1 / 24

Proper Piping Practices (Pumps)

Proper Piping Practices (Pumps). Condensate Return. Hotter boiler feed water temperatures Minimizes the amount of chemicals required to treat boiler feed water Eliminates environmental concerns Minimizes water usage which is critical in some areas

evelynf
Download Presentation

Proper Piping Practices (Pumps)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proper Piping Practices (Pumps)

  2. Condensate Return • Hotter boiler feed water temperatures • Minimizes the amount of chemicals required to treat boiler feed water • Eliminates environmental concerns • Minimizes water usage which is critical in some areas • Condensate is a tangible item which can be measured in the form of a savings analysis • Effective return can lower overall costs which can impact profitability Let’s take a look at a savings analysis...

  3. A. Condensate Load A= 2000 lb/hr B. Annual hours of operation B= 5000 hrs C. Total Water Cost = (C1+C2) C1. Untreated water and sewage .002 $/gal C2. Water treatment chemicals .003 $/gal C= .005 $/gal D. Make-up water preheating requirements D1. Condensate return temperature 200 °F D2. Make-up water temperature 60 °F D = (D1-D2) x 1.0 BTU/lb / °F D= 140 BTU/ lb E. Steam cost E= 5.00 $/1000 lb F. Savings in water costs (A) x 2000 x (B) 5000 x (C) .005 8.34 lb/gal F= 5,995 $/yr G. Savings for preheating make-up water *(BTU/lb from direct steam injection) (A) 2000 x (B) 5000 x (D) 140 x (E) 5.00 *1000 x 1000 G= 7,000 $/yr H. Cost of steam to run Armstrong Pump Trap 3 x (A) 2000 x (B) 5000 x (E) 5.00 *1000 x 1000 H= 150 $/yr I. Total annual savings = (F+G+H) F. Savings in water costs 5,995 $/yr G. Savings for preheating make-up water +7,000 $/yr H. Cost of steam to run Armstrong Pump Trap - 150 $/yr I= 12,845 $/yr J. Payback of pump purchase Payback = $5,063 (cost of pump package) 12,845 J= .39 yrs

  4. Piping Considerations: Doing it right the first time • Check Valves • Fill Head • Lead/Lag • PRV Station • Receiver Sizing • Vent piping • Condensate return lines

  5. SWING CHECK VALVE:INLET

  6. IN-LINE NON-SLAM CHECK VALVE:Inlet or Outlet

  7. Condensate Return Lines • Undersized return lines cause major problems for the entire system. • Increased velocity from undersized return lines result in WATER HAMMER PROBLEMS.

  8. Pipe Sizing • Piping should be based on2-3 times the normal condensing ratedue to instantaneous discharge rate of the pump • Minimize elevation changesto prevent hydraulic shock • Utilize check valves at main header to minimize backflow • Run separate lines for pumped and pressurized condensate, if possible, to minimize thermal shock potential • Always calculate themaximum flash ratein return lines

  9. CONDENSATE RETURN LINE SIZING • ELIMINATE THE POSSIBILITY OF DAMAGING WATER HAMMER. OFTEN OVERLOOKED DURING SYSTEM UPDATES. • PIPE SIZE IS BASED ON FLASH STEAM VOLUME SINCE ITS VOLUME IS SO MUCH GREATER THAN LIQUID WATER. • FEWER PROBLEMS WITH OVERSIZED PIPE THAN UNDERSIZED PIPING.

  10. Vented Receiver Sizing

  11. Closed Loop Receiver Sizing

  12. Product Range • Single pump capacities from 350 lb/hr to 73,000 lb/hr • Flash recovery vessels • Electric condensate pumps

  13. Rescue Cap™ • Fits Spirax Sarco PPC/PPF pumps. • Watson McDaniel • Spence • Hoffman PCS • Gestra FPS23 • Johnson • Clark Reliance

  14. Armstrong Stainless Steel Sump Ejector • Replaces standard electric sump pumps (must have high pressure steam available • For steam pits, tunnels and enclosed spaces where ground or rain water can accumulate and requires pumping • Can be used in any application where the water temperature will not exceed 140°F • Great for locations that run underground steam lines where the drip traps are in tunnels or manholes

  15. Armstrong AFT Vertical Flash Vessels • Excellent for providing low velocity flash steam with no water carryover • ASME Sec. VIII U stamped to 150 psi (other pressures upon request)

  16. Packaged Solutions • Standard Packages • Custom Fabrications • ASME Packages • Low Boy Solutions • Vented Systems • Closed-loop Systems • Process Water Packages and more… Closed-loop Low-Boy Receiver Package

  17. Common Industry Applications • Jacketed Kettles • Process Air Heating • Tank Heaters • Shell & Tube Exchangers • Process Media (water, oil, food etc.) • Any steam consuming process heat exchanger utilizing… Modulating Control

More Related