An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UK Project Finance & Schedule Alan Grant

  2. Overview Schedule & Risk • Schedule Overview • Step IV • Step V • Step VI Finance • Current Allocation Period and Current Position • Capital Request • Forward look to complete step VI – flat cash • Resource loaded forward look to complete step VI • Resource loaded forward look to complete step V

  3. Schedule Overview • Schedule now includes PRY for step IV following recommendations of the Magnetic Field Mitigation review panel. • All compressors will be installed on the West Wall. Compressors will not be installed until August 2014. • Magnet power supply and control racks will be installed in new rack room with full agreement of ISIS. • Schedule identifies tasks with risk element & associated risk delay. Work in progress!! • SS’s & Tracker’s assembled in R9 then moved to MICE Hall. • Magnet training only begins after cooling channel and PRY is installed (this includes EMR, KL & TOF). • 15 weeks total for all magnet training after cooling channel is installed.

  4. Step IV schedule – Shipping • RF system - TIARA • RF distribution equipment delivered TH116 installed, 4616 pre amplifier installed, water services panel installed • Upstream Spectrometer Solenoid - Delivered • Downstream Spectrometer Solenoid - Expected May 2014 • AFC #2 – Delivered • EMR – Delivered and testing complete • Diffuser – Available at Oxford • PRY - South yoke expected April 2014, North yoke expected July 2014 (Risk)-(R1) 80day delay (Risk)-(R2) 40day delay (Risk)-(R3) 20day delay (Risk)-(R4) 10day delay

  5. Step IV schedule – R9 Pre Installation Work (Risk)-(R1) 80day delay (Risk)-(R2) 40day delay (Risk)-(R3) 20day delay (Risk)-(R4) 10day delay

  6. Mechanical Integration Work in Hall • Relocating compressors to West Wall involves a lot of work • Mezzanine structure, services, supports • Means we need to make other Hall modifications • South mezzanine air con, stairs, crane, existing west wall services • Includes New Rack Room – space agreed with ISIS

  7. Step IV Installation • Magnet training of SS begins after cooling channel is installed (this includes EMR, KL & TOF) • 15 weeks total for all magnet training after cooling channel is installed. • Step IV completion now -  end Jan 2015

  8. Step IV Schedule – Critical Path (Risk)-(R2) 40day delay (Risk)-(R3) 20day delay (Risk)-(R4) 10day delay

  9. Step IV schedule 27/10/15 30/8/15 30/1/15 • Assumes South side PRY available mid April - subject to contractual negotiations • Assumes North side PRY available mid July – installation begins mid September • Critical path driven by West Mezzanine Wall and compressor installation • Magnets cooled in September 14 • Magnet training can only take place only after full PRY is installed

  10. Step V (Transitional Schedule) – Critical Path • Step V – Key Deliverables • RFCC – March 2018, risk level 1 • Hydrogen system 2 –November 2016 • RF system – March 2015 • PRY – not planned for as yet!! (Risk)-(R1) 80day delay (Risk)-(R2) 40day delay (Risk)-(R3) 20day delay (Risk)-(R4) 10day delay

  11. Step V - Transitional Schedule 24/4/19 8/4/19 27/8/18

  12. Step VI Schedule – Critical Path • Step VI – Key Deliverables • RFCC – Sept 2019, risk level 1 • AFC –April 2018 • Hydrogen system 3 –August 2016 • RF system – November 2017 • PRY – not planned for as yet!! (Risk)-(R1) 80day delay (Risk)-(R2) 40day delay (Risk)-(R3) 20day delay (Risk)-(R4) 10day delay

  13. Step VI Schedule 29/1/21 7/1/21 14/5/20

  14. Schedule Summary Step IV • Critical path driven by West Mezzanine Wall and compressor installation • Ongoing - identifying & quantifying risks. • Initial estimated cost for mag field mitigation:- £372k • £500k & 5man yrs effort UK our estimate in risk register • Assumes delivery of South PRY mid April 14 and North PRY mid July 14 • North PRY not installed until September 14 • Risk Delay – assumes we incur all identified delays • Schedule & risks need to be monitored as these will change

  15. Finance

  16. Allocation - This Approval Period • Approval period runs to Apr 2016 • Projected overspend this FY was £132k (7.5%) • To cover Magnetic Field Mitigation requirement (staff & non staff) • STFC agreed overspend and review in October • Current projected overspend as of September £208k (11.75%) • £35k – RF crowbar • £12k - AFC monitoring equipment • £20k- Hydrogen vacuum enclosure • £7k – New roller shutter door

  17. Submitted Capital Request At the request of STFC the project team have provided a list of capital items that could be advanced should resources become available.

  18. Forward Look Spend to Step VI • Assumes flat cash allocation • Proposed delivery of RFCC#2 which now includes contingency, means an allocation will be required in future years. This was the expected outcome based on the contingency analysis presented in May. • Based on current analysis a re-base lining of UK-US plan is warranted for next review. Draft! Work in Progress

  19. Operations Management Structure Needs additional resources to deliver this structure

  20. Resource Loaded Forward Look Spend to Step VI • Assumes resource requirements positions are filled to deliver and operate MICE • Essential resources:- • Experimental Co-ordinator • Possibly jointly funded position with UK university • Integration Scientist • P. Hanlet (IIT) • Operations Team Leader • Lab staff … reporting line through Laboratory as safety critical • Cryo expert • Mark Tucker (PPD); presently 50%. Need 100% with full experiment • Magnet expert • Lab staff … reporting line through Laboratory as safety critical • Work in progress: • Full analysis includingexplicit WM and contingencyin preparation.

  21. Resource Loaded Forward Look Spend to Step V • Assumes resource requirements positions are filled to deliver and operate MICE • No AFC#3 • No Hydrogen System#3 • No RF power for systems 3&4 • Rescheduled delivery of RFCC#1 means there will be some staff costs in 2018/19:- • PM & PO office • Mechanical Integration • Electrical Integration • RF Installation • 2018/19 - Retain staff expertise for • Hydrogen system • RF system • Software & Computing, Operations and Analysis fully supported from 2018/19 onwards Draft! Work in Progress

  22. Resource Loaded Forward Look Spend