Section 408 Approval Process(New 408 Regional General Permit) Richard J. Muraski Jr. Colonel, Corps of Engineers Commander Fort Worth District
Overview • 408 Approval Authority • Flood Risk Paradigm • Why Streamline? • Streamlining Initiatives • 408 RGP – What is it? • Key Takeaways • POCs / Resources • Questions & Answers
How are they Applied? Stakeholder Projects • Waters of the US • Federal Project RGP PEA 404 / 10 408
408 Approval Authority • 33 USC 408 (Rivers & Harbors Appropriations Act of 1899) • Title 33 – Navigation and Navigable Waters • Section 408 – Taking possession of, use of, or injury to harbor or river improvements • Unlawful for any person or persons to build upon, alter, deface work built by the US to prevent floods unless SecArmygrants permission based on determination that the proposed project will: • Not be injurious to the public interest (NEPA Component) • Not impair the usefulness of the Federal project
Flood Risk Paradigm • THEN • Flood Damage Reduction (FDR) • Paradigm: Federal Protection • “We are Safe” • Individual Agency Processes • Project-by-Project • Focus on reducing damages by • managing floods • Minimal consideration to future • land use or other social effects • Decisions based on reducing the • potential for failure • NOW • Flood Risk Management (FRM) • Paradigm: Shared Risk Reduction • Integrated Agency & Stakeholder • processes to buy-down risks to a • tolerable level • Focus on reducing probability of • flooding & consequences should • flooding occur • Systems Approach (weakest link) • Integrate environmental, social, • and economic factors
Communication Levee Safety Program Activities
Why Streamline? • Perception: Some projects have required multiple years for review • Reality: Acquiring sufficient data for proper review & required Agency determination has sometimes been lengthy • Contributing Factors • Lack of Stakeholder understanding of roles, responsibilities and process • Insufficient Corps Guidelines for technical and NEPA submittals • Failure to coordinate/secure Sponsor review & approval • Incomplete submittal packages • Insufficient technical analysis • Lack of sufficient environmental compliance documentation
Fort Worth District Streamlining Initiatives • Developing Standard Business Process • Regional General Permit • Programmatic EA • Section 214
Standard Business Process • Developing Standard Business Process • Increase efficiency & reliability • Define Roles & Responsibilities • Process Map / Responsibility Matrix • Submittal Checklists • Increase Clarity / Decrease Anxiety
408 RGP – What is it? • Permit Name: Modification and Alterations of Corps of Engineers Projects • Permit Number: CESWF-09-RGP-12 • Issued 24 FEB 2010 • Expires 23 FEB 2015 • Purpose: Eliminate unnecessary duplication of work where the environmental consequences of the proposed action are individually and cumulatively minimal
Programmatic Environmental Assessment • Certain Conditions must be met to use • Must be a Minor Section 408 • Only affect grassland habitats or be covered under a Nationwide Permit or the RGP • Must not result in significant adverse impacts to cultural resources • Must not impact threatened or endangered species
WRDA Section 214 Authority • Legislation allows the Corps to accept funds from Non-Federal Public Entities to expedite 408 Actions & Regulatory Permits • Program Must: • Serve Public Interest with Accountability & Transparency • Ensure Impartial Decision Making • Expedite Permits • NCTCOG & USACE entered into a MOA October 2008 to process Regulatory Permits • COG is applicant & sets priorities for projects • Completed 30 Permit Actions to Date; 31 Pending Projects • Draft MOA being processed with NTCOG to process 408 Actions
Comparison of Section 214 Projects VS Regulatory Branch Performance in 2010 • Section 214 - 100% of Individual Permits issued in 120 days • Branch - 54.8% of Individual Permits issued in 120 days • Section 214 – General Permit verification averaged 7.6 days • Branch – General Permit verification averaged 25.7 days
Current Section 408 Actions • Major Modifications • No Major Section 408’s have been processed by the Ft Worth District for final approval by HQ • Cities of Irving and Dallas have Section 408 100-year levee remediation projects in process • May become minor Section 408’s if the modifications are determined to be insignificant • Anticipate several upcoming bridge/roadway levee crossings will be major actions • Estimated review & approval costs in the $150,000 range • Minor Modifications • Receiving numerous requests to modify DFW area projects • Goal to process and approve actions within 30 days of final submittal package • Review costs dependent on complexity but usually less than $10,000/ action
Key Takeaways • USACE is standardizing the process • Shared Risks – Shared Responsibility • Help improve Stakeholder understanding – embrace the concept • Early coordination with Sponsor by applicant will help reduce/minimize USACE review times. • Better integration of engineering design with environmental impacts needed to comply with NEPA and CWA (404) and RHA (Sec 10) • Ensure complete, comprehensive 408 submittal packages
POCs / Resources • 408 Business Process (Primary Contact) • Terry Bachim, Chief Maintenance Section • Terry.bachim@usace.army.mil • hyperlink • Regional General Permit (RGP) • Stephen Brooks, Chief Regulatory Branch • Stephen.brooks@usace.army.mil • http://www.swf.usace.army.mil/pubdata/environ/Regulatory/permitting/rgp/CESWF_09_RGP_12_Final_Signed.pdf • Programmatic Environmental Assessment (PEA) • Rob Newman, Chief Environmental Branch • Rob.newman@usace.army.mil • http://www.swf.usace.army.mil/pubdata/Notices/Minor408PEA/Final_Minor_408_PEA.pdf • Section 214 • Elston Eckhardt, Chief Civil Programs • Elston.eckhardt@usace.army.mil