An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CE 276Site Design Wes Marshall, P.E. University of ConnecticutMarch 2007 Prismoidal Cut/Fill Analysis

  2. Average End Area Method • Take cross sections at regular intervals indicating both existing & proposed contours • Calculate the amount of cut & fill at each cross-section based upon existing & proposed grades • Multiply average of two adjacent cross-sections by the length between them

  3. Average End Area Method V = [(A1 + A2) / 2] x L V = Volume A1, A2 = Cut/Fill area of cross sections L = Distance between A1 & A2

  4. Garber and Hoel, 2002

  5. Estimating End Area Cut Fill Ground line http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  6. Estimating End Area Fill Area = ∑Shapes Cut Fill Ground line http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  7. Computing Volume Station 1: Cut Area = 6 ft2 Fill Area = 29 ft2 Cut Fill Ground line http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  8. Computing Volume Station 2: Cut Area = 29 ft2 Fill Area = 5 ft2 Cut Fill Ground line http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  9. Volume Errors • Average End Area technique leads to volume errors when cross-sections taper between cut and fill sections • Due to these “prisms,” computer-aided calculations often use the Prismoidal Formula http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  10. Prismoidal Formula V = (A1+ 4Am + A2)/6 x L Where V is Volume and A1 and A2 are end areas at ends of section Am = cross sectional area in middle of section, and Am is based on linear measurements at the middle L = length from A1 to A2 http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  11. http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppthttp://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  12. Consider cone as a prism • Radius = R, height = H • End Area 1 = πR2 • End Area 2 = 0 • Radius at midpoint = R/2 • Volume =((π R2+4π(R/2)2+ 0)/ 6) * H = (π R2/3) * H http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  13. Grid Method Also known as the Borrow Pit Method • Create a grid over the area to be graded • Smaller cells → More accurate • For each grid cell • Find the average change in elevation by determining the elevation difference for all four corners of the grid cell • The volume is calculated by • Adding the averaged cut & fill volumes separately • Then multiplying by the area of one grid cell

  14. Step 1Create Grid

  15. Step 2Find Avg. Change in Elevation (existing spot) proposed spot

  16. Grid Method • Lay a grid over a drawing and determine existing/proposed grades at each node • Calculate Cut and Fill at each node • Calculate average Cut and Fill for each grid cell • Sum Cuts and Fills separately and multiply by the area of one grid http://www.ctre.iastate.edu/educweb/ce453/lectures/24%20Mass%20diagram.ppt

  17. Step 2Find Avg. Change in Elevation Vavg = (h1 + h2 + h3 + h4) / 4 Vavg = 3.5+4.4+2.6+3.3 4 Vavg = 3.45 feet of cut Repeat for each grid cell…

  18. Step 3Add Cuts/Fill Separately& Multiply by Grid Cell Area Grid Cell #1 = 3.45 feet cut Grid Cell #4 = 2.30 feet cut Grid Cell #2 = 3.48 feet cut Grid Cell #5 = 2.35 feet cut Grid Cell #3 = 2.50 feet cut Grid Cell #6 = 1.78 feet cut • Add cuts & fills separately • In this case, the site is all cut • Total of Grid Cells = 15.85 feet cut • Multiply by the Area of one Grid Cell • 15.85’(100’)(100’) = 158,500 ft3 → 5,870 yd3

  19. Grid Method The Grid Method is best used for complex grading projects and urban conditions