1 / 21

ATLAS Tile Calorimeter WBS 3.4

ATLAS Tile Calorimeter WBS 3.4. Larry Price ANL. M&O Status and Plans Toronto August 3, 2005. Construction Project (Installation). Installation Schedule in Pit. Barrel March-December 2004 EBC: August-November 2005 (Oct-Nov) EBA: December-March 2006 (Dec-Jan).

michon
Download Presentation

ATLAS Tile Calorimeter WBS 3.4

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS Tile CalorimeterWBS 3.4 Larry Price ANL M&O Status and Plans TorontoAugust 3, 2005

  2. Construction Project (Installation)

  3. Installation Schedule in Pit • Barrel March-December 2004 • EBC: August-November 2005 (Oct-Nov) • EBA: December-March 2006 (Dec-Jan)

  4. Assembly/commissioning schedule (Version 7, still official) • Comments: • -Probable 4 weeks delay on LB movement (not official)=> delay EB assembly+LB commissioning • EC toroid A that follows EBA assembly is not available in time. • When EB is pushed inside toroid for ID installation or solenoid magnetic field test, the dist LB-EB~ 4m and minivan-scaffolding still in place =>can access EB/B fingers (to be looked in more detail).

  5. Schedule for barrel Commissioning phase 1 active Tile WPs ( based on V7 schedule) 20 June05 This table does not taken into account that unofficially (most probably) the start of commissioning by sectors planned for 7 Sept-15Nov05 will be delayed by 3-4 weeks due to delay of the toroid installation/barrel movement

  6. Schedule for barrel Commissioning phase 1 non active Tile WPs (20 June 05) page 2

  7. Schedule for barrel Commissioning phase 1 non active Tile WPs (20 June 05) page 3

  8. TileCal Front-End Electronics Repairs on HF Truck Sept-Oct 04 -Tests on: TTC, CANbus, HV, laser fibres via LED, BCID @ 100 kHz L1A, readout noise, … - Replaced failing components - Will continue in Jan-Feb when OPAL cradle will be removed

  9. WP 4.1: In situ FE electronics certification with Mobidick (status in June05; Claudio,Fabrice) • Remaining tasks for z=0 (before starting commissioning, no access now): • 14 Super Drawers to be repaired ( 7 out of 64 modules) • 2 SD to be inserted • Repair/certify FE in cases of failures are found with MobiDAQ • Finish this week last 4 modules certification (without fingers) • Next step in July+Aug (Nikos): perform FE stability tests in all modules using MobiDAQ +temporary cables (~ 8 SD running ~ 3 days with portable cooling).

  10. WP4.2: FE tests with MOBIDAQ (Gerolf,Iacopo,Amir,Oleg,Giorgi,Andrea) (8 drawers at the time from USA15+temporarly cables/fibres) MobiDAQ • MOBIDAQ in pit for many weeks and working in stable mode for a few days. • Still need to include LED test to send light to PMTs (will replace laser system for fibres QC) Cosmic receiver setup PC (MobiDAQ interface)

  11. Cosmic rays expert week 20-28 June (Richard et al.) 8 superdrawers (2 top +2 bottom modules) 8 sets of temporary cables (TTC/GLINK, CANbus, trigger, laser/LED) 8 temporary LVPS 2 temporary cooling units MobiDAQ in USA15 2 Coincidence boards (Chicago) Details:http://agenda.cern.ch/askArchive.php?base=agenda&categ=a053788&id=a053788s1t6%2Ftransparencies%2FTEUSCHER_Cosmic_Ray_Expert_Week_Summary_June_2005.ppt

  12. Event with Back-to-Back Trigger

  13. Next expert weeks/integration runs: • July ’05: ROD Expert week in USA15 • Read out 8 superdrawers with final ROD Motherboard • Debug DAQ/ROD • Dec ’05/Jan ‘06: Begin cosmic-ray running on barrel • Following installation of final services and Low Voltage PS at z=0 • Up to 12 top + 12 bottom modules • 2006: Continue periodic runs until global ATLAS cosmic run in March ‘07 • Integrate with LAr barrel after cool-down (~April ‘06) • Repeat with TileCal EBA / EBC / HEC / FCAL when ready in ‘06

  14. Summary or dates as understood on June 27th (based on v7).

  15. MBTS counters 2 segments in h; inner segment covers pixel detectors

  16. Principal US M&O Work in 2005 • Validation, calibration, and repair of modules and electronics • Adjustments and modifications to accommodate adjacent systems, e.g., LAr and Cryostat • Establishment of test/repair facility • Work with TC on services validation • Cosmic Ray Commissioning • Cosmic ray trigger system • “First ATLAS Data from the underground area” • Performance monitoring and calibration software development • Setup for cosmic ray commissioning and performance measurement • Vapor shields for central and forward cryostats • MBTS Scintillators • Validation and testing of LVPS • Initial integration with TDAQ and extensive exercise of interfaces (MobiDAQ) • Establishment of conditions and other databases • Design and prototyping of MBTS Counters

  17. Plans for US M&O Work in 2006 • Complete MBTS Counters • Barrel integration with TDAQ + DCS and extensive exercise of interfaces • Barrel commissioning • Locally by sectors • Cosmics with TDAQ readout • EB Commissioning (as above) • Final mechanical and light integrity validation of EBA modules before installation in pit • Software development • Complete initial calibration, diagnostic, and status reporting software • Database development • Establish and exercise the procedure for regular diagnostics and calibrations • Validation and testing of LVPS • Identify and carry out needed electronics repairs • Completion of test/repair facility • Understand calorimeter performance and integrate with LAr and physics studies

  18. FY 2006 Budget

  19. Issues • Completion of LVPS • Congestion in the pit • Tile Extended Barrel assembly • Muon Barrel assembly • Tile Barrel commissioning • Will need probably to work in 2 shifts/day in Sept->Dec with several teams working in parallel. • Consequently need: • Big teams of physicists/tech/eng. at CERN during second half 2005 and first half of 2006. • Commission each Tile sub-system in standalone as much as possible before end August in USA15/UX15 with temporary cables • Good coordination within Tile sub-systems and with other ATLAS systems (through TC). TC