1 / 13

Don Morse Park Phase 1 – Project Progress Update Shoreline Restoration & Beach Enhancement City Council Presentatio

J.A. Brennan Associates, PLLC in association with Reid Middleton | Coast & Harbor Engineering The Watershed Company | Shannon & Wilson Nelson Geotechnical Engineer | Northwest Archaeological Associates.

fawzi
Download Presentation

Don Morse Park Phase 1 – Project Progress Update Shoreline Restoration & Beach Enhancement City Council Presentatio

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. J.A.Brennan Associates, PLLCin association withReid Middleton | Coast & Harbor EngineeringThe Watershed Company | Shannon & Wilson Nelson Geotechnical Engineer | Northwest Archaeological Associates Don Morse Park Phase 1 – Project Progress UpdateShoreline Restoration & Beach Enhancement City Council Presentation, February 9, 2012 (Bid Results) - Improving a treasured shoreline resource

  2. Phase 1 Budget Analysis The Phase 1 implementation budget is as follows: RCO Grant Marina (BFP) Funding: $1,000,000 City Match: $1,200,000 Total Implementation budget Marina (BFP) Grant: $2,200,000 RCO Grant Upland Beach (WWRP) Funding: $500,000 City Match: $500,000 Total Implementation budget Upland Beach (WWRP) Grant: $1,000,000 Total Implementation budget Phase 1: $3,200,000 Design Fee: Permitting, Design (20% of budget): $640,000 Total Construction Implementation Budget: $2,560,000 Construction Budget Calculation: Total Implementation Budget: $2,560,000 Construction Contingency 10%: $256,000 Original Maximum Allowable Construction Cost (MACC)$2,304,000 (w/ sales tax) Subtract pre-purchase of pea gravel $121,000 with tax. $2,304,000 minus $121,000 = New MACC $2,183,000.

  3. Phase 1 Project –Bid Item 1 (base bid) Cost = $1,998,044

  4. Phase 1 Project – Bid items, 1, 2, &5 Cost = +/- $ 2,114,760

  5. Phase 1 Project – Bid item 2 Gravel Beach

  6. Phase 1 Project – Bid Items 1, 3, & 5 Cost = $2,297,233

  7. Phase 1 Project – Bid Items 1, 4, &5 (Dream Plan) (Connected beach from Natatorium to Marina Breakwater) Cost = $2,355,066

  8. Phase 1 Project - Dream Plan Section

  9. Phase 1 Project - Dream Plan Cost Choices • Fixes failing wall • Sand in the backshore • Natatorium improvements • Cover over wall • Project exceeds funded area • Project costs higher • Improved revenue • Enhanced recreation

  10. Don Morse Park – Lowest Bids Bid Alternate Options

  11. Phase 1 Budget – (from last council meeting) The Phase 1 implementation budget is as follows: RCO Grant Marina (BFP) Funding: $1,000,000 City Match: $1,200,000 Total Implementation budget Marina (BFP) Grant: $2,200,000 RCO Grant Upland Beach (WWRP) Funding: $500,000 City Match: $500,000 Total Implementation budget Upland Beach (WWRP) Grant: $1,000,000 Total Implementation budget Phase 1: $3,200,000 Design Fee: Permitting, Design (20% of budget): $640,000 Total Construction Implementation Budget: $2,560,000 Construction Budget Calculation: Total Implementation Budget: $2,560,000 Construction Contingency 10%: $256,000 Maximum Allowable Construction Cost (MACC)$2,304,000

  12. Phase 1 – Beach Maintenance Costs The Phase 1 implementation budget is as follows: RCO Grant Marina (BFP) Funding: $1,000,000 City Match: $1,200,000 Total Implementation budget Marina (BFP) Grant: $2,200,000 RCO Grant Upland Beach (WWRP) Funding: $500,000 City Match: $500,000 Total Implementation budget Upland Beach (WWRP) Grant: $1,000,000 Total Implementation budget Phase 1: $3,200,000 Design Fee: Permitting, Design (20% of budget): $640,000 Total Construction Implementation Budget: $2,560,000 Construction Budget Calculation: Total Implementation Budget: $2,560,000 Construction Contingency 10%: $256,000 Maximum Allowable Construction Cost (MACC)$2,304,000

  13. Factors to Consider • Tourism Infrastructure • Potential revenue increase from marina, boat launch, parking, and campground • Potential tax revenue from economic development • Permits will expire • Construction costs are low now • Desired length of time to complete project • Safety Issues • Cost to City and taxpayers

More Related