Sunrise Powerlink Project Update Orange County Business Council March 10, 2009

Sunrise Powerlink Project Update Orange County Business Council March 10, 2009. Project Background. Sunrise Powerlink was proposed in 2005 to provide 3 primary benefits to customers…. Improve electric system reliability Provide access to renewable energy resources in the Imperial Valley

filia
Download Presentation

Sunrise Powerlink Project Update Orange County Business Council March 10, 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sunrise Powerlink Project Update Orange County Business Council March 10, 2009

  2. Project Background Sunrise Powerlink was proposed in 2005 to provide 3 primary benefits to customers…. Improve electric system reliability Provide access to renewable energy resources in the Imperial Valley Reduce energy costs for SDG&E customers

  3. Project Description 120-mile electric transmission line from Imperial County to San Diego Project begins at the SDG&E Imperial Valley Substation, continues to a new substation southeast of Alpine, then continues north west to the SDG&E Sycamore CanyonSubstation at East Miramar Sunrise will have the capacity to carry 1,000 megawatts, enough to power 650,000 homes Project cost -- $1.8 billion

  4. Approval Process SDG&E’s application submitted to the California Public Utilities Commission (December 2005) Public hearings, environmental review, regulatory scrutiny (December 2005 to December 2008) More than 43 CPUC and SDG&E public meetings held throughout San Diego County More than 2,500 pages of official comments submitted on the 11,000-page EIR/EIS by numerous agencies and individuals CPUC and BLM approval (December 2008 and January 2009)

  5. Route Selection SDG&E submitted amended application to the CPUC proposing a Preferred Northern Route (August 2006) CPUC Commissioner Grueneich ordered a Southern Route be studied (September 2006 Public Participation Hearing and January 2007 Scoping Memo) Significant opposition to Anza Borrego Desert State Park impacts from Governor Schwarzenegger and State Parks Department and Commission CPUC and BLM certified the EIR/EIS and approved southern route (December 2008 and January 2009)

  6. Sunrise Powerlink Timeline BLM Record of Decision Jan. 2009 Route Planning Community Input 2005 CPUC Phase II Hearings April 2008 CPUC Decision Dec. 2008 Start Construction Jun. 2010 Commercial Operation Jun. 2012 CPUC Phase I Hearings June 2007 Project Application Filed Dec. 2005 2008 2007 2006 2009 2010 2012 2005 2011 • Obtain Additional Permits/Approvals • Land Acquisition • Material Purchase Final Environmental Impact Report (FEIR) Oct. 2008

  7. The California Public Utilities Commission (CPUC) approved the project by a vote of 4 to 1 on December 18, 2008 U.S. Bureau of Land Management (BLM) Record of Decision approved on January 20, 2009 Authorized budget through December 2008 is $134 million Spend through year-end 2008 was $114 million CPUC Decision Includes a project “Cost Cap” of $1.883 billion Licensing Status *MAJOR PERMITS HAVE BEEN OBTAINED *PROJECT IS WITHIN BUDGET AND PREPARED FOR EQUIPMENT PROCUREMENT

  8. Licensing Status *Additional Permits Are in Process and “Enabled” by Certification of the Environmental Impact Statement (EIS) • U.S. Forest Service “Record of Decision” • U.S. Forest Service “Plan Amendment” • Habitat Acquisition Plan • Emission Offset Acquisition, etc. *Various Legal and Regulatory Challenges Underway • Public Utilities Commission “Rehearing Requests” • State Supreme Court Challenge • Expect Federal Challenges to Occur Soon

  9. Administrative/Judicial Review Major Permits Subject to Challenge: • CPUC Final Decision • U.S. Bureau of Land Management (BLM) – Record of Decision • U.S. Fish and Wildlife Service (U.S.F.W.S.) – Biological Opinion • U.S. Forest Service (U.S.F.S.) – Record of Decision – Plan Amendment

  10. Continued Support for Sunrise • Sunrise is critical to ensuring a reliable energy supply in San Diego and Southern Orange Counties • Provides access to 1,000 megawatts of clean, renewable energy – reducing green gas house emissions • Will generate over $115 million in net benefits to customers • CPUC approval was a significant victory and critical to the success of state and national efforts to ensure a clean energy future • Together we must ensure Sunrise gets built