1 / 24

Assembly Hall in Hybrid-A’ and ILD

Assembly Hall in Hybrid-A’ and ILD. 2014/9/6 Yasuhiro Sugimoto. Assembly hall for ILD. Five pieces of ILD yoke (YE-, YB-, YB0, YB+, YE+) are assembled in the surface assembly hall (AH)

ethan-beard
Download Presentation

Assembly Hall in Hybrid-A’ and ILD

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto

  2. Assembly hall for ILD • Five pieces of ILD yoke (YE-, YB-, YB0, YB+, YE+) are assembled in the surface assembly hall (AH) • Each yoke is assembled on the floor, and moved to a platform in AH by air-pads, and lowered to the underground detector hall after installation of some sub-detectors and magnetic field mapping • Muon detectors, solenoid coil, and barrel/endcap calorimeters are installed on surface (Trackers are installed underground)

  3. ILD requirement for AH • Space • ILD needs assembly space for 5 yoke rings and solenoid • If we assume 25mx10m space for each of YE± and YB±, and 25x20m for YB0 and solenoid, respectively, 25mx80m space is necessary • Crane • A 250 ton crane for yoke assembly and an 80 ton crane for solenoid/detector assembly and installation are needed • ~4000 ton gantry crane for detector lowering • Hall height • 22.6m from the floor to crane rail, 6m from crane rail to ceiling, plus alpha for lights and fans on the ceiling • Cryogenics • He gas pipes have to be connected from the compressor building for magnetic field mapping in AH • Platform • ILD should have its own platform on surface to avoid the risk of delay of SiD construction

  4. AH with a garage • AH should have a garage (alcove) for ILD to put 2 pieces (YE+, YB+) aside • This configuration gives several merits Garage

  5. Merits of AH with garage • Shorter AH • ILD assembly area: 80m65m • Flexibility of assembly area configuration, and effective use of 2 cranes • Preferable lowering order of ILD • YE-  YB-  YE+  YB+  YB0 is preferable, and can be achieved if we have a garage • YE-  YB-  YB0  YB+  YE+ might be OK if cryogenic apparatus on YB0 is small enough 80t crane has no task at this stage

  6. Lowering order of ILD • AH w/o garage YB- YB0 YB+ YE+ YE-

  7. Lowering order of ILD • AH w/o garage using SiD platform 1. Field mapping 4. YE+ Platform for ILD Platform for SiD 5. YB+ 2. YE- 3. YB- 6. YB0

  8. Lowering order of ILD • AH with a garage 1. Field mapping 4. YE+ 2. YE- 5. YB+ 3. YB- 6. YB0 YE+, YB+ step aside YB0 step back

  9. A possible design of AH • Plan view Compressor building 1st phase assembly hall for ILD 50m space between 2 assembly halls is required for VS/DH construction

  10. A possible design of AH • Side view

  11. Size of garage

  12. A possible ILD assembly scenario • Assumption • Similar timeline as Fig.14.10. in TDR Vol.3.II • Surface AH shown in the previous pages • Same assembly scenario of superconducting magnet as CMS; YB0  Outer Vacuum Tank (OVT)  Coil  Inner Vacuum Tank (IVT) OVT assembly Coil insertion IVT insertion

  13. A possible ILD assembly scenario 10 9 8 5 4 1 2 3 6 7 • Not ILD official timeline • Just a working assumption for the assembly space study

  14. A possible ILD assembly scenarioStep-1 Platform for ILD • Surface platform construction • YB0 assembly • Preparation for coil assembly Garage 250t crane 1st phase assembly hall 80t crane Swiveling platform for coil assembly

  15. Step-2 • YE+ assembly • Coil outer vacuum tank (OVT) assembly • Coil assembly

  16. Step-3 • YE- assembly • YE+ Muon detector installation • Inner vacuum tank (IVT) assembly • Coil assembly IVT

  17. Step-4 • YE- assembly • YE+ Calorimeter installation • IVT, Coil assembly

  18. Step-5 • YE- assembly • YE+ Calorimeter cabling • YB0 Muon detector installation • Coil assembly

  19. Step-6 • YB+ assembly • YE+ pushed into garage, ECAL cabling • YE- Muon detector installation • Coil assembly

  20. Step-7 • YB+ assembly • YE- Calorimeter installation • Coil, IVT installation  test for vacuum, cooling, and low current

  21. Step-8 • YB+ Muon detector installation • YB0 Calorimeter installation

  22. Step-9 • YB+ pushed into garage • YE- pushed to vertical shaft side • YB- assembly, Muon detector installation • YB0 Calorimeter installation

  23. Step-10 • Close detector • Field mapping (SiD is >50m away from ILD)

  24. Conclusion • AH with a garage has several merits for ILD • If AH can have a garage, ILD can be assembled with 65m (=52.5m+12.5m) length of AH (1st phase AH) • Total length of AH could be ~180m (65+50+65m) if SiD requires same length of assembly area

More Related