810 likes | 1.32k Views
Construction (Design and Management) . INTRODUCTION . Construction Health and Safety. Overview of the Construction Industry's Health and Safety Record. Safety Record. 228 workers died in 2007/8 compared to 247 in 2006/7.There was a slight decrease in the construction sector; 72 compared to 79 Construction accounts for more than a quarter of all work related deaths.
E N D
1.
CDM 2007
Project Management
The Bartlett, UCL
Presented by:
Nigel Evans MIIRSM, RMaPS, FRSPH
5. Safety Record Since CDM
6. CDM Prosecutions 12 month period (37)
20. CDM Example actions: The CDM Co-ordinator established that the design team meet on a regular basis and that “Health and Safety” is a regular part of the agenda. It was agreed that the drawings and design risk register would be regularly circulated around the team.
23. CDM EXAMPLES OF DESIGNER ACTIONS A school is situated adjacent to the site.
Architect schedules out the school start and finish times to enable contractors to avoid peak deliveries in these periods.
New drains connecting to existing effluent system.
Engineer arranges for analysis of effluent data to be included in H&S Plan, to allow contractor to provide safety precautions.
25. Note
SFAIRP – So far as is reasonably practicable
Note
SFAIRP – So far as is reasonably practicable
30. CDM 2007Principal contractors & contractors
31. Duties on the principal contractor (1) Little change between CDM 1994 and CDM 2007
Client should appoint a PC for notifiable projects and appoint as soon as is practicable
Principal contractor should ensure that client is aware of duties, CDM co-ordinator has been appointed and HSE notified
Those they appoint are competent
The construction phase is properly planned, managed, monitored and resourced
32. Duties on the principalcontractor (2) Inform contractors of the minimum time allowed for planning and preparation
Provide relevant information to contractors
Ensure safe working, co-ordination and co-operation between contractors
Construction phase health and safety plan is prepared and implemented
Plan needs to set out the organisation and arrangements for managing risk and co-ordinating work
Plan should be tailoured to the particular project and risks involved
Suitable welfare from the start
Manage health and safety on site, not the paperwork
33. Duties on the principalcontractor (3) Prepare and enforce site rules as required
Give reasonable direction to contractors including client appointed contractors
Prevent unauthorised entry
Provide plan to those who need it
Promptly provide the CDM co-ordinator with information for the file
Liaise with CDM co-ordinator in relation to design and design changes
Ensure all workers have been provided with suitable health and safety induction, information and training
Note
The duties are to monitor the construction phase – this does not mean they are required to supervise the work, that is the duty of the individual contractors to manage, supervise etc their own work, but the PC should have monitoring role – each contractor will have, to a varying degree, their own management arrangements.Note
The duties are to monitor the construction phase – this does not mean they are required to supervise the work, that is the duty of the individual contractors to manage, supervise etc their own work, but the PC should have monitoring role – each contractor will have, to a varying degree, their own management arrangements.
34. Duties on the principalcontractor (4) Ensure the workforce is consulted about health and safety matters
Display key project information to workers
Does not have to
Provide training to workers they do not employ (but contractors do)
Undertake detailed supervision of contractors’ work
Fill the construction phase plan with irrelevant information or endless generic paperwork
35. PRINCIPAL CONTRACTORExample actions: A copy of the Construction Stage Health and Safety Plan is included in all prospective sub-contractor tender documentation.
Weekly meetings arranged with all sub-contractors to co-ordinate forthcoming work activities and to ensure that critical interfaces and data are exchanged.
