1 / 24

New Nuclear Plant Designs & New Licensing Process

New Nuclear Plant Designs & New Licensing Process. Alex Marion Executive Director Nuclear Operations & Engineering. What is Driving Interest in New Nuclear Plants. Need for power – baseload generation Margins are becoming critical Increasing environmental constraints

faunus
Download Presentation

New Nuclear Plant Designs & New Licensing Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New Nuclear Plant Designs &New Licensing Process Alex Marion Executive Director Nuclear Operations & Engineering

  2. What is Driving Interest in New Nuclear Plants • Need for power – baseload generation • Margins are becoming critical • Increasing environmental constraints • Volatility in natural gas prices • Increasing recognition & support from public & policymakers

  3. Status • 5 Designs certified/under review/being prepared • First two ESPs issued, two more under review • 16 companies & consortia preparing COL applications for 30 reactors in 13 States • First COL applications Fall 2007 • 42 month review schedule • Environmental review critical path • Long lead items being ordered

  4. Part 50 Licensing Process Construction Permit Application * Construction Operating License Application Operating License Issued * Operations * Public Comment Opportunity

  5. Intent of Part 52 Process • Resolve safety issues before the start of construction • Increase public involvement • Make more information available to the public at the appropriate time in the process • Increase regulatory certainty & predictability • Increase public & investor confidence in licensing process

  6. New NRC 10 CFR Part 52 Licensing Process Early Site Permit * Construction Acceptance Criteria Met * Combined License * Construction Operation Design Certification * * Public Comment Opportunity

  7. Near Term Deployment5 Designs being Considered • Areva EPR – 1600 MWe Four-Loop PWR • Mitsubishi APWR – 1700 MWe Four-Loop PWR • Westinghouse AP1000 – 1175 MWe Two-Loop PWR • GE ABWR – 1350 MWe BWR • GE ESBWR – 1500 MWe BWR

  8. Industry Drive for Better Designs & Increased Safety Margins • 1990s EPRI Utility Requirements Document • Set of common general utility specifications for new nuclear power plants • Joint designer-owner (supplier-customer) project • NRC Policy Statement set expectation for safer designs • Industry delivered safer designs

  9. Common Improvements • Two designs -- Use of natural phenomena • Gravity, conduction & convection • Three designs • Additional safety divisions & safety equipment • Designs incorporate lessons learned from 9/11 security reviews on existing plants • More robust designs • Probability of a core damage event from plant-centered events (TMI type accident – LOCA event) significantly reduced • Severe accident mitigation features included in the design

  10. Common Improvements • Design to reduce occupational radiation dose • Digital, multi-channel fiber optic I&C • Equipment design-life -- 60 years • Operator task-based as opposed to system-based training • Use of simulators • Designs to facilitate modular construction • Safety-related construction period -- initial 48 month • Goal – 36 – 42 month

  11. Common Improvements • Easier maintenance & inspection access • Increased laydown area inside containment • Built in/pre-fabricated equipment access platforms • Improved access to Containment • Improved separation between sets of safety equipment • Radioactive vs nonradioactive • Fire areas , especially inside containment

  12. Areva EPR • Improved four-loop PWR • Double containment with annular space maintained at a negative pressure • Four sets of safety equipment as opposed to two • Two sets are bunkered • Increased protection for fuel storage pool

  13. Mitsubishi APWR • Similar improvements to Areva’s EPR • Larger generator – 1700 MWe • Smaller generating designs – an option • Based on plants operating in Japan

  14. Westinghouse AP1000 • Safety systems rely on natural phenomena (passive) • Gravity, conduction and convection (natural circulation and injection) • Emergency injection via accumulators & gravity feed • Equipment layout ensures core remains underwater in design-basis accident scenarios • Increased safety margins during design basis accident conditions • Simplified and improved reactor coolant systems with canned motor pumps (no shaft seal system) • No bottom mounted instrumentation

  15. AP1000 Safety Valves 1400 Pumps 184 3.6 miles nuclear piping 227 miles, electric cable Presuureizer 2100 cu. Ft SG Tube Rupture – No operator action LOCA PCT – 1600F 65% fewer welds 90% fewer supports Standard 1000MW PWR Safety Valves 2850 Pumps 280 20.8 miles, nuclear piping 1725 miles, electric cable Pressurizer – 1400 cu. Ft SG Tube Rupture – Operator action within 10 mins LOCA PCT – 2000F AP1000 Reduction in Components

  16. GE ABWR • No reactor recirc system pipework • Recirc pumps mounted directly to RPV • Three separate sets of safety equipment • Diverse EDG & GT generating equipment for loss-of-offsite power

  17. Evolution of the BWR

  18. GE-ESBWR • 1500MWe natural circulating BWR • No Reactor Recirc Pumps • Emergency injection via accumulators & gravity feed, if feedwater system fails • Natural circulation emergency core cooling • Severe accident management design features

More Related