Sixth Plenary ENVISAT RADAR ALTIMETRY CROSS-CALIBRATION and VALIDATION TEAM Meeting (#17). Jérôme Benveniste ENVISAT RA-2/MWR Cross-Calibration and Validation Team Coordinator European Space Agency, Earth Observation Applications Department
E N D
Sixth Plenary ENVISAT RADAR ALTIMETRY CROSS-CALIBRATION and VALIDATION TEAMMeeting (#17) Jérôme Benveniste ENVISAT RA-2/MWR Cross-Calibration andValidation Team Coordinator European Space Agency, Earth Observation Applications Department ESRIN, Via Galileo Galilei, I-00044, Frascati (RM), Italy, (e-mail: Jerome.Benveniste@esa.int) RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Before recalling the objectives of the meeting, a few important matters that need immediate dealing with…. Welcome to ESRIN ! RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Participants to tonight’s dinner please sign up! Do you want to go to the same one than last time? How many of us have a car? RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
You are invited to a welcome cocktail at 17h30 in the Canteen RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Meeting Logistics • Coffee breaks at 10:30 and 15:30 • Lunch break at 13:00 • On the floor below: • Self service canteen • Travel office • Taxi reservation forms to fill out (leave 2 hours before take-off) • Bank, ATM • A complimentary shuttle leaves the Frascati Piazza Roma (newspaper stand) at 8:05 and 8:20 and back at 17:15 and 18:15 RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Objectives of the Meeting • Present results obtained on nearly three cycles of GDRs and two cycles of SGDRs • Discuss cross-calibration results and validation status • Make recommendations for future evolutions • Prepare for publication at EGS-AGU-EUG & IGARSS • Prepare for Final Report RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Original Schedule • L=1 March 2002, SO=12 March 2002 • (L+1m) First data report (on S-O day 12/03) • (L+2m) Preliminary report from Esrin in house verif (10 may) • (L+2m) CCVT splinter meeting on products and algorithm verification • (L+3m) Data release to CCVTeam (15 June) • (L+4m) Interim Report (prod val, l2 verif, prel x-cal) • (L+6m) End comm ph Cross-cal and Val full report • (L+6m) RA-2/MWR CCVT plenary meeting (9-10 Sept) • (L+6m) Calibration review (10-13 Sept) • (L+9m) Validation Workshop (report+ presentation) (10-13/ Dec) • (L+10m) Final RA-2/MWR CCVT meeting (9-10/12 or 14-15/01/03) • (L+12m) Final report on Cross-cal • (L+12m) end of RA-2/MWR CCVT project 15 August for FDMAR 9 November for GDR etc. skipped Preliminaryproductvalidation Jan-Feb-Mar/03 Processing of 3 cycles Extended schedule… RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Extended Schedule • (L+9m) Validation Workshop (report+ presentation) (10-13/ Dec) • (L+10m) Acquisition and processing of three cycles until 17 Jan 03 • (L+13m) Sixth RA-2/MWR CCVT meeting (25-27 March 03) • (L+14m) EGS/AGU/EUG Special session Geodesy-13 “Impact of new and planned mission” , Nice (F) (7-11 April 03) • (L+15 m) Final report on Cross-calibration and Validation (May 03) • (L+15m) end of RA-2/MWR CCVT project (end May 03) • IGARSS Special Session, Toulouse (F) (July 03) RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Agenda RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
ENVISAT MISSION STATUS By Henri Laur, ENVISAT Mission Manager RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Data Availability • Presented by Nicolas Picot, CNES (F-PAC) RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03
Agenda RA-2/MWR Cross-Cal & Val Team, ESRIN 25-27/03/03