36. Duties on contractors and self employed – all projects (1) Check clients are aware of their duties
Not start work until they have obtained the pre-construction information from the client (or PC)
Plan, manage and monitor their own work to make sure that their workers are safe
Ensure they and those they appoint are competent and adequately resourced
37. Duties on contractors and self employed – all projects (2) Inform any contractor that they engage, of the minimum amount of time they have for planning and preparation
Provide their workers (whether employed or self-employed) with any necessary information and training and induction
Report anything that they are aware of that is likely to endanger the H&S of themselves or others
Ensure that any design work they do complies with CDM design duties
38. Duties on contractors and self employed – all projects (3) Comply with the duties for site health and safety
Co-operate and co-ordinate with others working on the project
Consult the workforce
Not begin work unless they have taken reasonable steps to prevent unauthorised access to the site
Obtain specialist advice (e.g. from a structural engineer or occupational hygienist) where necessary
39. Duties on contractors and self employed – notifiable projects (1) Check that a CDM co-ordinator has been appointed and HSE notified before they start work
Co-operate with the principal contractor, CDM co-ordinator and others working on the project
Tell the principal contractor about risks to others created by their work
Comply with any reasonable directions from the principal contractor
Work in accordance with the construction phase plan
40. Duties on contractors and self employed – notifiable projects (2) Inform the principal contractor of the identity of any contractor he appoints or engages
Inform the principal contractor of any problems with the plan or risks identified during their work that have significant implications for the management of the project
Inform the principal contractor about any death, injury, condition or dangerous occurrence
Provide information for the health and safety file
41. Contractors – Key messages You will benefit from the changes to the CDM Regulations by being involved in the project earlier, working to designs that are safer and healthier to build, receiving more relevant information and less paperwork
It will be easier for you to show the principal contractor, or your client, that you and your subcontractors have the right skills and experience for the job
Manager health and safety on site – manage the risk, not the paperwork
43. Note
Objective: Key problems with designers under the CDM 1994 was a ‘lack’ of understanding of what was expected and a proliferation of paper work that branded CDM as inefficient and ineffective. This ‘common’ view has been damaging, CDM and the effective management of risk.
For CDM 2007 we need to be clear
Eliminate hazards.
Complex paper systems are not required or desirable
Good designers have always eliminated hazards.
Objective to engage in the process, take ownership and reduce the total amount of risk in the process.
We do not want to encourage a back covering exercises based on the reverse burden of proof or verification culture. The focus is in reducing risk by design –making a difference
Note
Objective: Key problems with designers under the CDM 1994 was a ‘lack’ of understanding of what was expected and a proliferation of paper work that branded CDM as inefficient and ineffective. This ‘common’ view has been damaging, CDM and the effective management of risk.
For CDM 2007 we need to be clear
Eliminate hazards.
Complex paper systems are not required or desirable
Good designers have always eliminated hazards.
Objective to engage in the process, take ownership and reduce the total amount of risk in the process.
We do not want to encourage a back covering exercises based on the reverse burden of proof or verification culture. The focus is in reducing risk by design –making a difference
44. Note
Essential that designers provide clear (& concise) information about residual risks of their design, to those that need to know. Eg Other members of the design team, Pr Con, Coordinator, subcontractors (especially any specialist subcontractors). Do not tell contractors to wear Wellington boots etc. Control measure on site are for the contractor to manage
Don’t overload with trivial & obvious risk information. They need to know any risks likely to arise from the design that will affect their work. Particularly the non-obvious risks. Some risks may be difficult to manage, and will require more effort than others. This should be identified. If they are not sure of what may be relevant then they can discuss it with the contractors and ask what is relevant to them.
Note
Essential that designers provide clear (& concise) information about residual risks of their design, to those that need to know. Eg Other members of the design team, Pr Con, Coordinator, subcontractors (especially any specialist subcontractors). Do not tell contractors to wear Wellington boots etc. Control measure on site are for the contractor to manage
Don’t overload with trivial & obvious risk information. They need to know any risks likely to arise from the design that will affect their work. Particularly the non-obvious risks. Some risks may be difficult to manage, and will require more effort than others. This should be identified. If they are not sure of what may be relevant then they can discuss it with the contractors and ask what is relevant to them.
46. Note
A flue pipe. Could it have been sited in a worse position for future maintenance? This has designed in risk and cost for any future work. When speaking to a designer remember ask what they have actually done to make a difference.
Note
A flue pipe. Could it have been sited in a worse position for future maintenance? This has designed in risk and cost for any future work. When speaking to a designer remember ask what they have actually done to make a difference.
