MinerA Fiber/Cables/VSTand JUPITER update Steven ManlyUniversity of Rochester DOE Program Review17 July 2005
MINERA: Optical system - overview Clear Fiber Cables PMT Boxes WLS Fibers ~32,000 channels ~4000 clear 8-fiber cables, light tight ~2000 ODU’s ~12,000 connectors, polished ends ~90 km of WLS fiber, mirrored on one end ~65 km of clear fiber Scintillator Plane
MINERA: Optical system - overview Optical system is huge and critical Optical system … the nerves of MINERA. We must collect enough light, know our efficiency for doing it and understand the mapping to the PMT’s or the experiment cannot work. Requires conservative design and choice of materials, extensive R&D and testing, careful production, QC during production Management, design, R&D, creating specs, procurement, qualifying procured materials, QC procedures, manufacturing procedures, safety during manufacture and in use, production, QC during production, calibration database, shipping
MINERA: Optical system – People and optical system duties Howard Budd: level 2 manager of fiber and cables, design, R&D, in charge of VST, design of QC procedures and equipment Steve Manly: design fibers/cables, procurement of fiber and connectors, clear cable production, module scanning Robert Bradford: Module scanner design/construction Robert Flight: cable light tighting mold and boot design, mechanical interface, routing of fibers, module scanner design Jim Steinman: Cable R&D, cable light tighting boot materials and production, investigating tube material Jesse Chvojka: fiber R&D (bend tests), VST analysis Jaewon Park: fiber R&D (attenuation tests) Dan Ruggiero: connector R&D and QC, production Janina Gielata: to join in September, cable production
MINERA: Optical system - Fiber Will use Kuraray fiber: WLS: 1.2 mm, 175 ppm (Y-11), S-35, multi-clad Clear: Kuraray, 1.2 mm, S-35, multi-clad fiber WLS fiber from VST Some of the R&D done this year – Bend tests – 5” diameter bend, important for fiber routing and mechanical design Optimize fiber diameter (light output, bend radius, cost) Attenuation measurements - light output Glued vs. unglued in scintillator – light output Mirrored vs unmirrored – light output Y-11 (175 ppm) vs expensive Y-7 (300 ppm) Bend test (Budd, Manly, Ruggiero, Park, Chvojka)
Clip Box Ferrule MINERA: Optical system - Connectors (Budd, Manly, Ruggiero) Use connectors from Fujikura/DDK Similar to those used in CDF plug upgrade 1.2 mm fiber means new Ferrule design/mold First connectors produced had excellent alignment (good optically) but were rather tight to connect/disconnect. Currently working with DDK on modification. New connectors expected to arrive at FNAL today or tomorrow. FNAL Ice polish R&D Polished fiber in connector
Clip Box Ferrule MINERA: Optical system - Cables Must make clear fiber cables light tight. Use polyurethane “boot” molded around black opaque tubing that surrounds the eight fibers (Flight, Steinman)
MINERA: Optical system – Cables R&D/testing/QC (Budd, Chvojka, Flight, Park, Ruggiero) Connector and cable attenuation test setup Light injector box Real life connector and cable test in progress (in dark box) Results from test showing no degradation with time of optical transmissivity of connection using optical grease
MINERA: Vertical Slice Test (VST) 3-layer, 21 scintillator prototype Mirrored WLS fiber glued into co-extruded scintillator bars and fed into prototype MINERA electronics (no clear fibers or MINERA connectors). Trigger scintillators above and below Measured 21 pe/MIP for each layer Min-I track position resolution measured to be 3.4 mm Led by Budd, analysis by Chvojka
JUPITER: phenomenology (Bodek, Bradford, Budd) Recent measurements of nucleon vector form factors in eA scattering show validity of dipole form factor parameterization is questionable eA elastic nucleon form factors used to get vector QE cross section in neutrino scattering. JLab Hall A Collaboration, PRL 84 (2000) 1398. New parameterization(s) needed
JUPITER: phenomenology Bradford, Bodek, Budd, Arrington, hep-ex/0602017. BBBA 05 parameterization based on work by Kelly plus additional duality constraints
