1 / 24

Overview, remarks, lamentations, hope and despair

Overview, remarks, lamentations, hope and despair. Introduction and stuff. M. Sozzi NA62 TDAQ Working Group meeting February 8 th 2012 - CERN. M. Sozzi TDAQ WG meeting 14 December 2011. Agenda. TDCB.

ethel
Download Presentation

Overview, remarks, lamentations, hope and despair

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview, remarks, lamentations, hope and despair Introduction and stuff M. Sozzi NA62 TDAQ Working Group meetingFebruary 8th 2012 - CERN M. Sozzi TDAQ WG meeting 14 December 2011

  2. Agenda

  3. TDCB 12 boards + cables distributed in November for validation (sustainable rate, time resolution, noise, etc.): CEDAR, CHANTI, LAV, RICH, MUV, IRC/SAC, STRAWS Performance/rate tests: report by S. Venditti Tests in Perugia: report by M. Piccini Firmware rewrite completed, testing to be started. Test bench hardware not started yet. Final version PCB started yesterday: no major changes foreseen. Pisa

  4. Waiting for validation of the boards by sub-detector groups(none so far) IF MORE BOARDS ARE NEEDED FOR 2012 THEY SHOULD BE REQUESTED BY FEBRUARY 2012 Otherwise NO boards will be produced until 2013 on top of those which you have Price will depend on the number of boardsBase: 1000 €/board + 500 €/4 cables

  5. TEL62 Status report by F. Spinella Most parts of the board tested on prototype Second prototype to be mounted Control software for programming (JAM): not yet working,Perugia working with LHCb to fix this Final firmware, documentation, control software startedGUI for multiple-board control to be started Pre-production (10-12 boards for 2012 runs) to be started in 1 month. Full production planned for 2013 (Pisa+Roma TV). Test procedure (Roma TV) not started yet Need to decide on STRAWS readout needs Pisa

  6. From NA62 TWiki pages:

  7. TEL62 firmware - II • Work can start now (on TELL1 if hardware testing needed) • The developing TEL62 firmware is stored at CERN under SVN (instructions on TWiki). Concurrent development works fine.Anybody can start to contribute even on TEL62. • Need specifications of sub-detector requirements for processing blocks (data, packing, registers, memory space for look-up tables, etc.) • Firmware writing guidelines on TWiki

  8. TEL62 firmware • Which (reduced) functionality for 2012? PrioritizationManpower issues still unresolvedResponsible people (1 per sub-detector) (almost) identified: • RICH: C. Santoni (Perugia)LAV: M. Raggi (Frascati)CEDAR: K. Massri (Birmingham)LKr/L0: A. Salamon (Roma TV)CHANTI: D. Di Filippo (Napoli)MUV: R. Wanke (Mainz) ?SAC/IRC: V. Kozhunarov (Sofia) ? • Work can start now (on TELL1 if hardware testing needed)Need specifications of sub-detector requirements for processing blocks (data, packing, registers, memory space for look-up tables, etc.)

  9. TEL62 firmware - III STARTED STARTED STARTED(FOR RICH) STARTED

  10. TEL62 firmware - III STARTED STARTED ADVANCED STARTED STARTED(FOR RICH) STARTED ADVANCED NEW SINCE LAST MEETING

  11. Crates, racks Racks positions finalized 8 “Front-end TEL62” crates ordered to Wiener + all (36) special backplanes: CEDAR: 1STRAWS: 1LAV: 3RICH: 1MUV: 1Spare: 1

  12. Clock modules - I LTU (NA62 version, Birmingham): paid for, ready, available, first firmware and software versions ready: talk by V. CernyModules available to sub-detectorsNew documentation page available on TWiki TTCex (new version, CERN):paid for, built, PLL problem (random clock offset) in new version. Modules required by sub-detectors for 2012 available1 high-quality module required by RICH rented from EPOOL Optical splittersTested, sub-detector requirements collected, common order placed BirminghamBratislava

  13. Clock modules - II LTUs are at Marian’s TTCex are at Riccardo’s Marian’s proposal: out of the LTU/TTCex required and available for 2012, each sub-detector takes 1 pair to their lab for testing and (in case they ordered more than 1), leave the second one at CERN, in order to setup the central clock crate for the 2012 runs.

