or tight? Information to Insurers • extensive and clear enough? Anders Lindberg, If P&C Insurance
Risk / Exposure Physical damage Time schedule delays Damage to Third Party Damage to the Environment Design Errors Financial losses Performance Guarantees Insurable? yes no yes yes, sudden and accidental yes but limitations certain exposures only no Risks and Exposures to a Project Anders Lindberg, If P&C Insurance
Construction and Maintenance Periods Contractors' experience and record Risk Management Programme The Insurance Market's experience Extent of Insurance Cover requested Sums Insured / Loss Limits Potential for Large Losses Level of Deductibles What drives the premium for a specific Project?(p1 of 2) Anders Lindberg, If P&C Insurance
Exposure Type of Project Size of Project Prototypes LocationGeologyNat Cat exposures Third Party Driving parameters Potential for large and/or frequent Losses Capacity requirements Unproven design, technology and/or material Rock and Soil conditionsStorm, Flood, Earth Quake... Capacity shortage! Urban projects e.g. underground systems What drives the premium for a specific Project?(p2 of 2) Anders Lindberg, If P&C Insurance
The Insurance Market for Large Projects(p1 of 5) Capacity - Infrastructure Projects of special concern • Tunnels and Underground works • Bridges • Road Construction • Wet works e.g. Harbours • Off shore installations e.g. Wind Turbines, Sea Cables Anders Lindberg, If P&C Insurance
The Insurance Market for Large Projects(p2 of 5) Anders Lindberg, If P&C Insurance
The Insurance Market for Large Projects(p3 of 5) Large Losses - example Singapore MRT spring 2004 Anders Lindberg, If P&C Insurance
The Insurance Market for Large Projects(p4 of 5) Public Projects - Special Insurance Problems Public tender regulations • Reservations and/or deviations may not be accepted Consequence • Insurance requirements as per the tender documents can not always be met by the Insurance Market The Reality • Capacity is available with few exceptions, but extent of cover, deductibles and premium to be negotiated and agreed Anders Lindberg, If P&C Insurance
The Insurance Market for Large Projects(p5 of 5) Policy Wordings - Special Conditions Major Risks / Exposures –Restrictions of Cover and Loss Limits may be imposed Long and complicated projects – Review Clauses Risk Management Requirements • To be mentioned specifically: A Code of Practice for Risk Management of Tunnel Works Compliance with this code is or will be a prerequisite for insurance cover of tunnel projects in all major markets Anders Lindberg, If P&C Insurance
The Players in the Insurance Market Brokers, Insurers, Reinsurers and Loss Adjustors always look for: • Experience and know-how • Capacity • Satisfactory Financial Rating (Insurers and Reinsurers) Anders Lindberg, If P&C Insurance
Sources for further information • IMIA, the International Association of Engineering Insurers www.imia.com • Insurers’ and Reinsurers’ publications e.g. Munich Re, Swiss Re • The Insurance Institute of London: Report of Advanced Study Group 208B, CONSTRUCTION INSURANCE Anders Lindberg, If P&C Insurance