THE RESOURCE BOOK Methodology and Case Studies

. Presentation. BackgroundMethodologyGeneral conclusionsSector analysesWater and waste waterSolid wasteTransport infrastructureRecent developments. . Background. Guidelines for the Development of Successful PPPs"Seminars in Brussels and the Candidate CountriesRequest for examples of real p

ferdinand
Download Presentation

THE RESOURCE BOOK Methodology and Case Studies

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. THE RESOURCE BOOK Methodology and Case Studies Simon Murray Brussels 5th July 2004 ISPA – PPP Framework Contract

    2. Presentation Background Methodology General conclusions Sector analyses Water and waste water Solid waste Transport infrastructure Recent developments

    3. Background “Guidelines for the Development of Successful PPPs” Seminars in Brussels and the Candidate Countries Request for examples of real projects to complement the Guidelines Three key sectors chosen Case studies identified and analysed Report published

    4. Methodology The Resource Book supports the Guidelines It provides detailed case studies of actual projects in three key sectors Three sectors in which the EC has provided grant financing to the Candidate Countries through ISPA and the Cohesion Fund Case studies are not statistically representative But they do demonstrate structures, issues and problems that are commonly found Case studies have been analysed against six criteria

    5. Criteria for Analysis of Case Studies Value of the investment Contract duration Transfer of responsibility Demand risk Availability risk Contract type

    6. Values Assigned to Criteria

    7. Investment value – largest investments in water and transport. Smallest in solid waste. Contract duration – water and transport sectors have the longest contract durations, often over 20 years. Responsibility transfer – solid waste projects have the highest transfer of responsibility to the private sector. Results of the Analysis