Contextualization of available technologies in wastewater treatment: from BIODISC to MBR

Contextualization of available technologies in wastewater treatment: from BIODISC to MBR. Eng. M. Galdi Eng. K. Al Zeer Eng. R. Ruggiero. CANNON Group Italian group International, present in 40 countries Industrial engineering 900 employees 200 m€ turnover. Fields of Activity

eydie
Download Presentation

Contextualization of available technologies in wastewater treatment: from BIODISC to MBR

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Contextualization of available technologies in wastewater treatment: from BIODISC to MBR Eng. M. Galdi Eng. K. Al Zeer Eng. R. Ruggiero

  2. CANNON Group • Italian group • International, present in 40 countries • Industrial engineering • 900 employees • 200 m€ turnover • Fields of Activity • Plastics Processing (59%) • Heat & Power (24%) • Water Treatment (13%) • Automation Machine (4%)

  3. ARTES Ingegneria S.p.A. was founded in 1975 as the Company within the BONO Group in charge of the waste water treatment market Peschiera Borromeo Milano Oliveto Citra Salerno Salerno Headquarter

  4. Total Area : 30.000 m2 Covered Area : 8.900 m2 Workshop : 7.800 m2 Office : 1.000 m2

  5. Technical Dept. 25 Sales & Marketing 15 After Sales Services 5 Purchasing & Warehouse 3 Administration Dept. 3 Production Supervisors 3 Quality Dept. 3 Workshop 33+15 Total Employees 105

  6. OUR CERTIFICATES • ISO 9001:2008 certified • ISO 14001 & OHSAS 18001 in progress • ASME Authorisations – “U”, “S”, “R” code stamps • Quality Control Personnel: • Quality Assurance manager • Quality control inspectors • Quality control assistants

  7. OUR CUSTOMERS (OIL&GAS)

  8. OUR CUSTOMERS (POWER GENERATION)

  9. OTHER CUSTOMERS

  10. Export

  11. Europe, Russia and CIS Countries 26% America 6% Middle East & Africa South Est Asia & Oceania 48% 20%

  12. SECTORS • Food and Beverages

  13. SECTORS • Textile & Laundry

  14. SECTORS • Paper

  15. SECTORS • Pharmaceutical and Chimical

  16. SECTORS • Building & Construction

  17. Tourism & Recreation

  18. Potabilization

  19. TECHNOLOGY

  20. BRC +DCl BRC + MF + DUV AS + MF + DUV MBR + DUV Where: BRC = BIOLOGIC ROTATING CONTACTOR DCl = DISINFECTION WITH CHLORINE MF = MICROFILTRATION DUV = DISINFECTION WITH UV LAMP AS = ACTIVATED SLUDGE MBR = MEMBRANE BIOLOGICAL REACTOR

  21. rotation BRC water submerged for about40% tank  BRC = BIOLOGIC ROTATING CONTACTOR

  22. pannel airtight lid shaft gear motor BRC

  23. BRC

  24. BRC • Advantages: • Easy to absorb overload without failure in the treatment process • No bulking problems, no filament bacteria • Easy to expand and upgrade, it is a modular plant • Ability to process a very low organic loads; Unlike the activated sludge plants • Less space occupied for the oxidation step and the step of final sedimentation • Reduced need for energy consumption (about 40% less than the activated sludge plant) • Automation and ease of use • Very low levels of noise • Limited environmental impact. There are no problems with troublesome odors and / or aerosols. Since each unit is fitted with an airtight lid • No need to recycle sludge, self-regulating plant • Handicaps: • Possible mechanical problems • Limited efficiency: Compared with AS or MBR

  25. MBR = MEMBRANE BIOLOGICAL REACTOR • A membrane bio reactor is... • a combination of biological waste water treatment and membrane filtration • a membrane filtration which separates biomass from water • a membrane filtration which is based on ultra or micro filtration

  26. Frompreliminary treatments Aerobic step Sand filter anoxic step conventional Activated Sludge process Q membrane 4Q Q anoxic step Aerobic step 5Q MBR process

  27. 4 Qm Qm Qm Suction pump 5 Qm Recirculation pump blower blower PROCESS DIAGRAM MBR

  28. Why to use an MBR 1. Recycling Possibility • Safe rejection of biomass, solids and bacteria • Pre-treatment for following treatment steps (reverse osmosis, nano filtration, UV and ozone) 2. Plant size • Place saving installation due higher sludge concentration • Increasing of capacity in an existing plant 3. Effluent Quality • Enhanced quality of treated water • Constant quality of treated water • Conformance of enhanced standards of hygiene(EC guidelines for bathing water) • Higher efficiency due increasing concentration of biomass in the activated sludge tank

  29. What is …Contextualization • Means: • plants with easy maintenance and management, reliable, and simple installation to be served for small, medium and large rural settlements; • plants that are technologically "state of the art" of higher cost, but performance significantly better in terms of quality of produced water, to be served in settlements where the environmental impact is important, where the presence of skilled personnel is possible, where the quality of treated water is particularly important (settlements in bathing areas, Hotel, resorts, etc.);

  30. The parameters that we will consider are : • Efficiency • Installationcost • System's complexity (difficulty in finding qualified personnel) • Enviromental impact

  31. 1,0 efficiency 0,8 0,6 0,4 0,2 0,0 installation cost

  32. 1,0 system's complexity 0,8 0,6 0,4 0,2 0,0 installation cost

  33. installationcost environmental impact

  34. system's complexity 0,0 0,2 0,4 0,6 0,8 1,0 efficiency

  35. By "contextualize" we define four areas with different needs (about water quality and environmental impact) and different resources (about financial resources and specialized personnel): ruralareas (low economicresources, low availability of specialized personnel, where the environmental impact and the water quality are not very important) inlandareas (where the environmental impact isnotveryimportant, thereisn’t specializedpersonnel, the water qualityisimportantenough and there are sufficient economic resources) coastalareas (where the environmental impact and water quality are importantenough and you can find both the economic resources that qualified personnel) touristicareas (where the environmental impact and water quality are veryimportant and tofind financial resources and qualified personnel is not a problem)

  36. intersecting the defined areas and the needs/resources above described on we obtain a value “V” 1 = LOW IMPORTANT/ NO AVAILABLE 4 = VERY IMPORTANT/ AVAILABLE

  37. With “V” = 4 BRC + DCl

  38. With 4 < “V” < 6 BRC + F + DUV

  39. With 6 < “V” < 12 AS + F + DUV

  40. With 12 < “V” < 16 MBR + DUV

  41. THANK YOU FOR YOUR ATTENTION! Eng. M. Galdi Eng. K. Al Zeer Eng. R. Ruggiero