47. Note
There is no “right or wrong” way for designers to provide information to others. It will depend upon what the information is, and to whom it is being addressed.
Notes on drawings are good, but will the person who will end up using the drawing be able to understand them in that format?
Providing a sequence of construction may assist others. The designer may also be a contractor too, carrying out the work of their own design with their own employees.
The information should be project specific, and concentrate on the significant risks.
NOTE:
ERI(C) – The “C” stands for control. This will normally apply to contractors and not to designers. Designers seldom have control on site to reduce the risk – that is a role of the contractor.
Note
There is no “right or wrong” way for designers to provide information to others. It will depend upon what the information is, and to whom it is being addressed.
Notes on drawings are good, but will the person who will end up using the drawing be able to understand them in that format?
Providing a sequence of construction may assist others. The designer may also be a contractor too, carrying out the work of their own design with their own employees.
The information should be project specific, and concentrate on the significant risks.
NOTE:
ERI(C) – The “C” stands for control. This will normally apply to contractors and not to designers. Designers seldom have control on site to reduce the risk – that is a role of the contractor.
49. Note
The clear message from HSE is we do not expect designer risk assessment to be done. If they are done it is because they are of benefit to the design process. They should not be done simply to satisfy the CDM co-ordinator or Inspectors. CDM co-ordinators should be positively discouraged from continuing the DRA or similar.
Remember the objective of CDM is to reduce risk on site not to feed a system with paper. Note
The clear message from HSE is we do not expect designer risk assessment to be done. If they are done it is because they are of benefit to the design process. They should not be done simply to satisfy the CDM co-ordinator or Inspectors. CDM co-ordinators should be positively discouraged from continuing the DRA or similar.
Remember the objective of CDM is to reduce risk on site not to feed a system with paper.
50. Note
We do not want paper kept for HSE. We want designers to reduce risk.
This is a key and strong message only record etc when this has benefits to reduce risk on site.Note
We do not want paper kept for HSE. We want designers to reduce risk.
This is a key and strong message only record etc when this has benefits to reduce risk on site.
51. Note
Do not confuse Design Risk Assessment with Design Review. Design Review is a process of co-ordination. It should allow the design team to critically analyse the design to ensure that it is suitable. The review should also involve contractors, clients, building users/ operators where appropriate. This should help to ensure that the the client gets what is required, but also that issues of health and safety are addressed and resolved at the design stage.
For notifiable projects the CDM co-ordinator will be involved.
Note
Do not confuse Design Risk Assessment with Design Review. Design Review is a process of co-ordination. It should allow the design team to critically analyse the design to ensure that it is suitable. The review should also involve contractors, clients, building users/ operators where appropriate. This should help to ensure that the the client gets what is required, but also that issues of health and safety are addressed and resolved at the design stage.
For notifiable projects the CDM co-ordinator will be involved.
57. Working above shoulder heightinevitable when building masonry If there is potentially a lot of work above shoulder height, can the design eliminate some of this? The contractor can mitigate on site by consideration of how he constructs the scaffold.If there is potentially a lot of work above shoulder height, can the design eliminate some of this? The contractor can mitigate on site by consideration of how he constructs the scaffold.