JUPITER: Hall C – measurement of F2 and R=L/T on nuclear targets in the nucleon resonance region From contribution of V. Tvaskis, J. Steinman and R. Bradford to NuInt’05 (Steinman, Manly, Bodek, Bradford) Log10(Q2) JLab coverage E02-109 and E04-001 (Bodek, co-spokesperson) eA data on H, D, C, Al, Fe targets Steinman thesis topic: measure F2 and R Will help experiments understand cross sections and nuclear effects CVC relates vector structure functions in electron scattering to neutrino counterparts N fractional error ~ 0.5R N fractional error ~ 1.5R R = 0.2 implies 10% error on N and 30% error on N Log10(x) Neutrino structure function measurements and MINOS kinematic coverage – WA59 has error on F2 of 20-30% and done on Ne See E04-001 proposal at http://www.pas.rochester.edu/~bodek/jlab/F2-Rnuclear-HallC.pdf
JUPITER: Hall C From talk by V. Tvaskis at NuInt’05 Steinman working primarily with Christy (Hampton/JLab) and Tvaskis (JLab), Manly acting as superviser Keppel (Hampton/JLab), Bodek, Bradford also involved Substantial progress made in the last year and a half Preliminary cross sections available and calibrations and charge symmetric background corrections done Expect to finish extend to heavier targets and produce final cross sections and structure function measurements in the next 1-1.5 years
JUPITER: Hall B (CLAS) – misc. measurements of exclusive final states in eA scattering to understand better nuclear effects relevant for experiments in the resonance region (Manly, Bradford and undergrads: Dave Sher, Ian Kleckner, Jennifer Cano) Manly gave talk on this at JLab neutrino workshop in June. Great interest in these measurements among neutrino folk. Allows neutrino MC tuners to take into account nuclear effects like transparency and absorption in a brute force way. They can look at data for vector part and appropriate Q2 only. • Examples of measurements: • Momentum distributions for protons and charged pions in 1- and 2- events (E, Q2, A=H,C,Fe) • ep epo ep+below 2 threshold • o/+ ratio as function of W and Q2 How often do you see proton from QE event? (Affects Evis and event categorization.) How often do you lose a pion in a resonance or inelastic event? (Affects Evis and event categorization) Coherent oproduction background electron neutrinos. How often does charge exchange happen? Is there an A dependence? Neutral and charged pions look different in detectors. Need to understand A dependence. The reconstructed neutrino energy is a critical quantity for neutrino expts. Tune models with CLAS measurements.
JUPITER: Hall B Neutral and charged pions look different in detectors. E is a critical quantity. Tune models that can be used in expts. No oscillations Oscillations i.e., K2K result, E is important Paschos, Schienbein, Yu, hep-ph/0408148 ANP model calculations K2K Collaboration, hep-ex/0212007.
JUPITER: Hall B Fermi smearing and radiative corrections ~cancel o+acceptance differences ~cancel Fermi smearing and radiative corrections ~cancel Progress: Carbon: E=4.462 GeV Hydrogen: E=4.462 GeV Invariant mass of Reconstructed pizeros W W
Plans for upcoming year • Expect CD-1, CD-2, CD-3a approval for MINERA by spring. • Complete singe module prototype (Rochester production of cables and fiber, construction of module paper) • Progress on tracking (multi-module) prototype • Complete Hall-C F2 and R analysis on nuclear data • First results from Hall-B on exclusive final states
Requests Additional MINERA graduate student: based at FNAL to help with cable production and work with single module and multi-module prototypes. Work on exclusive eA analysis and integration of JUPITER information into MINERA MC. Additional MINERA research associate: based at FNAL to supervise module scanning/production and veto wall construction/installation and play a major role in detector commissioning. (Bradford is incredibly productive, but will be working with module construction and needs a little time to do science.) Continuation of Manly transition: need 2 months summer salary and travel/computing/operations funds. NP picked up Steinman for one year. This year NP picking up all travel/computing/operations funds for Manly/Steinman, including MINERA.