An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS Endcap Muon SystemWBS 3.5 Frank Taylor MIT M&O Request FY06 TorontoAugust 3, 2005 V1.1

  2. U.S. Muon Schedule V7.03 Sequence: EIL4-13 EIL4-A&C BW-C SW-A SW-C BW-A

  3. Status-I 30-July-05 • MDT Chambers – EIL4+SW+BW • Phase I Commissioning of all 240 chambers @ CERN complete • All on-chamber electronics complete • Available personnel have largely moved to CERN • CSC Chambers – SW • 14 of 32 passed Phase I Commissioning @ BNL • All on-chamber electronics complete • Off-chamber RoD & Transition Modules in prototype • Will not be finished by CD4A but will be ready for installation • Alignment – EIL4+SW+BW+EO • All in-plane components complete • All components for alignment bars complete • Expect EIL4/BW/SW parts complete by CD4A • Except – CSC on-chamber parts (not part of Appendix 3) • EO parts will be completed before V7.03 need date

  4. Status-II 30-July-05 • Chamber installation tooling-Ready • Chamber ‘Verticalizer’, ‘Grabber’ & ‘Wisconsin’ tool TIS certified • BW Installation B180-Started • Last BT moved from B180 to Point 1 on 29-July-05 • Competition for space reduced but share B180 with TGC & ECT • BW-Large Sector tooling setup in B180 • BW-Sector 9C vertical • BW-Small Sector tooling delivered to CERN • Except A-frame that will be needed later • Remaining BW sector parts delivery Aug. through Nov. from Russia • Project tracking difficult • EIL4 Installation B180-Started • Work area setup in B180 and is operational • EIL4-13A installed on frame & integrated with TGCs in B180 • SW Installation B191-To Start early 2006 after ECT Assembly • SWA & SWC are at CERN • Were pre-assembled at Hatehof in Israel

  5. M&O-Installation Locations & Phases CSC Test Station BNL - 832 MDT Test Station BMC, UM, UW CERN - Bld 184 Phase I CY 04 - 05 Alignment System Test Station CERN - Bld 180 B184 CERN Installation on Support Structures Commission Big Wheel [BW] Sectors CERN - Bld 180, 185 PhaseII CY 04 - 06 Commission Small Wheel [SW] CERN - Bld 191 ATLAS UX15 Complete Phase III CY 05 - 07 Partially Complete Beam On - CY-07 Started

  6. Installation Pictures Installation of 1st Alignment Bar in Sector 9C Chamber Handling Tooling BW-L Tooling & Sector 9C SW @ Hatehof BW Sector 9C @ B180 EIL4 Work Area in B180 EIL4 A13 TGC+MDT

  7. Plans for FY06 • MDT Chambers • Production installation of EIL4 chambers (Operation 1) • 16 chambers – 4 are special in Sectors 1 & 9 • All 16 installed in UX15 by 15-March-06 • Production installation of BW-L & BW-S chambers (Operations 2&3) • 16 BW-C Sectors (5 MDT each) by 30-Jan-06 • Continue BW-A Sectors finish by Dec-06 • Set up SW area in B191 – start by 15-Jan-06 • Production installation of EI MDTs on SWs (Operations 4&5) • All EI MDTs (64) installed by ~ Oct-06 (Start ASAP – dependent on ECTs) • CSC Chambers • Ship all CSCs to CERN after Phase I finished @ BNL ~ Oct-05 • Setup CSC test area in B184 ~ Nov-Dec-05 • Integrate CSCs with support frames & alignment components • Installation of CSCs in SWs (Operations 4’&5’) • Finish by Oct-06

  8. US Muon Operations in B180 Small Wheel in B191 O(4&5) BW-S (O3) EIL4 (O1) BW-L (O2)

  9. 3.5 Budget Profile-Baseline Possible call on Management Reserve FY06,7,8 Phase II & III – Integration & Commissioning in UX15

  10. 3.5 Labor Plans-Baseline

  11. Installation Baseline Some carryover expected FY05->FY06 but unknown at this time

  12. FY06 M&O Request • Solicited M&O requirements from the 10 Muon Institutes • Replies from all 10 received Sum I+M&O = 2,278 Sum M&O = 1,895 1st round of budget scrubbing of requests while trying to maintain essential technical staff support

  13. M&O Resource Levels Analysis of Jan-05 still holds: Requirements for FY05, 06 & 07 estimated to be roughly same level FY05 M&O Budget 1,887k FY06 M&O Request after PM scrubbing 1,895k Installation in FY06 budget baseline 383k

  14. Management Reserve • Anticipate a call on MR ~ $354k in FY06 • Scheduled work delayed but end-date fixed • BW and SW installations and commissioning will have significant overlap • Expect roughly constant M&O resources needed FY05-FY07. • During FY06 work will focus on EIL4 & BW and later on SW installation and commissioning in B180 & B191, respectively • Installation and commissioning of EIL4-A13 and 1st BW-L sector should provide a calibration of time & manpower needed • Priority for call for MR funding • Essential technical & engineering staff @ CERN for installation & commissioning

  15. Summary • Many items completed on the CD4A list • However significant effort in the US remains until the end of FY05 that has impacted concentrated effort @ CERN • Delays BW Installation & Commissioning • B180 occupancy, delivery of BW frames & tooling • Because Installation in UX15 is fixed, more work will have to be performed in parallel • EIL4, BW and SW installation work will overlap in CY06 • 5 ‘Operations’ simultaneously conducted • Share manpower, share tooling, logistical overhead • M&O resources will have to support this compressed schedule