66. CDM 2007 Competence & training
67. What is competence? To be competent, an organisation or individual must have:
Sufficient knowledge of the specific tasks to be undertaken and the risks which the work will entail; and
Sufficient experience and ability to carry out their duties in relation to the project; to recognise their limitations and take appropriate action in order to prevent harm to those carrying out construction work, or those affected by the work
68. What does CDM 2007 require? All persons who have duties under CDM 2007 should:
Take “reasonable steps” to ensure persons who are appointed are competent
Not arrange for or instruct a worker to carry out or manage design or construction work unless the worker is competent
Not accept an appointment unless they are competent
Applies to corporate and individual competence
69. What does CDM 2007 require? Assessment should focus on the needs of the particular project and be proportionate to the risk, size and complexity of the work
CDM 2007 should streamline the competence assessment process
A key duty of the CDM co-ordinator is to advise the client about the competence of those employed by the client
70. Corporate competency should be assessed by a two-stage process
Stage 1: An assessment of the company’s organisation and arrangements for health and safety
Stage 2: An assessment of the company’s experience and track record
Companies will be expected to reach the standards set out in the core criteria in CDM 2007 ACoP Appendix 4
The Core Criteria have been agreed between industry & HSE Corporate competency
71. Duty holders can:
assess potential appointees against the core criteria or
can use independent accreditation schemes such as CHAS, National Britannia Safe Contractor
The agreed criteria will help prevent a diversity of demands from clients and others and reduce the amount of paperwork and bureaucracy Corporate competency Note
CHAS : Contractors Health and Safety Assessment SchemeNote
CHAS : Contractors Health and Safety Assessment Scheme
72. Individual competency Individual competency should be assessed by a two-stage process
Stage 1: Assessment of knowledge, training records and qualifications, including basic understanding of site risks
Stage 2: Past experience in the type of work you are asking them to do
Those new to construction work will need close supervision by a competent person until they can themselves demonstrate competence
73. Individual competency – designers When assessing the competence of individual designers, look for
Stage1: membership of professional institution e.g. RIBA, CIAT, ICE, IStruct E, CIOB etc.
Stage 2: evidence of past experience in similar work
You may need to take into account the skills and knowledge of other designers if the work is to be carried out by a design team
Note
Royal Institute of British Architects
Chartered Institute of Architectural Technologists
Institution of Civil Engineers
Institution of Structural Engineers
Chartered Institute of Building
Note
Royal Institute of British Architects
Chartered Institute of Architectural Technologists
Institution of Civil Engineers
Institution of Structural Engineers
Chartered Institute of Building
76. Individual competence – CDM Co-ordinator CDM co-ordinators play a key role in CDM 2007 and need
Good interpersonal skills to encourage co-operation and co-ordination
Understand the design process and the need to co-ordinate designers’ work
Knowledge of health and safety in construction
Identify the key information others will need to know
77. Individual competence – CDM Co-ordinator For smaller projects
Stage 1: Knowledge of the design process and health and safety in construction (e.g. qualification such as NEBOSH construction certificate, Membership of the ICE health and safety register, IPS, APS, etc)
Stage 2: Experience in applying the knowledge of construction
78. For larger/higher risk projects
Likely to be a corporate CDM co-ordinator appointment
Appendix 5 of CDM 2007 ACOP provides detailed guidance
The skills and knowledge of the CDM co-ordinator will need to reflect the complexity of the project and the specialist knowledge necessary to ensure that the risks are properly controlled Individual competence – CDM co-ordinator Stage 1: Knowledge of design process & H&S in construction. Membership of relevant construction institution, professionally qualified to Chartered level, validated CPD for H&S (including NEBOSH Constr. Cert), membership of APS/IPS
Stage 2: Evidence of experience & ability (eg worked on similar projects etc) Stage 1: Knowledge of design process & H&S in construction. Membership of relevant construction institution, professionally qualified to Chartered level, validated CPD for H&S (including NEBOSH Constr. Cert), membership of APS/IPS
Stage 2: Evidence of experience & ability (eg worked on similar projects etc)
79. Key points Notification triggers appointment of additional duty holders and duties
Principal contractor
CDM co-ordinator
Construction phase plan
Health and safety file
Most duties remain on clients, designers and contractors regardless of notification
80. HSE’s expectations on the construction industry A change in attitude is needed to deliver the much needed improvements in construction health and safety
A ‘business as usual’ approach is not acceptable
Industry needs to take ownership of the management of risk, show leadership and work in partnership
Focus on effective planning and managing risk
Ensure people are competent
Reduce bureaucracy and paperwork
81. CDM 2007 – Further Advice CDM 2007 Regulations and Approved Code of Practice
HSE Web Site - www.hse.gov.uk/construction/cdm
CDM 2007 Industry Guidance –
www.cskills.org/healthsafety/cdmregulations
Design issues
www.dbp.org.uk
www.dqi.org.uk
www.cic.org.uk
www.ciria.org.uk/cpn_intro.htm
82. CDM
CLOSE