  14. Clock infrastructure Fibers: Specification of optical fibers (incl. termination) and definition of optical network for TTC: doneInstallation will be in March 2012 Choke/error: cable (& connectors) specification (CAT7 + RJ45): doneTest of longest cable (150 m, EB20 to CEDAR) with LVDS tester (special firmware on LTU): February 2012Installation: April/May 2012 Central VME crate: prepared with 7 LTU, test with TALK board (L0TP for 2012) at CERN: February 2012Installation in ECN3: May/Jun 2012 Master clock generator: tested, installed, no spare Burst emulator: installed, to be adjusted BirminghamCERN

  15. L0TP FerraraTorino • No progress since last meeting.PC-based solution with Terasic FPGA development board not yet demonstrated to be valid. Two boards available (in Ferrara and Torino). • Ferrara is developing a software library to access data coming from FPGA. This would allow to measure time performances of primitive-matching algorithms • Torino started some preliminary measurements on ethernet transmission latency • No candidate for software (primitive-matching algorithm). 2012: use talk board for run (any prototype to be tested?). 2014: critical issue

  16. E. Rebuffello, E. Menichetti (Torino): tests on TCP/IP latency using FPGA development board and a PC Latency is way too large, but TCP is not what we want FPGA clock frequency is not a relevant parameter

  17. Farm and higher-level triggers Work in Mainz on L1/L2 farm software infrastructure Requirements for 2012 not yet clearData format change with respect to NA62 note (use UDP) Work in Pisa on: (1) fast driver (for farm and all PCs) and (2) microsecond-level time-synchronization protocol between hardware and PC (for PC-based L0TP and possible GPU-based L0 trigger): talk by L. Deri No LKr L0 trigger simulation yetNo L1 recipe so far to reach 100 kHzBandwidth allocation proposal needed (also true for L0)

  18. TDAQ for sub-detectors

  19. Non-standard readout systems Gigatracker: not relevant for 2012, to be reviewed LKr: not relevant for 2012, work ongoing, to be reviewed Straws: work ongoing, review today: talk by P. LichardDecision expected at this meeting between proposed system and fallback solution. Documentation TDAQ TWiki developing: https://twiki.cern.ch/twiki/bin/view/NA62/TdaqSystemInstructions to setup TEL62 firmware environment OKFeedback needed !

  20. Online Discussions on Control Program and online environment started: talk by R. FantechiHelp from EN/ICE available (lots of LHCb software can be reused)Some manpower identified: N. Lurkin (Louvain) to start real work soonOnline responsibility (group) to be clarified later Dry run / test run We have a TDAQ run coordinator! See G. Lamanna talk (and react to it)2012 will be a limited (but still important) TDAQ test

  21. Coming soon…(Expected for next meeting) • Review of TEL62 firmware • First detailed plan for Control Program • Detailed discussion of trigger farm software • Review of Gigatracker readout integration • Review of LKr readout integration

  22. Critical issues • L0TP: no proof of viable solution, no progress • Online software: no work done, no group responsibility • TEL62 firmware: lack of manpower: not ready in 2012 • Radiation tests: no progress • Crates: only very basic tests done before order • Simulation: missing L0 for LKr, L1 and L2 • Missing specifications: e.g. fine time L0 trig info

  23. Critical issues • L0TP: no proof of viable solution, no progress • Online software: no work done, no group responsibility • TEL62 firmware: lack of manpower: not ready in 2012 • Radiation tests: no progress • Crates: only very basic tests done before order • Simulation: missing L0 for LKr, L1 and L2 • Missing specifications: e.g. fine time L0 trig info a working solution for 2012 exists (TALK board) some manpower, work starting soon, help from EN/ICE minimal DAQ firmware should be available minimal mechanical/electrical tests were done specifications will freeze automatically

More Related